- Feb 2019 to Jul 2024
9 permits since 2000 (engineer on 9 permits): 4 completed, 3 in progress, 2 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jul 5, 2024 | In progress issued Oct 2024 | 2350 Noriega St | Teracom Services Llc | ref pa# 2023-0607-9503 installation of 1 chain link fence lid placed on top of existing trek fence enclosure and door lock upgrade to be installed on the enclosed doorDetails
ref pa# 2023-0607-9503 installation of 1 chain link fence lid placed on top of existing trek fence enclosure and door lock upgrade to be installed on the enclosed door | $25,000 |
| Jul 5, 2024 | In progress issued Oct 2024 | 4210 Ocean Av | Teracom Services Llc | ref pa# 2023-0608-9589 installation of chain link fence lid placed on top of existing trek fence enclosure and door lock upgrade to be installed on the enclosed door ref pa 202306089589Details
ref pa# 2023-0608-9589 installation of chain link fence lid placed on top of existing trek fence enclosure and door lock upgrade to be installed on the enclosed door ref pa 202306089589 | $25,000 |
| Jun 6, 2024 | In progress issued Oct 2024 | 1335 Webster St | Teracom Services Llc | maintenance/upgrade: installation of 1-chain-link fence lid, placed on top of existing trek fence enclosure and door lock upgrade to be installed on the enclosure door. ref pa# 202306079484.Details
maintenance/upgrade: installation of 1-chain-link fence lid, placed on top of existing trek fence enclosure and door lock upgrade to be installed on the enclosure door. ref pa# 202306079484. | $25,000 |
| Jun 6, 2024 | Completed final sign-off Dec 2025 | 3350 Mission St | Tricom Networks Inc | maintenance/upgrade installation of (1) chain-link fence lid, placed on top of existing trek fence enclosure & door lock upgrade to be installed on the enclosure doors. ref 202103186858. btc equipment and power units. remove 3 power units & 3 dispensers and replace with 2 power units & 3 dispensersDetails
maintenance/upgrade installation of (1) chain-link fence lid, placed on top of existing trek fence enclosure & door lock upgrade to be installed on the enclosure doors. ref 202103186858. btc equipment and power units. remove 3 power units & 3 dispensers and replace with 2 power units & 3 dispensers | $100,000 |
| Mar 18, 2021 | Completed final sign-off Aug 2021 | 3350 Mission St | Preferred Power Solutions Inc | ev: upgrade (e) ev dispensers. install (3) 175kw power gen units. remove & replace concrete pad as needed, same size. install (3) new dispensers with bollards. remove (e) unnecessary bollards. install light.Details
ev: upgrade (e) ev dispensers. install (3) 175kw power gen units. remove & replace concrete pad as needed, same size. install (3) new dispensers with bollards. remove (e) unnecessary bollards. install light. | $90,000 |
| Aug 8, 2020 | Expired or cancelled cancelled Jul 2024 | 1335 Webster St | the project proposes to install a battery energy storage system(bess) inside the equipment pad of the extg electric vehicle charging station.Details
the project proposes to install a battery energy storage system(bess) inside the equipment pad of the extg electric vehicle charging station. | $25,000 | |
| Apr 30, 2019 | Completed final sign-off Apr 2020 | 1335 Webster St | Preferred Power Solutions Inc | install 1 utility transformer, 1 switchboard assembly, 3 (150kw) btc power units, 3 (150kw) btc dispensers, 1 level 2 chargerDetails
install 1 utility transformer, 1 switchboard assembly, 3 (150kw) btc power units, 3 (150kw) btc dispensers, 1 level 2 charger | $100,000 |
| Apr 9, 2019 | Completed final sign-off Jun 2020 | 2350 Noriega St | Cupertino Electric Inc. | install one utility transformer, 1 switchboard assembly, 4 150 kw btc power units, 4 150 kw btc dispensers.Details
install one utility transformer, 1 switchboard assembly, 4 150 kw btc power units, 4 150 kw btc dispensers. | $100,000 |
| Feb 12, 2019 | Expired or cancelled withdrawn Apr 2019 | 1201 Bryant St | addition of electric vehicle charging station to(e)parking lot. installation includes: (1)utility transformer, (1)400a service switchboard, (2) 2000a remote switchboards, (3)pedestrian lightpoles & fixtures, (3)lighting fixtures/wall mounted, (15)50kw terra abb ev chargers, (5)fusible disconnects.Details
addition of electric vehicle charging station to(e)parking lot. installation includes: (1)utility transformer, (1)400a service switchboard, (2) 2000a remote switchboards, (3)pedestrian lightpoles & fixtures, (3)lighting fixtures/wall mounted, (15)50kw terra abb ev chargers, (5)fusible disconnects. | $245,000 |