Eric C Taylor
- License
- M38663
- Mechanical engineer
- About the Board for Professional Engineers, Land Surveyors, and Geologists
- Look up M38663 at the Board for Professional Engineers
- Listed as
- engineer
- On San Francisco permits
- Sep 2019 to Dec 2019
3 permits since 2000 (engineer on 3 permits): 2 completed, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records
Worked with
Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.
- Contractors
- Jorgensen-Reeve Builders (2), Michilli Inc
- Architects
- David D. Montalba (2)
- Engineers
- Nicholas Decoster (2), Craig Chamberlain
Where they worked
- Single-family 0
- Multi-family (2-family, apartments) 0
- Commercial 0
- Other or unknown 3
One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 19, 2019 | Completed final sign-off Dec 2021 | 1500 Mission St | Jorgensen-Reeve Builders | rev to pa201905039670 - interior non-structural partiion configuration & assocated mep.Details
rev to pa201905039670 - interior non-structural partiion configuration & assocated mep. | |
| Nov 26, 2019 | Never finaled issued Nov 2019, no final | 50 Beale St | Michilli Inc | floors 1,2.3: rev to pa201809129843 - clarify labeling on fire fight control panel and sequences of operation to show compliance with smoke controle narrative. maher n/a.Details
floors 1,2.3: rev to pa201809129843 - clarify labeling on fire fight control panel and sequences of operation to show compliance with smoke controle narrative. maher n/a. | |
| Sep 9, 2019 | Completed final sign-off Jan 2020 | 1543 Mission St | Jorgensen-Reeve Builders | temporary ti within an existing building to be used as pre-sales showroomDetails
temporary ti within an existing building to be used as pre-sales showroom | $330,000 |