61 permits since 2000: 31 completed, 23 in progress, 4 never finaled, 3 expired or cancelled.
Of the 4 never-finaled permits, 4 are 3 to 5 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for bathroom remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Bathroom remodel permits
24 bathroom remodel permits: 14 completed, 9 in progress, 1 never finaled. Typically 20 days from filing to permit and 182 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 11, 2026 | In progress issued Aug 2026 | 38 Keystone Wy | 1st floor foundation and slab replacement; lowered finished slab by 12 inches max. remodel bathroom. install ply'd shearwalls and holdownsDetails
1st floor foundation and slab replacement; lowered finished slab by 12 inches max. remodel bathroom. install ply'd shearwalls and holdowns | $50,000 |
| Jul 10, 2026 | In progress issued Jul 2026 | 611 40th Av | revision to 202511260478. reconfigure layout of family room, kitchenette, excercise area and full bath. relocate laundry set-up garage. relocate tankless water heater. at 2nd flr, replace (2) windoes and (1) sliding door, all facing backyard.Details
revision to 202511260478. reconfigure layout of family room, kitchenette, excercise area and full bath. relocate laundry set-up garage. relocate tankless water heater. at 2nd flr, replace (2) windoes and (1) sliding door, all facing backyard. | $6,000 |
| Jul 2, 2026 | In progress issued Jul 2026 | 1356 Mcallister St | remodel one bathroom in kind. no removal of wallsDetails
remodel one bathroom in kind. no removal of walls | $20,000 |
| Apr 3, 2026 | In progress issued May 2026 | 569 28th St | revision 202510248124- 1st floor laundry, wet bar, and bathroom remodel. repalce 3rd floor and 2nd floor guardrails with glass railing. extended 1st floor deck.Details
revision 202510248124- 1st floor laundry, wet bar, and bathroom remodel. repalce 3rd floor and 2nd floor guardrails with glass railing. extended 1st floor deck. | $10,000 |
| Nov 26, 2025 | In progress issued Mar 2026 | 611 40th Av | 2nd fl - shift interior stair toward the front of bldg; remove stairs in lightwell; reconstruct balcony in sunroom. ground fl - infill open space below (e) sunroom to create indoor plant add family room w/kitchenette (2 burner), full bath, exercise room & laundry area; add detached gazebo with ofuroDetails
2nd fl - shift interior stair toward the front of bldg; remove stairs in lightwell; reconstruct balcony in sunroom. ground fl - infill open space below (e) sunroom to create indoor plant add family room w/kitchenette (2 burner), full bath, exercise room & laundry area; add detached gazebo with ofuro | $150,000 |
| Oct 24, 2025 | In progress issued Oct 2025 | 569 28th St | 1/f: convert (e) storage to living space (2 bed, 2 bath, media room, and wet bar), 764 sq ft. rebuild ground level deck. 2/f: remodel kitchen, reconfigure bathroom. add interior stairs to 1/f. 3/f: remodel bathroom and closet. replace front windows with all wood clad in kind. same operation. replaceDetails
1/f: convert (e) storage to living space (2 bed, 2 bath, media room, and wet bar), 764 sq ft. rebuild ground level deck. 2/f: remodel kitchen, reconfigure bathroom. add interior stairs to 1/f. 3/f: remodel bathroom and closet. replace front windows with all wood clad in kind. same operation. replace | $240,000 |
| Sep 12, 2025 | Completed final sign-off Jan 2026 | 93 Uranus Tr | waterproofing existing deck. new habitable space below-add rear portion. new full bathroom. modify bottom of existing stair adding a landing platform. rear patio door at level 1 shall not have a lock for means of egress from new basement room back into the house and shall remain openable at all timeDetails
waterproofing existing deck. new habitable space below-add rear portion. new full bathroom. modify bottom of existing stair adding a landing platform. rear patio door at level 1 shall not have a lock for means of egress from new basement room back into the house and shall remain openable at all time | $70,000 |
| Jun 17, 2025 | Completed final sign-off Oct 2025 | 63 Keystone Wy | remodel (1) kitchen and (1) bathroom in kind.Details
remodel (1) kitchen and (1) bathroom in kind. | $30,000 |
| May 16, 2025 | In progress issued Jul 2025 | 68 Rudden Av | 1/f: add 1 family room, 1 bedroom and 1 full bathroom. replace (e) furnace and tank water-heater.Details
1/f: add 1 family room, 1 bedroom and 1 full bathroom. replace (e) furnace and tank water-heater. | $70,000 |
| Apr 25, 2025 | Completed final sign-off Aug 2025 | 579 06th Av | remodel one kitchen and two bathrooms in kind no change to layout. no new wall and no existing wall relocation. new lighting shall comply with cec 150.0(k)3 & (k)5. number of plumbing fixture count remain same.Details
remodel one kitchen and two bathrooms in kind no change to layout. no new wall and no existing wall relocation. new lighting shall comply with cec 150.0(k)3 & (k)5. number of plumbing fixture count remain same. | $30,000 |
