Caliber Carpentry Inc
- Based in
- San Pablo
- On San Francisco permits
- Feb 2020 to Aug 2025
- Last 24 months
- 1 permit filed
6 permits since 2000: 6 completed.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 13, 2025 | Completed final sign-off Jun 2026 | 702 Vermont St | front bldg: in kind remodel of e) kitchen, in kind remodel of e) bathroom, siding repair & maintance at rear of bldgDetails
front bldg: in kind remodel of e) kitchen, in kind remodel of e) bathroom, siding repair & maintance at rear of bldg | $25,000 |
| Aug 21, 2024 | Completed final sign-off Sep 2024 | 2053 Filbert St | removal of a wall installation of new header to open kitchen spaceDetails
removal of a wall installation of new header to open kitchen space | $3,000 |
| Mar 31, 2023 | Completed final sign-off Jul 2025 | 706 Vermont St | rev to pa# 202002184616 s2, conversion of the green roof to an occupied roof deck.Details
rev to pa# 202002184616 s2, conversion of the green roof to an occupied roof deck. | |
| Jan 18, 2023 | Completed final sign-off Jul 2025 | 706 Vermont St | revision to pa# 2020-0218-4616: deletion of steel beams from strucutral upgrades to ground floor, relocation of shear wall on 2nd fl. shortening of shear panel at 3rd fl. hall bathDetails
revision to pa# 2020-0218-4616: deletion of steel beams from strucutral upgrades to ground floor, relocation of shear wall on 2nd fl. shortening of shear panel at 3rd fl. hall bath | $800,000 |
| Feb 25, 2021 | Completed final sign-off Mar 2021 | 1869 Turk St | remove existing 2x6 decking assess condition of joists. repair 2 replace rotten joists with pt 2x10 or equivalant to existing. flash joist and sidding re-install 2x6 redwood decking. dock approx size of 6x20 repair in less than 50%Details
remove existing 2x6 decking assess condition of joists. repair 2 replace rotten joists with pt 2x10 or equivalant to existing. flash joist and sidding re-install 2x6 redwood decking. dock approx size of 6x20 repair in less than 50% | $13,500 |
| Feb 18, 2020 | Completed final sign-off Jul 2025 | 706 Vermont St | expansion of conditioned living space at the third floor to include a new primary bedroom and en-suite bath, two bedrooms, hall bath, and re-configuration of the kitchen and bedroom areas at the second floor.Details
expansion of conditioned living space at the third floor to include a new primary bedroom and en-suite bath, two bedrooms, hall bath, and re-configuration of the kitchen and bedroom areas at the second floor. | $80,000 |