Permit GraphShortlistSan Francisco building permits since 2000

Oudi Construction Dba Audi Construction

Contractor license
922802
State license record
Based in
San Francisco
On San Francisco permits
Jun 2008 to Sep 2026
Last 24 months
11 permits filed

27 permits since 2000: 13 completed, 7 in progress, 5 never finaled, 2 expired or cancelled.

Of the 5 never-finaled permits, 3 are 3 to 5 years old, 2 are 5 to 10 years old.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywideThis contractor’s finished permits

Each point is the quarter the permits were filed, for bathroom remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.

Where they worked

One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.

Bathroom remodel permits

AllStairs 1Kitchen remodel 9Bathroom remodel 14

14 bathroom remodel permits: 7 completed, 4 in progress, 2 never finaled, 1 expired or cancelled. Typically 4 days from filing to permit and 162 days from permit to final inspection.

FiledOutcomeAddressWork described on the permitDeclared cost
Sep 24, 2026In progress
issued Sep 2026
149 Anderson Stadd a bathroom to the basement.
Details
Permit
202609248550
Permit issued
Sep 30, 2026

add a bathroom to the basement.

Open the permit page

$150,000
Jul 1, 2026In progress
issued Jul 2026
3895 Clay Sttotal kitchen remodeling and total bathroom remodeling in kind. new cabinets, new counter tops & new flooring. for the bathroom new flooring, new fixtures
Details
Permit
202607014441
Permit issued
Jul 1, 2026

total kitchen remodeling and total bathroom remodeling in kind. new cabinets, new counter tops & new flooring. for the bathroom new flooring, new fixtures

Open the permit page

$25,000
Dec 1, 2025Completed
final sign-off Jun 2026
163 Moffitt Stlegalize 1st fl office to be converted to master bed. install new master closet & master bath at 1st fl. remove (e) wall between kitchen & living room. rehabilitate existing kitchen.
Details
Permit
202512010669
Permit issued
Dec 11, 2025
Final sign-off
Jun 15, 2026

legalize 1st fl office to be converted to master bed. install new master closet & master bath at 1st fl. remove (e) wall between kitchen & living room. rehabilitate existing kitchen.

Open the permit page

$60,000
Apr 18, 2025In progress
issued Apr 2025
781 11th Avrevision to permit 202503101937 to include patch sheet rpck & tile to hallway, living room, dining room, bedrooms. perform drywall patch & replace throughout hallway, kitchen, bathrooms, living room, dining room, bedrooms. complete remodel of bathrooms and kitchen countertops, cabinets, appliances.
Details
Permit
202504184810
Permit issued
Apr 22, 2025

revision to permit 202503101937 to include patch sheet rpck & tile to hallway, living room, dining room, bedrooms. perform drywall patch & replace throughout hallway, kitchen, bathrooms, living room, dining room, bedrooms. complete remodel of bathrooms and kitchen countertops, cabinets, appliances.

Open the permit page

$10,000
Mar 10, 2025In progress
issued Mar 2025
781 11th Avpatch, sheetrock, and retile: bathroom and kitchen.
Details
Permit
202503101937
Permit issued
Mar 10, 2025

patch, sheetrock, and retile: bathroom and kitchen.

Open the permit page

$19,000
Jan 3, 2025Completed
final sign-off Feb 2025
155 Moffitt Sttotal bath remodeling, tile, bathtub, converted to shower. remove existing door and convert to pocket door. no change in size.
Details
Permit
202501037703
Permit issued
Jan 3, 2025
Final sign-off
Feb 4, 2025

total bath remodeling, tile, bathtub, converted to shower. remove existing door and convert to pocket door. no change in size.

Open the permit page

$10,000
Jun 12, 2023Never finaled
issued Jun 2023, no final
64 Chenery Strepair deteriorated framing @ bathroom including stud ways decayed floor & roof framing &deteriorated concrete flooring.
Details
Permit
202306129854
Permit issued
Jun 22, 2023

repair deteriorated framing @ bathroom including stud ways decayed floor & roof framing &deteriorated concrete flooring.

Open the permit page

$35,000
Nov 8, 2022Completed
final sign-off May 2023
2810 Diamond Stcustomer's bathroom remodeling complete update. customer's area flooring(new tile). no exterior work.
Details
Permit
202211086088
Permit issued
Nov 10, 2022
Final sign-off
May 18, 2023

customer's bathroom remodeling complete update. customer's area flooring(new tile). no exterior work.

Open the permit page

$18,000
Nov 19, 2021Completed
final sign-off Dec 2021
2040 Ocean Avinterior painting of dining area, cleaning 7 grouting of (e) floor tile. repolacing bathroom door (not frame) and rpelacing sinks incooking area. to comply with pid202184560 and bid202184407 complaints. no structural work or layout changes.
Details
Permit
202111192813
Permit issued
Nov 19, 2021
Final sign-off
Dec 27, 2021

interior painting of dining area, cleaning 7 grouting of (e) floor tile. repolacing bathroom door (not frame) and rpelacing sinks incooking area. to comply with pid202184560 and bid202184407 complaints. no structural work or layout changes.

Open the permit page

$9,000
Feb 28, 2019Never finaled
issued Jul 2019, no final
658 06th Avunit a. kitchen and bathroom remodel. updating drywall, electrical and painting.
Details
Permit
201902284049
Permit issued
Jul 23, 2019

unit a. kitchen and bathroom remodel. updating drywall, electrical and painting.

Open the permit page

$55,000
Feb 13, 2019Expired or cancelled
cancelled Jan 2026
3279 Mission St1st flr bathroom remodel at commercial space. new flooring, updating electrical and plumbing, painting.
Details
Permit
201902132872

1st flr bathroom remodel at commercial space. new flooring, updating electrical and plumbing, painting.

Open the permit page

$35,000
Jun 7, 2017Completed
final sign-off Jul 2018
658 06th Avunit #a: (front building only) remodel 1 kitchens, 2 bathrooms upgrade ele. patch walls & paint
Details
Permit
201706078671
Permit issued
Jun 26, 2017
Final sign-off
Jul 17, 2018

unit #a: (front building only) remodel 1 kitchens, 2 bathrooms upgrade ele. patch walls & paint

Open the permit page

$60,000
Nov 3, 2015Completed
final sign-off Mar 2016
1151 Hollister Avrestorage of same framing parts-remodeling 2 bathrooms-re-dry wall in 1st flr & 2 rooms in 2nd flr-back, elevation siding-restoration of flooring in the 2 stories,reroofing,painting interior & exterior-restoring deck in back in-kind.
Details
Permit
201511031621
Permit issued
Nov 4, 2015
Final sign-off
Mar 22, 2016

restorage of same framing parts-remodeling 2 bathrooms-re-dry wall in 1st flr & 2 rooms in 2nd flr-back, elevation siding-restoration of flooring in the 2 stories,reroofing,painting interior & exterior-restoring deck in back in-kind.

Open the permit page

$80,000
Oct 29, 2008Completed
final sign-off Apr 2009
4517 03rd Stadd a deli and pizza corner inside the existing grocery store, and add accessible bathroom.
Details
Permit
200810295399
Permit issued
Nov 3, 2008
Final sign-off
Apr 14, 2009

add a deli and pizza corner inside the existing grocery store, and add accessible bathroom.

Open the permit page

$50,000