16 permits since 2000 (engineer on 14 permits, architect on 2 permits): 12 completed, 2 in progress, 1 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 24, 2025 | Completed final sign-off Jun 2026 | 1151 Fairfax Av | Cahill - Nibbi Joint Ventures | development of a park on lot a of final map no.9677 located between hunters view block 14(permit #201909121446) and hunters view block 17 (permit # 201909121448).the park proposes publicly accessible amenities including a play area, learning garden, multi-use lawn,bbq area, and overlook.Details
development of a park on lot a of final map no.9677 located between hunters view block 14(permit #201909121446) and hunters view block 17 (permit # 201909121448).the park proposes publicly accessible amenities including a play area, learning garden, multi-use lawn,bbq area, and overlook. | $4,000,000 |
| Dec 3, 2024 | In progress issued Apr 2025 | 850 Turk St | Cahill Contractors Llc. | demolish a one story parking garage type ia, associated construction p/a 202212087884 for a replacement apt building, dmj 06/16/2024;Details
demolish a one story parking garage type ia, associated construction p/a 202212087884 for a replacement apt building, dmj 06/16/2024; | $10,000 |
| Sep 20, 2024 | In progress issued Oct 2024 | 750 Golden Gate Av | Cahill Contractors Llc. | 100% affordable housing mayor ed 13-01: altered site permit for administrative construction type change from 1a to 1b. no change in building design as approved under site permit reference pa # 202401083599.Details
100% affordable housing mayor ed 13-01: altered site permit for administrative construction type change from 1a to 1b. no change in building design as approved under site permit reference pa # 202401083599. | |
| Apr 20, 2022 | Expired or cancelled cancelled Jan 2026 | 1379 42nd Av | Cahill Contractors Llc. | install soil nails to support neighbor's retaining wall as that neighbor can proceed with constructing new building, ref to 201912099009 (1360 43rd av) for new building shoring and excavationDetails
install soil nails to support neighbor's retaining wall as that neighbor can proceed with constructing new building, ref to 201912099009 (1360 43rd av) for new building shoring and excavation | $10,000 |
| Sep 14, 2020 | Never finaled issued Apr 2022, no final | 201 West Point Rd | Cahill-Nibbi Joint Venture | site grading for lot development & public road infrastructure. the john steward company in partnership with hope sf provides this grading permit submittal for the hunters view phase 3 public housing complex in the bayview hunters pt neighborhood. the site is located on the eastern side of middle ptDetails
site grading for lot development & public road infrastructure. the john steward company in partnership with hope sf provides this grading permit submittal for the hunters view phase 3 public housing complex in the bayview hunters pt neighborhood. the site is located on the eastern side of middle pt | $1,400,000 |
| Sep 12, 2019 | Completed final sign-off Nov 2025 | 1151 Fairfax Av | Cahill - Nibbi Joint Ventures, Mc Millan Electric | mayor dir# 13-01. 100% affordable housing. to erect 6 stories, 1 basement, type iii-a over type i-a, 42 units residential mixed used. (r-2,b,a-3,s-2) apn# 4624-033 (hunters view phase 3-block 14, lot 3); received addendum 7 (tie down), suggest concurrent review, dmj 12/27/2023;Details
mayor dir# 13-01. 100% affordable housing. to erect 6 stories, 1 basement, type iii-a over type i-a, 42 units residential mixed used. (r-2,b,a-3,s-2) apn# 4624-033 (hunters view phase 3-block 14, lot 3); received addendum 7 (tie down), suggest concurrent review, dmj 12/27/2023; | $50,000,000 |
| Oct 10, 2013 | Completed final sign-off Apr 2017 | 96 Middle Point Rd | Evans Brothers Inc, Cahill-Nibbi Joint Venture | grading the site (along with block# 4624/ lots# 31 & 32) to create building pads & streets in the redevelopmnet of hunter view housing (phase 2).Details
