Permit GraphShortlistSan Francisco building permits since 2000

B N Builders Inc

Contractor license
799131
State license record
Based in
San Mateo
On San Francisco permits
Feb 2007 to Nov 2026
Last 24 months
29 permits filed

36 permits since 2000: 19 completed, 15 in progress, 2 never finaled.

Of the 2 never-finaled permits, 2 are 3 to 5 years old. 1 was filed but never issued.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records

Permits filed each year

How long permits take

Median days to final inspection, citywideMedian days to permit issued, citywide

Each point is the quarter the permits were filed, for kitchen remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor. Too few of this contractor’s permits have finished to plot them.

Where they worked

One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.

Kitchen remodel permits

AllStairs 2Kitchen remodel 2

2 kitchen remodel permits: 2 in progress. Typically 88 days from filing to permit.

FiledOutcomeAddressWork described on the permitDeclared cost
Sep 9, 2026In progress
issued Nov 2026
2 Harrison Stnew grease duct from ground floor type-1 hood to roof. duct shaft is existing from 3rd floor to roof and new from ground floor through 2nd floor. kitchen equipment is part of separate permit. accessibility deferred due to hvac work only.
Details
Permit
202609097834
Permit issued
Nov 5, 2026

new grease duct from ground floor type-1 hood to roof. duct shaft is existing from 3rd floor to roof and new from ground floor through 2nd floor. kitchen equipment is part of separate permit. accessibility deferred due to hvac work only.

Open the permit page

$44,730
Dec 30, 2025In progress
issued Apr 2026
2 Harrison St2nd fl: tenan improvement for existing 2nd fl. partial demo and construction of interior partitions, ceilings, light fixtures. mep included.micro kitchen deferred for sfdph.
Details
Permit
202512302974
Permit issued
Apr 27, 2026

2nd fl: tenan improvement for existing 2nd fl. partial demo and construction of interior partitions, ceilings, light fixtures. mep included.micro kitchen deferred for sfdph.

Open the permit page

$500,000