Permit GraphShortlistSan Francisco building permits since 2000

Permit 202610199584

88 Spear St

9th fl - deferred mep to pa 202610028988

Outcome
In progress (city status: issued, Oct 23, 2026)
Filed
Oct 19, 2026
Permit issued
Oct 23, 2026
Declared cost
$766,000
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Principal Builders Inc. (license 829808)
Property
All permits at this address (block 3712, lot 023)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Principal Builders Inc. (license 829808)
Engineer
Bradley Hollub, Randall Lamb Assoc (license M33234)
Engineer
Dean Macy (license E24383)
Engineer
Ivano Russo (license M34415)
Pmt consultant/expediter
David Lu, Gary Bell & Associates Inc. (no license listed), applicant