grading the site (along with block# 4624/ lots# 31 & 32) to create building pads & streets in the redevelopmnet of hunter view housing (phase 2). | $43,500 |
| Oct 10, 2013 | Completed final sign-off Apr 2017 | 201 West Point Rd | Evans Brothers Inc, Cahill-Nibbi Joint Venture | grading the site (along with block #4624/lots 29 & 31) to create a temporary access to west point road from middle point & a fire truck turn around for the redevelopmnet of hunter view housing (phase 2).Details
grading the site (along with block #4624/lots 29 & 31) to create a temporary access to west point road from middle point & a fire truck turn around for the redevelopmnet of hunter view housing (phase 2). | $2,000 |
| Oct 10, 2013 | Completed final sign-off Apr 2017 | 148 Middle Point Rd | Evans Brothers Inc, Cahill-Nibbi Joint Venture | grading the site (along with block 4624/lots 29 & 32) to create building pads & streets in the redevelopent of hunter view housing (phase 2)Details
grading the site (along with block 4624/lots 29 & 32) to create building pads & streets in the redevelopent of hunter view housing (phase 2) | $129,500 |
| Sep 10, 2013 | Completed final sign-off Apr 2017 | 96 Middle Point Rd | Cahill-Nibbi Joint Venture | construction placement of a perimeter temporary construction fence 10'-0" high for construction of hunters view phase 3 per plan. locks to be provided at street gate entrances.Details
construction placement of a perimeter temporary construction fence 10'-0" high for construction of hunters view phase 3 per plan. locks to be provided at street gate entrances. | $50,000 |
| Feb 28, 2013 | Completed final sign-off Apr 2014 | 52 Middle Point Rd | Cahill-Nibbi Joint Venture | revision to grading permit to document existence of fill on a portion of the site. original pa# 2010/07/22/7178. revision pa# 2011/03/02/1200.Details
revision to grading permit to document existence of fill on a portion of the site. original pa# 2010/07/22/7178. revision pa# 2011/03/02/1200. | |
| Oct 3, 2012 | Completed final sign-off Apr 2014 | 160 Acacia Av | Cahill-Nibbi Joint Venture | to document the change in lot number from 4624/004 to 4624/028 for purposes of grading permit signoff. original grading application 201007227178 and grading apps 201103021200.Details
to document the change in lot number from 4624/004 to 4624/028 for purposes of grading permit signoff. original grading application 201007227178 and grading apps 201103021200. | |
| Oct 3, 2012 | Completed final sign-off Apr 2014 | 250 Acacia Av | Cahill-Nibbi Joint Venture | to document the change in lot number from 4624/004 to 4624/027 for purposes of grading permit sign off. original grading app 201007227178 and revision 201103021200Details
to document the change in lot number from 4624/004 to 4624/027 for purposes of grading permit sign off. original grading app 201007227178 and revision 201103021200 | |
| Oct 3, 2012 | Completed final sign-off Apr 2014 | 1101 Fairfax Av | Cahill-Nibbi Joint Venture | to document the change in lot number from 4624/009 to 4624/026 for purposes of grading permit signoff. original grading application 201007227184 and revision 201103021205.Details
to document the change in lot number from 4624/009 to 4624/026 for purposes of grading permit signoff. original grading application 201007227184 and revision 201103021205. | |
| Sep 11, 2012 | Completed final sign-off Apr 2014 | 60 West Point Rd | Cahill-Nibbi Joint Venture | revision to appl #2011.0302.1205 (original appl #2010.0722.7184): replace gabion walls (retaining) with keystone walls in grading for a new private park, no structural changes.Details
revision to appl #2011.0302.1205 (original appl #2010.0722.7184): replace gabion walls (retaining) with keystone walls in grading for a new private park, no structural changes. | |
| Mar 8, 2012 | Completed final sign-off Apr 2014 | 519 Keith St | Cahill-Nibbi Joint Venture | revision to pa #201103021206 - to allow construction of an additional mse wall.Details
revision to pa #201103021206 - to allow construction of an additional mse wall. | $20,000 |