Permit 201605137352
121 Spear St
2nd floor - restroom barrier removal, replace plumbing fixtures & configure to meet current accessibility requirements. mep, fire sprinkler and life safety to be design-build and under separate submittals.
- Outcome
- Completed (city status: complete, Sep 1, 2016)
- Filed
- May 13, 2016
- Permit issued
- May 18, 2016
- Final sign-off
- Sep 1, 2016
- Declared cost
- $55,000
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- Peacock Construction (license 423901)
- Property
- All permits at this address (block 3716, lot 021)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Peacock Construction (license 423901), applicant
- Architect
- Pamela Robinson, Smithgroup (license C25429)