Speedy Building And Construction
- Based in
- San Francisco
- On San Francisco permits
- Oct 2019 to Sep 2026
- Last 24 months
- 20 permits filed
48 permits since 2000: 29 completed, 13 in progress, 3 never finaled, 3 expired or cancelled.
Of the 3 never-finaled permits, 3 are 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for roof deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Roof deck permits
3 roof deck permits: 2 completed, 1 never finaled. Typically 157 days from filing to permit and 561 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Oct 24, 2022 | Completed final sign-off Aug 2024 | 581 Ivy St | relocate kitchen and bedrooms. remodel 1st floor bath. add full bath to 2nd floor. add washer and dryer. install (2) new sliding doors from bedrooms to exterior alley. replace roof. replace foundation. seismic upgrade. upgrade roof for future roof deck filed under separate permit pa# 202210245010.Details
relocate kitchen and bedrooms. remodel 1st floor bath. add full bath to 2nd floor. add washer and dryer. install (2) new sliding doors from bedrooms to exterior alley. replace roof. replace foundation. seismic upgrade. upgrade roof for future roof deck filed under separate permit pa# 202210245010. | $100,000 |
| Oct 24, 2022 | Completed final sign-off Aug 2024 | 581 Ivy St | new 360 sq.ft. roof deck. add stair from 2nd floor to (n) roof deck.Details
new 360 sq.ft. roof deck. add stair from 2nd floor to (n) roof deck. | $50,000 |
| Apr 8, 2022 | Never finaled issued Sep 2022, no final | 3646 Baker St | addition of new rooftop deck.Details
addition of new rooftop deck. | $30,000 |