Permit GraphShortlistSan Francisco building permits since 2000

Permit 201911147259

345 California St

15th and 20th floor: electrical av upgrades to 7 locations. paint and carpet upgrades in noted locations. restrooms to have ada partition upgrades. ada stall on 2oth floor. to recieve upgraded toilet.

Outcome
Completed (city status: complete, Jun 24, 2020)
Filed
Nov 14, 2019
Permit issued
Dec 18, 2019
Final sign-off
Jun 24, 2020
Declared cost
$280,000
Building use
office
Neighborhood
Financial District/South Beach (how long permits take there)
Contractor
Dpr Construction (license 953749)
Property
All permits at this address (block 0261, lot 017)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Dpr Construction (license 953749), applicant
Architect
John Workley, Vocon Partners (license C30605)