Hong Chang Construction Inc
- Based in
- San Francisco
- On San Francisco permits
- Jul 2002 to Feb 2026
- Last 24 months
- 3 permits filed
60 permits since 2000: 53 completed, 6 never finaled, 1 expired or cancelled.
Of the 6 never-finaled permits, 1 is 5 to 10 years old, 5 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for kitchen remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Kitchen remodel permits
21 kitchen remodel permits: 18 completed, 3 never finaled. Typically 0 days from filing to permit and 112 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Feb 27, 2026 | Completed final sign-off Aug 2026 | 535 Guerrero St | remodel existing kitchen and bathroom in kind. kitchen approx 90 sq ft, bathroom approx 50 sq ft. remove wall plaster for bedroom (2 exterior walls) and insulate and recover with sheetrock. install eletric sub panel for the unit. 5/8" type x sheet rock in kitchen, bathroom and bedroom(2 ext.walls).Details
remodel existing kitchen and bathroom in kind. kitchen approx 90 sq ft, bathroom approx 50 sq ft. remove wall plaster for bedroom (2 exterior walls) and insulate and recover with sheetrock. install eletric sub panel for the unit. 5/8" type x sheet rock in kitchen, bathroom and bedroom(2 ext.walls). | $73,500 |
| Feb 27, 2026 | Completed final sign-off Jul 2026 | 539 Guerrero St | partial kitchen remodel in kind. 7' run of base cabinets with sink, faucet and countertop. replace range hood in kind. install new slow faucet for bathroom. install electrical sub panel for the unit.Details
partial kitchen remodel in kind. 7' run of base cabinets with sink, faucet and countertop. replace range hood in kind. install new slow faucet for bathroom. install electrical sub panel for the unit. | $11,500 |
| Sep 3, 2025 | Completed final sign-off Oct 2025 | 1915 Laguna St | unit 2: remodel existing kitchen (cabinet, countertop, sink, appliance). install new kitchen (cabinet, countertop, sink, appliance, vinyl floor). install one new 50 amp subpanel for kitchen.Details
unit 2: remodel existing kitchen (cabinet, countertop, sink, appliance). install new kitchen (cabinet, countertop, sink, appliance, vinyl floor). install one new 50 amp subpanel for kitchen. | $15,000 |
| Mar 25, 2024 | Completed final sign-off Jul 2024 | 537 Guerrero St | remodel (1) kitchen, (2) bathrooms in the unit. upgrade electrical in kitchen and bathrooms. add electrical outlet in bedrooms. no removal of wallsDetails
remodel (1) kitchen, (2) bathrooms in the unit. upgrade electrical in kitchen and bathrooms. add electrical outlet in bedrooms. no removal of walls | $52,000 |
| Dec 18, 2023 | Completed final sign-off Mar 2024 | 448 12th Av | main bathroom remodeling, install new fan, light sink, tile. install new counter top, sink, faucet. add new 125 amp subpanel for the unit. add electrical receptacles for kitchen. relocate gas furnance in basement. new painting for entire unit.Details
main bathroom remodeling, install new fan, light sink, tile. install new counter top, sink, faucet. add new 125 amp subpanel for the unit. add electrical receptacles for kitchen. relocate gas furnance in basement. new painting for entire unit. | $42,500 |
| Jun 17, 2021 | Completed final sign-off Jan 2022 | 50 Morningside Dr | remodel (1) kitchen & 1 bathroom on 2/f. including plumbing & electrical.Details
remodel (1) kitchen & 1 bathroom on 2/f. including plumbing & electrical. | $35,000 |
| Feb 24, 2020 | Completed final sign-off Mar 2020 | 460 Brussels St | remodle kitchen, 1 full bathroom at second floor. comply with complaint # 202012331 and 202012341Details
remodle kitchen, 1 full bathroom at second floor. comply with complaint # 202012331 and 202012341 | $22,000 |
| Oct 31, 2019 | Completed final sign-off Aug 2020 | 143 Gaven St | construct 2 bedroom, 2 full baths @ ground floor; relocate (e) kitchen, remodel (e) bath room. add 1 new bathroom and convert (e) dining room to bedroom @ 2nd flDetails
construct 2 bedroom, 2 full baths @ ground floor; relocate (e) kitchen, remodel (e) bath room. add 1 new bathroom and convert (e) dining room to bedroom @ 2nd fl | $135,000 |
| Oct 10, 2018 | Never finaled issued Oct 2018, no final | 187 Stanyan St | remove existing kitchen cabinets, tile, countertop, plumbing fixtures, and appliances. install new kitchen cabinets, countertop, sink, faucet, lighting fixtures for ceiling, electrical outlets, new hardwood floor. kitchen size: 10' x 12'Details
remove existing kitchen cabinets, tile, countertop, plumbing fixtures, and appliances. install new kitchen cabinets, countertop, sink, faucet, lighting fixtures for ceiling, electrical outlets, new hardwood floor. kitchen size: 10' x 12' | $11,500 |
| Dec 23, 2016 | Completed final sign-off May 2017 | 33 Lisbon St | alter (e) 2nd flr - remodel (e) kitchen, bathroom and dining room. remove walls between kitchen and dining rm and utility rm, add new bathroom . replace w/h & furnaceDetails
alter (e) 2nd flr - remodel (e) kitchen, bathroom and dining room. remove walls between kitchen and dining rm and utility rm, add new bathroom . replace w/h & furnace | $30,000 |
