Bayside Heating & A/C Inc
- Based in
- San Mateo
- On San Francisco permits
- Jul 2003 to Jul 2012
- Last 24 months
- 0 permits filed
9 permits since 2000: 8 completed, 1 never finaled.
Of the 1 never-finaled permit, 1 is over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for all building permits across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Most recent permits
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Jul 6, 2012 | Completed final sign-off Aug 2012 | 755 Ocean Av | replace 7 fan coils, 7 condensing units, like for like. no change in capacityDetails
replace 7 fan coils, 7 condensing units, like for like. no change in capacity | $51,000 |
| Feb 24, 2012 | Completed final sign-off Apr 2012 | 88 Howard St | replace 4 water source heat pumps. install 4 air cooled split system heat humps, same capacityDetails
replace 4 water source heat pumps. install 4 air cooled split system heat humps, same capacity | $60,000 |
| Dec 29, 2011 | Completed final sign-off Mar 2012 | 88 Howard St | replace 2 heat pump systems, install new air cooled heat pumps.Details
replace 2 heat pump systems, install new air cooled heat pumps. | $25,000 |
| Oct 20, 2010 | Completed final sign-off May 2011 | 340 Brannan St | replace cooling towers. replace hydronic boiler, no change in equipemnt size, same locations on roof.Details
replace cooling towers. replace hydronic boiler, no change in equipemnt size, same locations on roof. | $65,000 |
| Jun 10, 2010 | Completed final sign-off Apr 2011 | 340 Brannan St | reconfigure mechanical @ suite #301.Details
reconfigure mechanical @ suite #301. | $3,000 |
| May 21, 2010 | Never finaled issued May 2010, no final | 340 Brannan St | ste 302 - mechanical permit-extend new duct approx. 24ft. off (e) vav box. bldg. permit #201004150339.Details
ste 302 - mechanical permit-extend new duct approx. 24ft. off (e) vav box. bldg. permit #201004150339. | $2,000 |
| Aug 19, 2008 | Completed final sign-off Apr 2009 | 755 Ocean Av | modify below roof duct system to serve reconfigured office layout. ref pa #200806265476.Details
modify below roof duct system to serve reconfigured office layout. ref pa #200806265476. | $13,000 |
| Dec 29, 2005 | Completed final sign-off Apr 2006 | 755 Ocean Av | rev to 200504291232 hvac mech work only addition of a 5 ton heat pump to heat and cool a new weight lifting room at lick-wilmerding high school.Details
rev to 200504291232 hvac mech work only addition of a 5 ton heat pump to heat and cool a new weight lifting room at lick-wilmerding high school. | $13,500 |
| Jul 7, 2003 | Completed final sign-off Aug 2003 | 1 Mission St | replace existing cooling tower same model size weight heightDetails
replace existing cooling tower same model size weight height | $25,000 |