| Feb 20, 2025 | Completed final sign-off Jul 2025 | 180 Robinhood Dr | add one bathroom to ground floor.Details
add one bathroom to ground floor. | $20,000 |
| Oct 23, 2024 | Completed final sign-off Feb 2025 | 159 Faith St | convert (e) storage room to an unconditional new bathroom and laundry room at basement levelDetails
convert (e) storage room to an unconditional new bathroom and laundry room at basement level | $30,000 |
| Oct 22, 2024 | In progress issued Sep 2026 | 209 Wawona St | reconfigure/remodel 1st floor plan. relocate the office, bathroom, kitchen at 1st floor. reconfigure 2nd floor plan with 2 new bathrooms and new master bedroom at 2nd floor. a 2 story addition to the rear and side of the building of approx. 702 sq ft.Details
reconfigure/remodel 1st floor plan. relocate the office, bathroom, kitchen at 1st floor. reconfigure 2nd floor plan with 2 new bathrooms and new master bedroom at 2nd floor. a 2 story addition to the rear and side of the building of approx. 702 sq ft. | $403,000 |
| Oct 1, 2024 | Completed final sign-off Jun 2025 | 366 Staples Av | revision to pa 202405101926 move bathroom to other bedroom. closet in bedrooms. move sink in new laundrym remove nicheDetails
revision to pa 202405101926 move bathroom to other bedroom. closet in bedrooms. move sink in new laundrym remove niche | |
| Jul 19, 2024 | Completed final sign-off Oct 2024 | 289 Baltimore Wy | remodel 1 bath & 1 kitchen on 2nd fl in kindDetails
remodel 1 bath & 1 kitchen on 2nd fl in kind | $40,000 |
| Jun 27, 2024 | In progress issued Sep 2024 | 240 Vicente St | 2/f: existing 2 bathroom and 1 kitchen remodel. new full bathroom and powder room. change directions of stairs at rear deck.Details
2/f: existing 2 bathroom and 1 kitchen remodel. new full bathroom and powder room. change directions of stairs at rear deck. | $50,000 |
| May 10, 2024 | Completed final sign-off Jun 2025 | 366 Staples Av | rebuild (e) stair and make larger stairwell. (n) windows. add (2) bedrooms. (n) bathroom on 1st floor. replace (e) gas furance w/ heat pump system for heating and cooling air and water.Details
rebuild (e) stair and make larger stairwell. (n) windows. add (2) bedrooms. (n) bathroom on 1st floor. replace (e) gas furance w/ heat pump system for heating and cooling air and water. | $100,000 |
| May 1, 2024 | Completed final sign-off Jan 2025 | 1459 31st Av | 1f: provide (n) wet bar. new home office and laundry. expand existing family room into corridor. upgrade electrical panel to 200 amp. 2f: remodel (e) kitchen, bathroom, and new toilet room. replace rear and side windows, skylights and doors.Details
1f: provide (n) wet bar. new home office and laundry. expand existing family room into corridor. upgrade electrical panel to 200 amp. 2f: remodel (e) kitchen, bathroom, and new toilet room. replace rear and side windows, skylights and doors. | $75,000 |
| Feb 23, 2024 | Completed final sign-off Jul 2024 | 2939 Harrison St | remodel one kitchen and one bathroom, same layout. add new subpanel to 3rd floor.Details
remodel one kitchen and one bathroom, same layout. add new subpanel to 3rd floor. | $25,000 |
| Feb 7, 2024 | Completed final sign-off Jul 2025 | 93 Uranus Tr | kitchen & bathroom remodel with (e) deck repair and maintenance. bathroom additon @ 2nd fl. exterior window replacement at rear only.Details
kitchen & bathroom remodel with (e) deck repair and maintenance. bathroom additon @ 2nd fl. exterior window replacement at rear only. | $120,000 |
| Aug 1, 2023 | Completed final sign-off Sep 2024 | 68 Keystone Wy | 1st. fl. new bedroom, new 2 bathrooms, new family room, 2nd fl. new code compliant interior staircaseDetails
1st. fl. new bedroom, new 2 bathrooms, new family room, 2nd fl. new code compliant interior staircase | $30,000 |
| May 12, 2023 | Completed final sign-off Jul 2025 | 268 Church St | change of use from retail to cannabis retail- tenant improvement to demo extg interior partitions, accessibility upgrades to extg bathrooms, new private office, storage rooms, new electrical throughout. install exterior security gate.Details
change of use from retail to cannabis retail- tenant improvement to demo extg interior partitions, accessibility upgrades to extg bathrooms, new private office, storage rooms, new electrical throughout. install exterior security gate. | $25,000 |
| Mar 21, 2022 | Never finaled issued Aug 2023, no final | 1352 Mcallister St | the scope of work includes a rear horizontal addition to reconfigure the existing common exterior egress stairs, rebuild and expand the rear dining room area, add a half bath at unit 1352, etc.Details
the scope of work includes a rear horizontal addition to reconfigure the existing common exterior egress stairs, rebuild and expand the rear dining room area, add a half bath at unit 1352, etc. | $38,000 |
| Dec 10, 2021 | Completed final sign-off Oct 2023 | 2311 09th Av | add one bedroom,one family room,one bath @ ground floor. remodel kitchen & bath @ 2nd floor.Details
add one bedroom,one family room,one bath @ ground floor. remodel kitchen & bath @ 2nd floor. | $50,888 |