Permit 200712190892
500 Washington St
5th and 6th floor ti. interior demolition and construction of new non-structural demising walls throughout. new restrooms. hvac, electrical and life safety work will be done under separate permit
- Outcome
- Completed (city status: complete, Nov 19, 2008)
- Filed
- Dec 19, 2007
- Permit issued
- Dec 20, 2007
- Final sign-off
- Nov 19, 2008
- Declared cost
- $700,000
- Building use
- office
- Neighborhood
- Chinatown (how long permits take there)
- Contractor
- None listed with a license number
- Property
- All permits at this address (block 0196, lot 023)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Architect
- Melissa Pesci, Hammel, Green & Abrahamson (license C32725)
- Pmt consultant/expediter
- Lori Thompson, Pamela Harris****** (no license listed), applicant