19 permits since 2000 (architect on 19 permits): 17 completed, 2 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 7, 2023 | Completed final sign-off Mar 2025 | 947 Green St | Alpha Restoration & Wateproof | remove failed coatings from exterior as req. concrete repair, seal, flash, repaint e window frames. per drawings replace e wood sashes in kind. per drawings replace e aluminum window inserts in kind. where indicated restore e wood window frames and sashes. replace pigeon screens. new waterproof coatDetails
remove failed coatings from exterior as req. concrete repair, seal, flash, repaint e window frames. per drawings replace e wood sashes in kind. per drawings replace e aluminum window inserts in kind. where indicated restore e wood window frames and sashes. replace pigeon screens. new waterproof coat | $175,000 |
| Dec 19, 2022 | Completed final sign-off Aug 2023 | 2355 Scott St | Sure, Inc. | replace (e) door and window and provide waterproofing on the back of the bldg facing rear yard. install new fluid appied air barrier to walls & rough opening. (n) sheet metal windows pans & accociated liquid applied flashing & sealant joints. (n) wood trim & cladding match (e). no changes to mechDetails
replace (e) door and window and provide waterproofing on the back of the bldg facing rear yard. install new fluid appied air barrier to walls & rough opening. (n) sheet metal windows pans & accociated liquid applied flashing & sealant joints. (n) wood trim & cladding match (e). no changes to mech | $25,000 |
| Aug 4, 2022 | Never finaled issued Oct 2023, no final | 99 Saint Germain Av | Picone Renovations | install a new dumbwaiter elevator incluidng all structural supports as needed. add structurally reinfored concrete retaining wall and infill concrete slab. replace stucco wall below stairs, waterproofing over mechanical room and tile replacement as needed.area drains. plans traveling w/ 202208039878Details
install a new dumbwaiter elevator incluidng all structural supports as needed. add structurally reinfored concrete retaining wall and infill concrete slab. replace stucco wall below stairs, waterproofing over mechanical room and tile replacement as needed.area drains. plans traveling w/ 202208039878 | $192,500 |
| Aug 4, 2022 | Never finaled issued Oct 2023, no final | 95 Saint Germain Av | Picone Renovations | install a new dumbwaiter elevator incluidng all structural supports as needed. add structurally reinfored concrete retaining wall and infill concrete slab. replace stucco wall below stairs, waterproofing over mechanical room and tile replacement as needed.area drains. plans traveling w/ 202208039876Details
install a new dumbwaiter elevator incluidng all structural supports as needed. add structurally reinfored concrete retaining wall and infill concrete slab. replace stucco wall below stairs, waterproofing over mechanical room and tile replacement as needed.area drains. plans traveling w/ 202208039876 | $192,500 |
| Jun 8, 2022 | Completed final sign-off Jun 2023 | 730 Sacramento St | Everest Waterproofing & Restoration Inc. | concrete repair of deck and facade in-kind. repair to steel balcony in-kind. waterproof coating on balcony.Details
concrete repair of deck and facade in-kind. repair to steel balcony in-kind. waterproof coating on balcony. | $55,000 |
| May 17, 2022 | Completed final sign-off Feb 2024 | 733 Front St | Saarman Construction,Ltd. | add new janitor room and ada bathroom.Details
add new janitor room and ada bathroom. | $100,000 |
| May 8, 2019 | Completed final sign-off Mar 2021 | 19 Presidio Tr | Scott & Warner Builders Inc | ref app#201903125033 acoustic remedation per attached plans. n/a for maherDetails
ref app#201903125033 acoustic remedation per attached plans. n/a for maher | $1,250,000 |
| Jan 19, 2018 | Completed final sign-off Sep 2018 | 1407 Montgomery St | Saarman Construction,Ltd. | repair and remodel bathroom, add laundry and sink in spaceDetails
repair and remodel bathroom, add laundry and sink in space | $12,000 |
| Jan 19, 2018 | Completed final sign-off Oct 2018 | 1407 Montgomery St | Saarman Construction,Ltd. | repair water damage at north wall. replace/upgrade water barrier; replace kitchen & bedroom windows in kind. not visible from st. front bldg 3 unitsDetails
repair water damage at north wall. replace/upgrade water barrier; replace kitchen & bedroom windows in kind. not visible from st. front bldg 3 units | $100,000 |
