Permit 201301077328
200 Paul Av
revision to consist of reconfiguration of the new entrance into the data center and relocation of one crac unit. ref app#201202174415
- Outcome
- Completed (city status: complete, May 16, 2017)
- Filed
- Jan 7, 2013
- Permit issued
- Jan 9, 2013
- Final sign-off
- May 16, 2017
- Building use
- office
- Neighborhood
- Bayview Hunters Point (how long permits take there)
- Contractor
- Skyline Construction (license 727637)
- Property
- All permits at this address (block 5431A, lot 001F)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Skyline Construction (license 727637), applicant
- Lessee
- Digital Realty Digital Realty (no license listed)