Permit GraphSan Francisco building permits since 2000

Permit 201404173555

200 Paul Av

1st and 2nd floor:t.i. for electrical rooms. new data center area, common area, electrical support area, new concrete pads for generators, installtion of 2 new generators.n/a for the maher ordinance #155-13

Outcome
Completed (city status: complete, Jan 23, 2015)
Filed
Apr 17, 2014
Permit issued
Aug 1, 2014
Final sign-off
Jan 23, 2015
Declared cost
$5,300,000
Building use
office
Neighborhood
Bayview Hunters Point
Contractor
Skyline Construction (license 727637)
Property
All permits at this address (block 5431A, lot 001F)