Svala Construction Inc
- Based in
- San Francisco
- On San Francisco permits
- Feb 2003 to Jan 2026
- Last 24 months
- 4 permits filed
15 permits since 2000: 14 completed, 1 never finaled.
Of the 1 never-finaled permit, 1 is over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jan 30, 2026 | Completed final sign-off Mar 2026 | 100 Larkin St | revision to 202512192263. removal of 3 of the 5 originally permitted safety floor grilles.Details
revision to 202512192263. removal of 3 of the 5 originally permitted safety floor grilles. | $15,000 |
| Dec 19, 2025 | Completed final sign-off Mar 2026 | 100 Larkin St | installation of safety floor grilles at selected floor openings on 3rd and 4th floor of main library. floor grilles are a safety measure to prevent people from jumping off the (e) guard rails.Details
installation of safety floor grilles at selected floor openings on 3rd and 4th floor of main library. floor grilles are a safety measure to prevent people from jumping off the (e) guard rails. | $175,000 |
| Dec 9, 2025 | Completed final sign-off Apr 2026 | 100 Larkin St | laminated glass safety barriers will be bolted to the existing metal guardrailsDetails
laminated glass safety barriers will be bolted to the existing metal guardrails | $490,000 |
| Dec 9, 2025 | Completed final sign-off Apr 2026 | 100 Larkin St | 3rd & 4th fl - installation of laminated glass safety barriers around the central curved atrium floor opening at the 3rd & 4th fl of the main library. laminated glass safety barriers will be bolted to the existing metal guardrails.Details
3rd & 4th fl - installation of laminated glass safety barriers around the central curved atrium floor opening at the 3rd & 4th fl of the main library. laminated glass safety barriers will be bolted to the existing metal guardrails. | $180,000 |
| May 9, 2023 | Completed final sign-off Jun 2023 | 101 Horne Av | permit ref# 201912300885 - 2nd floor studio, 150 sq ft. during the construction of the above ref permitted project, a small electrical fire damaged an artist studio. dbi inspector michael gunnell inspector the damage and approved a no plans required correct report- like for like repairs. stud, roofDetails
permit ref# 201912300885 - 2nd floor studio, 150 sq ft. during the construction of the above ref permitted project, a small electrical fire damaged an artist studio. dbi inspector michael gunnell inspector the damage and approved a no plans required correct report- like for like repairs. stud, roof | $40,000 |
| Dec 19, 2019 | Completed final sign-off Jan 2021 | 2186 Geary Bl | install 2 new doors and remodeling 2-3 foot wide wallsDetails
install 2 new doors and remodeling 2-3 foot wide walls | $2,000 |
| Jun 19, 2019 | Completed final sign-off Mar 2022 | 2868 Mission St | priority project - voluntary interior toilet rooms, barrier removal and finishes replacement, minor barrier removal and finishes replacement, passenger elevator modernization, freight elevator replacement with service elevator. provide bottle filling station.Details
priority project - voluntary interior toilet rooms, barrier removal and finishes replacement, minor barrier removal and finishes replacement, passenger elevator modernization, freight elevator replacement with service elevator. provide bottle filling station. | $950,000 |
| Oct 1, 2018 | Completed final sign-off Apr 2019 | 99 Grove St | install neon artwork along western elevation of bill graham civic auditorium. penetrations limited to existing grout lines. subject to hpc motion no. 0325 and conditions of approval contained therein.Details
install neon artwork along western elevation of bill graham civic auditorium. penetrations limited to existing grout lines. subject to hpc motion no. 0325 and conditions of approval contained therein. | $300,000 |
| Apr 27, 2018 | Completed final sign-off Aug 2018 | 901 Presidio Av | barrier removal at 1 existing mens restroom and repair of exhaust fan. new plumbing fixtures. toilet partitions, and toilet accessories and finishesDetails
barrier removal at 1 existing mens restroom and repair of exhaust fan. new plumbing fixtures. toilet partitions, and toilet accessories and finishes | $244,000 |
| Mar 21, 2016 | Completed final sign-off Jun 2016 | 356 07th St | revision for permit 201406279877: revise main entry ramp, landing and maintenace room as requested by client due to operational changes and site conditions. maher n/aDetails
revision for permit 201406279877: revise main entry ramp, landing and maintenace room as requested by client due to operational changes and site conditions. maher n/a | $10,000 |
| Aug 31, 2007 | Completed final sign-off Dec 2008 | 163 Collingwood St | install autosprinkler in new apt.Details
install autosprinkler in new apt. | $28,400 |
| Oct 25, 2004 | Completed final sign-off Oct 2004 | 1349 Taraval St | field rev. to pa 2003/12/01/1330 - enlarge h..c. bathroomDetails
field rev. to pa 2003/12/01/1330 - enlarge h..c. bathroom | |
| Mar 1, 2004 | Completed final sign-off Oct 2004 | 1349 Taraval St | relocate bathrooms reference approved drawings app #2003/12/01/1330Details
relocate bathrooms reference approved drawings app #2003/12/01/1330 | $100 |
| Dec 1, 2003 | Never finaled issued Dec 2003, no final | 1349 Taraval St | renovate and provide tenant improvements to the existing commercial spacee at the groundfloor levelDetails
renovate and provide tenant improvements to the existing commercial spacee at the groundfloor level | $20,000 |
| Feb 27, 2003 | Completed final sign-off Mar 2003 | 2320 Sutter St | relocate 9 doors, remove existing and install new partitionsDetails
relocate 9 doors, remove existing and install new partitions | $2,000 |