Kurt Jehling Construction
- Based in
- Corte Madera
- On San Francisco permits
- Aug 2014 to Jul 2016
- Last 24 months
- 0 permits filed
3 permits since 2000: 2 completed, 1 never finaled.
Of the 1 never-finaled permit, 1 is over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for kitchen remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Kitchen remodel permits
1 kitchen remodel permit: 1 completed. Typically 48 days from filing to permit and 235 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 29, 2014 | Completed final sign-off Jun 2015 | 1967 29th Av | interior renovation of (e) 1st floor: renovate 1 (e) bath, eliminate 1 (e) bathroom, enlarge (e) closet, add entry security gate. 2nd flr: renovate (e) kitchen, renovate 2 (e) bathrooms. electrical & plumbing work as req'd @ bht floors. no structural work, no change to doors/windows.Details
interior renovation of (e) 1st floor: renovate 1 (e) bath, eliminate 1 (e) bathroom, enlarge (e) closet, add entry security gate. 2nd flr: renovate (e) kitchen, renovate 2 (e) bathrooms. electrical & plumbing work as req'd @ bht floors. no structural work, no change to doors/windows. | $88,000 |