- 1 permit filed
251 permits since 2000: 216 completed, 1 in progress, 25 never finaled, 9 expired or cancelled.
Of the 25 never-finaled permits, 9 are 5 to 10 years old, 16 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for roof deck across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.
Roof deck permits
4 roof deck permits: 4 completed. Typically 55 days from filing to permit and 240 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Mar 12, 2015 | Completed final sign-off Nov 2016 | 459 Geary St | revision to pa #2014.0627.9895 - install bison pedestal system with 850 s.f. of ipe wood deck palletes on previously submitted roof deck.Details
revision to pa #2014.0627.9895 - install bison pedestal system with 850 s.f. of ipe wood deck palletes on previously submitted roof deck. | $50,000 |
| Jun 27, 2014 | Completed final sign-off Jul 2015 | 459 Geary St | exterior tenant improvement. ceate 500 sf roof deck on e mech roof space with lighting, landscape and trellis elements. accessory to b occupancy. ref 201206082224, 201403180983Details
exterior tenant improvement. ceate 500 sf roof deck on e mech roof space with lighting, landscape and trellis elements. accessory to b occupancy. ref 201206082224, 201403180983 | $75,000 |
| May 17, 2013 | Completed final sign-off Jan 2016 | 340 Bryant St | change of use-2,3,4 fls to office fr. industrial. renovation of exterior including (n)entrance & aluminum windows in (e)opening @ portions of 1st & 2nd fl, construction of occupied roof, mech enclosure, & extension of stairs & accessible elevator to serve roof deck.Details
change of use-2,3,4 fls to office fr. industrial. renovation of exterior including (n)entrance & aluminum windows in (e)opening @ portions of 1st & 2nd fl, construction of occupied roof, mech enclosure, & extension of stairs & accessible elevator to serve roof deck. | $250,000 |
| Sep 13, 2012 | Completed final sign-off Dec 2012 | 143 08th St | construction of new offices, new breakroom, new finishes, new lighting, office partitoin walls, workstations. replacement of existing non-conforming stair with new installation of new ada elevator under separate permit from 1st floor to roof deck. mep is under seperate permit.Details
construction of new offices, new breakroom, new finishes, new lighting, office partitoin walls, workstations. replacement of existing non-conforming stair with new installation of new ada elevator under separate permit from 1st floor to roof deck. mep is under seperate permit. | $210,000 |