Permit 201404173555
200 Paul Av
1st and 2nd floor:t.i. for electrical rooms. new data center area, common area, electrical support area, new concrete pads for generators, installtion of 2 new generators.n/a for the maher ordinance #155-13
- Outcome
- Completed (city status: complete, Jan 23, 2015)
- Filed
- Apr 17, 2014
- Permit issued
- Aug 1, 2014
- Final sign-off
- Jan 23, 2015
- Declared cost
- $5,300,000
- Building use
- office
- Neighborhood
- Bayview Hunters Point
- Contractor
- Skyline Construction (license 727637)
- Property
- All permits at this address (block 5431A, lot 001F)