Stapleton Construction Dba Revival Const
- Based in
- Oakland
- On San Francisco permits
- Aug 2016 to Apr 2018
- Last 24 months
- 0 permits filed
9 permits since 2000: 6 completed, 3 never finaled.
Of the 3 never-finaled permits, 2 are 5 to 10 years old, 1 is over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Deck permits
1 deck permit: 1 completed. Typically 273 days from filing to permit and 470 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Sep 19, 2016 | Completed final sign-off Oct 2018 | 219 Douglass St | horizontal addition (+224 sf) ground floor at rear of house with 2nd level deck above. no work at front. added room to be a bedroom.Details
horizontal addition (+224 sf) ground floor at rear of house with 2nd level deck above. no work at front. added room to be a bedroom. | $100,000 |