Block 6538, lot 016
4164 25th St
- City’s use
- Multi-Family Residential
- Built
- 1900
- Stories
- 2
- Units
- 4
- Rooms
- 4 bathrooms
- Building
- 3,800 sq ft
- Lot
- 3,419 sq ft
- Zoning
- RH2
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
13 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 23, 2025 | In progress issued Sep 2025 | 4164 25th St | Golden State Marble And Construction Inc | kitchen & bathroom remodel. no structural change.Details
kitchen & bathroom remodel. no structural change. | $30,000 |
| Jan 14, 2025 | In progress issued Jan 2025 | 4160 25th St | Golden State Marble & Granite Inc. | unit 4160a - 2nd fl. floor: kitchen remodel no structural workDetails
unit 4160a - 2nd fl. floor: kitchen remodel no structural work | $15,000 |
| Dec 26, 2024 | In progress issued Jan 2025 | 4160 25th St | Arch Plumbing Inc | installation of fire sprinkler system per nfpa 13 + 24 basement, gargae, 2nd & 3rd fl. voluntary upgradeDetails
installation of fire sprinkler system per nfpa 13 + 24 basement, gargae, 2nd & 3rd fl. voluntary upgrade | $58,000 |
| Nov 9, 2023 | In progress issued Jun 2025 | 4160 25th St | Golden State Marble And Construction Inc | add bathroom,laundry room, media room, stairs & lounge on 1st fl (4162 25th st).infill west light well & new deck on top of infileed deck on 3rd fl (4164 25th st). add 2 walls in basement. entire building to be equipped with automatic fire sprinkler type nfpa 13r throughoutDetails
add bathroom,laundry room, media room, stairs & lounge on 1st fl (4162 25th st).infill west light well & new deck on top of infileed deck on 3rd fl (4164 25th st). add 2 walls in basement. entire building to be equipped with automatic fire sprinkler type nfpa 13r throughout | $140,000 |
| May 2, 2023 | Never finaled issued May 2023, no final | 4160 25th St | Golden State Marble & Granite Inc. | remodel bathroom and kitchen on 2nd fl; structural strengthening with plywood sheathing, floor strengthening where needed; remove two windows and relocate door on 1st fl; window replacement; no increase in square footage of existing space. amend to pa202302031394 for additional work.Details
remodel bathroom and kitchen on 2nd fl; structural strengthening with plywood sheathing, floor strengthening where needed; remove two windows and relocate door on 1st fl; window replacement; no increase in square footage of existing space. amend to pa202302031394 for additional work. | $85,000 |
| Feb 3, 2023 | Never finaled issued Feb 2023, no final | 4160 25th St | Golden State Marble & Granite Inc. | (1) kitchen remodel, no structural changeDetails
(1) kitchen remodel, no structural change | $15,000 |
| Feb 2, 2023 | Never finaled issued Feb 2023, no final | 4162 25th St | Golden State Marble & Granite Inc. | (1) kitchen (1) bathroom remodel, no structural change replace side & back windows at same locationDetails
(1) kitchen (1) bathroom remodel, no structural change replace side & back windows at same location | $35,000 |
| Mar 14, 2018 | Completed final sign-off May 2018 | 4162 25th St | Window Station Inc | to comply with notice of violation 201727181. replacement of twelve windows visible from the street. new windows - marvin wood interior with aluminum exterior - being double hung within the existing openings.aluminum wood cladDetails
to comply with notice of violation 201727181. replacement of twelve windows visible from the street. new windows - marvin wood interior with aluminum exterior - being double hung within the existing openings.aluminum wood clad | $20,000 |
| Nov 2, 2017 | Completed final sign-off Nov 2017 | 4160 25th St | M C Mechanical | fix & repair ductwork located at the garage to comply w/ 2017 99451 item 11.Details
fix & repair ductwork located at the garage to comply w/ 2017 99451 item 11. | $2,500 |
| Oct 10, 2017 | Completed final sign-off Nov 2017 | 4160 25th St | Bay Counties Construction & Maint. | comply w/ nov 201799451 item 9 -install fireproofing separatin betwween garage & rear storage areaDetails
comply w/ nov 201799451 item 9 -install fireproofing separatin betwween garage & rear storage area | $1,500 |
| Aug 30, 2017 | Completed final sign-off Sep 2017 | 4160 25th St | Bay Counties Construction & Maint. | restorewall in kitchen to provide fire-rated separation between chase and habitable spaces per notice of violation 201799391 - item #7Details
restorewall in kitchen to provide fire-rated separation between chase and habitable spaces per notice of violation 201799391 - item #7 | $1,500 |
| Aug 30, 2017 | Completed final sign-off Sep 2017 | 4160 25th St | Bay Counties Construction & Maint. | provide and install handrail at rear egress stairs per nov #201799451 - item #2 & 3Details
provide and install handrail at rear egress stairs per nov #201799451 - item #2 & 3 | $1,000 |
| Apr 4, 2017 | Completed final sign-off Jun 2017 | 4160 25th St | omply with complaint #201769603, #2. replace and/or repair rotting 2x6 cross brace framing of support structure at rear of building with pressure treated lumber. not to exceed 50 of cross bracing.Details
omply with complaint #201769603, #2. replace and/or repair rotting 2x6 cross brace framing of support structure at rear of building with pressure treated lumber. not to exceed 50 of cross bracing. | $300 |