10 permits since 2000 (architect on 10 permits): 9 completed, 1 in progress.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 6, 2025 | In progress issued Feb 2026 | 1333 Bush St | Alpha Restoration & Wateproof | renovate the existing deck-roof top deck.Details
renovate the existing deck-roof top deck. | $200,000 |
| Apr 20, 2015 | Completed final sign-off Dec 2017 | 188 West Point Rd | Cahill-Nibbi Joint Venture | construction of benches, paved areas and play area for use as a park facility. (phase i final map established block/lot 4624/031 to include this area. the phase ii final map #7545 establishes this lot as 4624/056).Details
construction of benches, paved areas and play area for use as a park facility. (phase i final map established block/lot 4624/031 to include this area. the phase ii final map #7545 establishes this lot as 4624/056). | $450,000 |
| Apr 12, 2013 | Completed final sign-off Aug 2014 | 1177 California St | Paul Ryan Associates | renovation of an (e) permitted roof deck including replacing (e) surface finishes, new code complaint handrails, new led ground lighting. repair (e) waterproofing membranes & flashing & new drain connection to (e) drain line & splash blockDetails
renovation of an (e) permitted roof deck including replacing (e) surface finishes, new code complaint handrails, new led ground lighting. repair (e) waterproofing membranes & flashing & new drain connection to (e) drain line & splash block | $35,000 |
| Dec 19, 2012 | Completed final sign-off Aug 2014 | 1177 California St | Paul Ryan Associates | unit# 1717, 17th fl - renovation of condo.(n)floor, (n) wall & ceiling finishes, (n) fixts, (n) plumbing fixts, (n) kitchen appliances, (n) fireplace & (n) casework. exterior wor limited to patio including replacement of patio tile w/ stone. new guardrail will be a deferred submittal.Details
unit# 1717, 17th fl - renovation of condo.(n)floor, (n) wall & ceiling finishes, (n) fixts, (n) plumbing fixts, (n) kitchen appliances, (n) fireplace & (n) casework. exterior wor limited to patio including replacement of patio tile w/ stone. new guardrail will be a deferred submittal. | $650,000 |
| Mar 13, 2012 | Completed final sign-off Feb 2014 | 1195 Fairfax Av | Cahill-Nibbi Joint Venture | construct a new privately owned park ( as part of the hunter's view development.)Details
construct a new privately owned park ( as part of the hunter's view development.) | $400,000 |
| Mar 13, 2012 | Completed final sign-off Feb 2014 | 1190 Fairfax Av | Cahill-Nibbi Joint Venture | construct a new privately owned park ( as part of the hunter's view development.)Details
construct a new privately owned park ( as part of the hunter's view development.) | $100,000 |
| Mar 13, 2012 | Completed final sign-off Feb 2014 | 1151 Fairfax Av | Cahill-Nibbi Joint Venture | construct a new privately owned park ( as part of the hunter's view development.)Details
construct a new privately owned park ( as part of the hunter's view development.) | $1,000,000 |
| Jan 27, 2011 | Completed final sign-off Apr 2014 | 98 West Point Rd | construction of a concrete wallway (to connect the new hunters view development to cashmere street) on theree parcels-to provide handicap accessble pedestrian acces.Details
construction of a concrete wallway (to connect the new hunters view development to cashmere street) on theree parcels-to provide handicap accessble pedestrian acces. | $100,000 | |
| Jan 27, 2011 | Completed final sign-off Apr 2014 | 1 Cashmere St | construction of a concrete wallway (to connect the new hunters view development to cashmere street) on three parcels-to provide handicap accessble pedestrian access.Details
construction of a concrete wallway (to connect the new hunters view development to cashmere street) on three parcels-to provide handicap accessble pedestrian access. | $50,000 | |
| Jan 27, 2011 | Completed final sign-off Apr 2014 | 1 Cashmere St | construction of a concrete wallway (to connect the new hunters view development to cashmere street) on three parcels-to provide handicap accessble pedestrian access.Details
construction of a concrete wallway (to connect the new hunters view development to cashmere street) on three parcels-to provide handicap accessble pedestrian access. | $50,000 |