Permit 201603152071
201 03rd St
ada hardship technical infeasibility request. existing clearance between core wall & structural column does not allow 44" clearance. ref pa 2015-0806-3509
- Outcome
- Completed (city status: complete, Mar 21, 2019)
- Filed
- Mar 15, 2016
- Permit issued
- Mar 16, 2016
- Final sign-off
- Mar 21, 2019
- Building use
- office
- Neighborhood
- Financial District/South Beach (how long permits take there)
- Contractor
- Gci, Inc (license 689958)
- Property
- All permits at this address (block 3735, lot 059)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Gci, Inc (license 689958)