David Gim Fong
- Listed as
- architect, designer
- Firm
- Fong & Chan
- Based in
- San Francisco
- On San Francisco permits
- Sep 2011 to Aug 2016
3 permits since 2000 (architect on 2 permits, designer on 1 permit): 3 completed.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 25, 2016 | Completed final sign-off Mar 2018 | 1400 Geary Bl | Dome Construction Corp | level b - laundry reconstruction project: renovate (e) storage room & office area into new commercial laundry facility w/assoc clean soiled linen room. an addition of epo switches & trench drains to an (e) ele room. fire alarm and sprinkler system revisions under separate applicationDetails
level b - laundry reconstruction project: renovate (e) storage room & office area into new commercial laundry facility w/assoc clean soiled linen room. an addition of epo switches & trench drains to an (e) ele room. fire alarm and sprinkler system revisions under separate application | $200,000 |
| Dec 23, 2013 | Completed final sign-off Jul 2015 | 1400 Geary Bl | Dome Construction Corp | utility upgrade:(e)elec. service + equip demo'd & replace(e)main switches & main switch board;(n)electrical room @ basement level;(n)circuit breaker class switch boards;(n)plug in bus riser 3rd thru 25th floors; decommisioning of(e)laundry room/basement converting to sotrage use.Details
utility upgrade:(e)elec. service + equip demo'd & replace(e)main switches & main switch board;(n)electrical room @ basement level;(n)circuit breaker class switch boards;(n)plug in bus riser 3rd thru 25th floors; decommisioning of(e)laundry room/basement converting to sotrage use. | $3,200,000 |
| Sep 14, 2011 | Completed final sign-off Oct 2013 | 1400 Geary Bl | Gonsalves & Stronck Construction Co. | renovation and refurbishing of bedrooms,toilets, shared program spaces, staff areas and corridors on the mezzanine and third floors of existing 26 story steel and concrete bldg. project also includes the renovation of existing construction in and around a large mechanical shaft on the mezz. & 3rd flDetails
renovation and refurbishing of bedrooms,toilets, shared program spaces, staff areas and corridors on the mezzanine and third floors of existing 26 story steel and concrete bldg. project also includes the renovation of existing construction in and around a large mechanical shaft on the mezz. & 3rd fl | $3,800,000 |