Mars Construction And Remodeling
- Based in
- Concord
- On San Francisco permits
- Aug 2024 to Jul 2026
- Last 24 months
- 12 permits filed
14 permits since 2000: 7 completed, 7 in progress.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 14, 2026 | In progress issued Jul 2026 | 74 Vista Verde Ct | like for like bathroom remodel update plumbing and electrical up to code.Details
like for like bathroom remodel update plumbing and electrical up to code. | $22,000 |
| Jun 30, 2026 | In progress issued Jul 2026 | 64 Sanchez St | to obtain final inspection for work approved under pa# 202506189017. all work is complete.Details
to obtain final inspection for work approved under pa# 202506189017. all work is complete. | |
| Jun 30, 2026 | In progress issued Jul 2026 | 64 Sanchez St | to obtain final inspetion for work approved under pa# 202506188945. all work is complete.Details
to obtain final inspetion for work approved under pa# 202506188945. all work is complete. | |
| Apr 13, 2026 | Completed final sign-off Aug 2026 | 420 Stanyan St | unit 3: remodel two bathrooms, one with shower, one with tub, repair plumbing and electrical as necessary, new flooring in hallways.Details
unit 3: remodel two bathrooms, one with shower, one with tub, repair plumbing and electrical as necessary, new flooring in hallways. | $55,000 |
| Feb 23, 2026 | Completed final sign-off Jul 2026 | 3559 17th St | 2nd floor:work in 3559a 17th st : int bathroom remodel including demo of existing fixture & finishes. installation of new shower pan & waterproofing system. relocation of plumbing fixtures. new electrical & fixtures. install of new vanity & toilet. intall new window & related framing in-kind.Details
2nd floor:work in 3559a 17th st : int bathroom remodel including demo of existing fixture & finishes. installation of new shower pan & waterproofing system. relocation of plumbing fixtures. new electrical & fixtures. install of new vanity & toilet. intall new window & related framing in-kind. | $30,000 |
| Feb 3, 2026 | Completed final sign-off Aug 2026 | 156 San Juan Av | new heat pump. bathroom remodel. provide min 3" support pad for hpDetails
new heat pump. bathroom remodel. provide min 3" support pad for hp | $27,230 |
| Dec 3, 2025 | Completed final sign-off Feb 2026 | 2722 Judah St | bathroom remodel w/ removal of partition non-load bearing walls,doors (e) shower enclosure,vanity,toilet & closet.relocation of vanity,large showers,(n) toilet,washer& dryer. (n) tile vanity,lights mirrors,plumbing fixtures,paint,gfci outlets,ceiling fan w/ humidity sensor.Details
bathroom remodel w/ removal of partition non-load bearing walls,doors (e) shower enclosure,vanity,toilet & closet.relocation of vanity,large showers,(n) toilet,washer& dryer. (n) tile vanity,lights mirrors,plumbing fixtures,paint,gfci outlets,ceiling fan w/ humidity sensor. | $34,000 |
| Aug 19, 2025 | In progress issued Sep 2025 | 64 Sanchez St | revision to pa #202410032291. structural changes and new structural plans; relocation of washer/dryer, kitchen layout update; subpanel relocation, stair case height adjustmentDetails
revision to pa #202410032291. structural changes and new structural plans; relocation of washer/dryer, kitchen layout update; subpanel relocation, stair case height adjustment | $15,000 |
| Jun 18, 2025 | In progress issued Jun 2025 | 64 Sanchez St | new bedroom to be added to existing 1st flr.Details
new bedroom to be added to existing 1st flr. | $10,000 |
| Jun 18, 2025 | In progress issued Jun 2025 | 64 Sanchez St | in-kind kitchen remodel. replace counter, cabinets, sink in the same location.Details
in-kind kitchen remodel. replace counter, cabinets, sink in the same location. | $20,000 |
| Oct 16, 2024 | Completed final sign-off Feb 2025 | 340 Ritch St | unit 5: addition of half bath on the lower level with new vanity, fan, lights, switches, toilet. includes 2 walls and one door.Details
unit 5: addition of half bath on the lower level with new vanity, fan, lights, switches, toilet. includes 2 walls and one door. | $15,000 |
| Oct 10, 2024 | Completed final sign-off Apr 2025 | 1783 San Jose Av | kitchen remodeling:work will include demolition of existing counter top, cabinets,vinyl flooring,relocation of sink approx 3 ft. install new engineer hard wood flooring,cabinets install appliances install,painting walls/ceiling. install 3 retro-fit windows at existing opening;not visible from streetDetails
kitchen remodeling:work will include demolition of existing counter top, cabinets,vinyl flooring,relocation of sink approx 3 ft. install new engineer hard wood flooring,cabinets install appliances install,painting walls/ceiling. install 3 retro-fit windows at existing opening;not visible from street | $3,200 |
| Oct 3, 2024 | In progress issued Oct 2024 | 64 Sanchez St | addition of staircase, raise ceiling with 2 new skylights, and bathroom additionDetails
addition of staircase, raise ceiling with 2 new skylights, and bathroom addition | $50,000 |
| Aug 8, 2024 | Completed final sign-off Sep 2025 | 1325 Indiana St | unit #8: interior remodel of a lofted condominium on 2nd fl. bedroom and ensuite are being updated with new fixtures, finishes, and cabinetry. addition of storage at entry.Details
unit #8: interior remodel of a lofted condominium on 2nd fl. bedroom and ensuite are being updated with new fixtures, finishes, and cabinetry. addition of storage at entry. | $40,000 |