| Sep 28, 2015 | Never finaled issued Sep 2015, no final | 271 Moscow St | replace new floor tile and wall tiles in kitchen & 1 bathroom ; replace 2 new vinyl windows in back yard wall, install new hardwood floor for enitre house, painting entire house.Details
replace new floor tile and wall tiles in kitchen & 1 bathroom ; replace 2 new vinyl windows in back yard wall, install new hardwood floor for enitre house, painting entire house. | $17,500 |
| Aug 23, 2013 | Never finaled issued Aug 2013, no final | 3623 Cabrillo St | reconfigure extg bathroom at 2nd floors per plan. remodel and relocate extg kitchen at 2nd and 3rd floor. new furnace and washer/dryer machine at 3rd floor. new master suite at 3rd floor. remodel extg bath at 3rd floor. replace extg window at rear and siding of bldg.Details
reconfigure extg bathroom at 2nd floors per plan. remodel and relocate extg kitchen at 2nd and 3rd floor. new furnace and washer/dryer machine at 3rd floor. new master suite at 3rd floor. remodel extg bath at 3rd floor. replace extg window at rear and siding of bldg. | $130,000 |
| Sep 5, 2012 | Completed final sign-off Nov 2013 | 151 Everglade Dr | add new bedroom and family room at 1st floor. legalize (e) bathroom and laundry room at 1st floor. remodel (e) master bathroom & kitchen at 2nd floor. add new bathroom at 2nd floor as per plan. replace window thru house, replace front window w/wood window, repair stucco at side fo bldg approx 100 sfDetails
add new bedroom and family room at 1st floor. legalize (e) bathroom and laundry room at 1st floor. remodel (e) master bathroom & kitchen at 2nd floor. add new bathroom at 2nd floor as per plan. replace window thru house, replace front window w/wood window, repair stucco at side fo bldg approx 100 sf | $46,000 |
| Dec 14, 2011 | Completed final sign-off Aug 2012 | 137 Lakeview Av | remodel two bathrooms & one kitchen. remove (e) plaster at walls of two bedrms, living rm & dinning rm w/n) 5/8" sheetrock nailed w/6d cooler nails @6"o.c. at edges, install insulation. use 5/8" type x gyp bd at exterior wall. approx. 600 sf of wall area. no wall relocation.Details
remodel two bathrooms & one kitchen. remove (e) plaster at walls of two bedrms, living rm & dinning rm w/n) 5/8" sheetrock nailed w/6d cooler nails @6"o.c. at edges, install insulation. use 5/8" type x gyp bd at exterior wall. approx. 600 sf of wall area. no wall relocation. | $20,000 |
| May 4, 2010 | Completed final sign-off Jul 2010 | 1673 18th Av | remove old cabinets in kitchen, install new kitchen cabinets & counter top. new tile floor, painting. no new lighting, replace 2 ceiling lights al least 50% high efficacy lighting by wattageDetails
remove old cabinets in kitchen, install new kitchen cabinets & counter top. new tile floor, painting. no new lighting, replace 2 ceiling lights al least 50% high efficacy lighting by wattage | $8,736 |
| May 4, 2010 | Completed final sign-off Jul 2010 | 2710 Webster St | install new cabinets in kitchen & counter top, install new wall tile & floor tile in bathroom, patch living room cracks & paint. no new lightingDetails
install new cabinets in kitchen & counter top, install new wall tile & floor tile in bathroom, patch living room cracks & paint. no new lighting | $9,964 |
| Aug 27, 2009 | Completed final sign-off Nov 2009 | 1246 25th Av | remodel (e) bathroom & kitchen on second floor. add new half bath on second floor. legalize existing family room and bathroom on first floor. add 150 sq. ft. new family room at first floor. replace 4 rear windows at 1st and 2nd floors, and replace front window in-kind.Details
remodel (e) bathroom & kitchen on second floor. add new half bath on second floor. legalize existing family room and bathroom on first floor. add 150 sq. ft. new family room at first floor. replace 4 rear windows at 1st and 2nd floors, and replace front window in-kind. | $20,000 |
| May 21, 2009 | Completed final sign-off Aug 2009 | 801 Pacheco St | remodel existing kitchen & bathroom on second, add new bedroom & bathroom on first floor, replace all windows in kind.Details
remodel existing kitchen & bathroom on second, add new bedroom & bathroom on first floor, replace all windows in kind. | $30,000 |
| Feb 17, 2009 | Completed final sign-off Apr 2009 | 526 29th Av | convert existing dining rom into a new bathrm and closet on second flor, remodel existing kitchen on second floor.Details
convert existing dining rom into a new bathrm and closet on second flor, remodel existing kitchen on second floor. | $16,000 |
| Apr 24, 2006 | Completed final sign-off Apr 2008 | 130 21st Av | lateral addition to include remodeled kitchen and new powder room.Details
lateral addition to include remodeled kitchen and new powder room. | $38,000 |
| Jul 31, 2002 | Completed final sign-off Aug 2002 | 166 Chilton Av | dry rot existing kitchen cabinet. replace new cabinet new stove new counter top new refrigerator.Details
dry rot existing kitchen cabinet. replace new cabinet new stove new counter top new refrigerator. | $2,800 |