Permit 200912173381
300 Clay St
11th floor-build one new office, one large office wall be divided into two smaller offices located on the east side of bldg. in addition the wall located on the e.side of 11.47 storage will be changed to 1-hr rated constr, add a door to 11.24 server room,mep,fire/life safety under separate permit.
- Outcome
- Completed (city status: complete, Jul 9, 2010)
- Filed
- Dec 17, 2009
- Permit issued
- Jan 7, 2010
- Final sign-off
- Jul 9, 2010
- Declared cost
- $30,000
- Building use
- office
- Neighborhood
- Financial District/South Beach
- Contractor
- Plant Construction Company Lp (license 830764)
- Property
- All permits at this address (block 0204, lot 021)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Plant Construction Company Lp (license 830764)
- Architect
- Mark Horton, Mark Horton Architecture (license C018065)