Cold Storage Manufacturing Inc
- Based in
- Union City
- On San Francisco permits
- Aug 2013 to Aug 2026
- Last 24 months
- 1 permit filed
8 permits since 2000: 5 completed, 2 in progress, 1 never finaled.
Of the 1 never-finaled permit, 1 is 5 to 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 19, 2026 | In progress issued Aug 2026 | 1970 Innes Av | (e) food manufacturing warehouse. to relocate (e) fence - 10' height - site gate & in-fill (e) outdoor truck ramp ev/concrete slab - all work limited to exterior.Details
(e) food manufacturing warehouse. to relocate (e) fence - 10' height - site gate & in-fill (e) outdoor truck ramp ev/concrete slab - all work limited to exterior. | $25,000 |
| Sep 25, 2024 | In progress issued Mar 2025 | 200 Napoleon St | remove cold storage insulated walls, floor insulation and refrigeration equipoemnt. revert to original warehouse. existing sprinklers, lights and fire alarm to remain in warehouse demo only ti under separate permitDetails
remove cold storage insulated walls, floor insulation and refrigeration equipoemnt. revert to original warehouse. existing sprinklers, lights and fire alarm to remain in warehouse demo only ti under separate permit | $400,000 |
| Dec 7, 2022 | Completed final sign-off Dec 2022 | 1401 Polk St | basement: to comply with complaint # 202298130, installation of a prefabricated walk-in freezer built by cold storage group. all components are removable. the size is 8'x 8'x 8' and does not impact any path of travel. tenant improvement, if any, shall be under separate permit.Details
basement: to comply with complaint # 202298130, installation of a prefabricated walk-in freezer built by cold storage group. all components are removable. the size is 8'x 8'x 8' and does not impact any path of travel. tenant improvement, if any, shall be under separate permit. | $15,000 |
| Jul 9, 2021 | Never finaled issued Aug 2021, no final | 1600 Donner Av | furnish and install a new bac vca-420a evaporative condenser on existing condenser platform. this condenser will replace the existing evaporative condenser. the new condenser matches the capacity of existing condenserDetails
furnish and install a new bac vca-420a evaporative condenser on existing condenser platform. this condenser will replace the existing evaporative condenser. the new condenser matches the capacity of existing condenser | $195,000 |
| Sep 5, 2017 | Completed final sign-off Feb 2018 | 1900 Jerrold Av | tenant improvement at above address to construct a regrigerated, walk-in cooler. scope also included the addition of an accessible mandoor in a existing coiling door & providing a rear exit to the tenant space. maher n/aDetails
tenant improvement at above address to construct a regrigerated, walk-in cooler. scope also included the addition of an accessible mandoor in a existing coiling door & providing a rear exit to the tenant space. maher n/a | $22,000 |
| Sep 24, 2014 | Completed final sign-off Nov 2014 | 2030 Jerrold Av | install cooler: 1)insulated wall and ceiling panels. 2)insulated metal doors. 3)refrigeration equipment, new control and power wiring. 4) install new light fixtures and electrical wiring as noted.Details
install cooler: 1)insulated wall and ceiling panels. 2)insulated metal doors. 3)refrigeration equipment, new control and power wiring. 4) install new light fixtures and electrical wiring as noted. | $25,000 |
| Apr 10, 2014 | Completed final sign-off Jun 2014 | 2101 Jerrold Av | tenant improvement for new freezer in existing tenant space. demo existing insulated ceiling panels, light fixtures for reinstallation and evap fan coil. installation of new insul ceiling panels on existing ins wall panels. installation of new evap coil fans, and condensing unitDetails
tenant improvement for new freezer in existing tenant space. demo existing insulated ceiling panels, light fixtures for reinstallation and evap fan coil. installation of new insul ceiling panels on existing ins wall panels. installation of new evap coil fans, and condensing unit | $17,000 |
| Aug 15, 2013 | Completed final sign-off Nov 2013 | 524 Post St | installation of new insulated metal wall panels, 3 light fixtures, 2 insulated doors & associated refrigeration equipment- sprinklers separate permit.Details
installation of new insulated metal wall panels, 3 light fixtures, 2 insulated doors & associated refrigeration equipment- sprinklers separate permit. | $50,000 |