| Oct 20, 2017 | Completed final sign-off Apr 2019 | 1090 Chestnut St | Giampolini & Co., Inc | project consists of repairing concrete facades, stripping existing coatings, new elastometric coating , removing existing wood double hung windows, installing new wood windows.repair decorative concrete ornaments at cornice or replace inkind. repair (e) metal works & grills.maher n/a.Details
project consists of repairing concrete facades, stripping existing coatings, new elastometric coating , removing existing wood double hung windows, installing new wood windows.repair decorative concrete ornaments at cornice or replace inkind. repair (e) metal works & grills.maher n/a. | $125,000 |
| May 4, 2017 | Completed final sign-off Sep 2020 | 198 Potrero Av | Plant Construction Co, Lp | change of use from restaurant(partial 2nd fl) to legitimize (e) office. exterior upgrades, demo include remove exterior door, fire escape, sidewalk, roof, deck & stair, skylights. accessible entrance, service door, deck, stair & rr upgrade strengthen roof frame. (2nd fl occupied, 1st & mezDetails
change of use from restaurant(partial 2nd fl) to legitimize (e) office. exterior upgrades, demo include remove exterior door, fire escape, sidewalk, roof, deck & stair, skylights. accessible entrance, service door, deck, stair & rr upgrade strengthen roof frame. (2nd fl occupied, 1st & mez | $300,000 |
| May 13, 2016 | Completed final sign-off May 2018 | 1001 California St | revision to pa #201503302223: roof - repair sheet metal cornice with waterproofing, replace existing failing skylight with structural infill, install new sheathing, drain waterproof to cornice roof.Details
revision to pa #201503302223: roof - repair sheet metal cornice with waterproofing, replace existing failing skylight with structural infill, install new sheathing, drain waterproof to cornice roof. | ||
| Jul 6, 2015 | Completed final sign-off May 2018 | 926 Grove St | Axis Construction | common area. repair siding as needed 50%. 500 sq ft siding in kind (like to like) under roof new deck coating at deck. remove and replace tile. no replacement of windows. do window tune up at all wnidows.Details
common area. repair siding as needed 50%. 500 sq ft siding in kind (like to like) under roof new deck coating at deck. remove and replace tile. no replacement of windows. do window tune up at all wnidows. | $500,000 |
| Mar 30, 2015 | Completed final sign-off May 2018 | 1001 California St | common area- repairs to existing concrete balustrade, stucco repairs, concrete rehabilitation, replacement of roof top terrace tile, new terrace guardrailDetails
common area- repairs to existing concrete balustrade, stucco repairs, concrete rehabilitation, replacement of roof top terrace tile, new terrace guardrail | $500,000 | |
| Aug 6, 2014 | Completed final sign-off Apr 2015 | 433 Collingwood St | Wall Construction | replacement of existing siding and stucco, repair decks, reflashing windowsDetails
replacement of existing siding and stucco, repair decks, reflashing windows | $573,000 |
| Apr 4, 2014 | Completed final sign-off Feb 2015 | 945 Green St | Alpha Restoration & Wateproof | add work to breezeway and service entry. demo and reconstruction including fountainDetails
add work to breezeway and service entry. demo and reconstruction including fountain | $115,500 |
| Jul 30, 2012 | Completed final sign-off Apr 2014 | 945 Green St | Alpha Restoration & Wateproof, Scaffold Soultions Inc. | phase 1, exterior work only - paint removal abatement, minor concrete repair, exterior coating, painting, partial window replacement.Details
phase 1, exterior work only - paint removal abatement, minor concrete repair, exterior coating, painting, partial window replacement. | $604,000 |
| Jun 6, 2012 | Completed final sign-off Jul 2012 | 2685 Pacific Av | Paul Ryan Associates | remove existing skylight in kitchen bay, new roof over existing kitchen bay (52sf). remove and replace (e) rough openings to match (1) door and (3) sidelight. new (3) led lights in ceiling of kitchen bayDetails
remove existing skylight in kitchen bay, new roof over existing kitchen bay (52sf). remove and replace (e) rough openings to match (1) door and (3) sidelight. new (3) led lights in ceiling of kitchen bay | $65,000 |
| Jan 22, 2007 | Completed final sign-off Jan 2007 | 85 Mountain Spring Av | Thompson Brooks Inc. | for final inspectio of app #2005/12/08/9844Details
for final inspectio of app #2005/12/08/9844 |