Western Allied Corp.

Contractor license
312875
State license record
Based in
Menlo Park
On San Francisco permits
Apr 2001 to Jul 2003
Last 24 months
0 permits filed

6 permits since 2000: 6 completed.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywideThis contractor’s finished permits

Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.

Most recent permits

All
FiledOutcomeAddressWork described on the permitDeclared cost
Jul 23, 2003Completed
final sign-off Jun 2004
111 Pine Stinstall a new ventilation system for the (e) chiller room per cmc section 1108
Details
Permit
200307230209
Status
complete
Filed
Jul 23, 2003
Permit issued
Oct 1, 2003
Final sign-off
Jun 16, 2004
Declared cost
$100,000
Address
111 Pine St

install a new ventilation system for the (e) chiller room per cmc section 1108

Open the permit page

$100,000
Jun 26, 2003Completed
final sign-off Oct 2003
725 Irving Stremove built up hvac system equipment & replace with one new rooftop package unit & new furnace/spli
Details
Permit
200306268057
Status
complete
Filed
Jun 26, 2003
Permit issued
Aug 27, 2003
Final sign-off
Oct 28, 2003
Declared cost
$60,000
Address
725 Irving St

remove built up hvac system equipment & replace with one new rooftop package unit & new furnace/spli

Open the permit page

$60,000
Jul 30, 2002Completed
final sign-off Jun 2003
350 Parnassus Avrevise to appln #200204012736 new 1-hr and wall between chiller room and boiler room
Details
Permit
200207302642
Status
complete
Filed
Jul 30, 2002
Permit issued
Jul 30, 2002
Final sign-off
Jun 26, 2003
Address
350 Parnassus Av

revise to appln #200204012736 new 1-hr and wall between chiller room and boiler room

Open the permit page

Apr 1, 2002Completed
final sign-off Jun 2003
350 Parnassus Avreplace existing boiler w/(n) boiler in same location
Details
Permit
200204012736
Status
complete
Filed
Apr 1, 2002
Permit issued
Apr 12, 2002
Final sign-off
Jun 26, 2003
Declared cost
$103,000
Address
350 Parnassus Av

replace existing boiler w/(n) boiler in same location

Open the permit page

$103,000
Mar 28, 2002Completed
final sign-off Sep 2002
3027 16th Streplace (e) hvac system with 2 new rooftop package units.coordinate and reinforce roof framing.
Details
Permit
200203282527
Status
complete
Filed
Mar 28, 2002
Permit issued
Mar 28, 2002
Final sign-off
Sep 5, 2002
Declared cost
$73,490
Address
3027 16th St

replace (e) hvac system with 2 new rooftop package units.coordinate and reinforce roof framing.

Open the permit page

$73,490
Apr 24, 2001Completed
final sign-off May 2002
180 Howard Strepl in kind 2 chillers,their associated cooling towers,2 auxilliary condenser
Details
Permit
200104247620
Status
complete
Filed
Apr 24, 2001
Permit issued
Apr 24, 2001
Final sign-off
May 20, 2002
Declared cost
$748,000
Address
180 Howard St

repl in kind 2 chillers,their associated cooling towers,2 auxilliary condenser

Open the permit page

$748,000