Permit GraphShortlistSan Francisco building permits since 2000

Block 4570, lot 030

1 Newhall St

City’s use
Commercial Office
Built
2017
Stories
2
Building
45,218 sq ft
Lot
51,882 sq ft
Zoning
PDR2
Construction type
C

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

15 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Oct 12, 2017Never finaled
filed Oct 2017, never issued
1 Newhall Ststreet space permit
Details
Permit
M843147
Status
filed
Filed
Oct 12, 2017
Address
1 Newhall St

street space permit

Open the permit page

Aug 8, 2017Completed
final sign-off Mar 2018
1 Newhall StClark Construction Group Ca Lprevision to permit #201406269545 s3. to facilitate fire alarm system review and show locations of fire rated shafts and shaft bottoms, and reflect options exercised from s5 - elevators and elevator shafts. maher na
Details
Permit
201708084134
Status
complete
Filed
Aug 8, 2017
Permit issued
Aug 23, 2017
Final sign-off
Mar 30, 2018
Address
1 Newhall St

revision to permit #201406269545 s3. to facilitate fire alarm system review and show locations of fire rated shafts and shaft bottoms, and reflect options exercised from s5 - elevators and elevator shafts. maher na

Open the permit page

Aug 8, 2017Completed
final sign-off Mar 2018
1 Newhall StClark Construction Group Ca Lprevision to permit #2014-0626-9545 s7. to facilitate emergency generator/fuel oil system review & fire alarm system review. update accurate locations of fsd's in electrical drawings, and provide load calcs for emergency generator. maher na
Details
Permit
201708084141
Status
complete
Filed
Aug 8, 2017
Permit issued
Aug 23, 2017
Final sign-off
Mar 30, 2018
Address
1 Newhall St

revision to permit #2014-0626-9545 s7. to facilitate emergency generator/fuel oil system review & fire alarm system review. update accurate locations of fsd's in electrical drawings, and provide load calcs for emergency generator. maher na

Open the permit page

May 10, 2017Completed
final sign-off Oct 2017
1 Newhall StPriority Architectural Graphics Dba Prio9 evacuation maps floors 1,2 maher not req
Details
Permit
201705106145
Status
complete
Filed
May 10, 2017
Permit issued
May 10, 2017
Final sign-off
Oct 3, 2017
Declared cost
$3,600
Address
1 Newhall St

9 evacuation maps floors 1,2 maher not req

Open the permit page

$3,600
Mar 13, 2017Never finaled
issued Apr 2017, no final
1 Newhall StClark Construction Group Ca Lpnfpa 24 underground fire water - install 113' feet of 6" ductile iron mortar lined pipe. ref app#201609137617. n/a for maher.
Details
Permit
201703131308
Status
issued
Filed
Mar 13, 2017
Permit issued
Apr 25, 2017
Declared cost
$45,000
Address
1 Newhall St

nfpa 24 underground fire water - install 113' feet of 6" ductile iron mortar lined pipe. ref app#201609137617. n/a for maher.

Open the permit page

$45,000
Mar 2, 2017Never finaled
issued Mar 2017, no final
1 Newhall Ststreet space
Details
Permit
M765307
Status
issued
Filed
Mar 2, 2017
Permit issued
Mar 2, 2017
Address
1 Newhall St

street space

Open the permit page

Dec 6, 2016Completed
final sign-off Sep 2017
1 Newhall StIntelligent Technologies & Services Incprovide one pre-action detection system on 1st floor, 1 clean agent system with 4 zones including 2 pre-action detection on 2nd floor. t.i. app#201406269545 n/a for maher.
Details
Permit
201612064245
Status
complete
Filed
Dec 6, 2016
Permit issued
Feb 2, 2017
Final sign-off
Sep 26, 2017
Declared cost
$103,000
Address
1 Newhall St

provide one pre-action detection system on 1st floor, 1 clean agent system with 4 zones including 2 pre-action detection on 2nd floor. t.i. app#201406269545 n/a for maher.

Open the permit page

$103,000
Sep 13, 2016Completed
final sign-off Dec 2017
1 Newhall StTransbay Fire Protection, Clark Construction Group Ca Lpsprinkler plans for wet system and preaction system. install to oh2 density design based on storage and lab uses
Details
Permit
201609137617
Status
complete
Filed
Sep 13, 2016
Permit issued
Feb 1, 2017
Final sign-off
Dec 20, 2017
Declared cost
$500,000
Address
1 Newhall St

sprinkler plans for wet system and preaction system. install to oh2 density design based on storage and lab uses

Open the permit page

$500,000
Sep 7, 2016Never finaled
issued Sep 2016, no final
1 Newhall Ststreetspace
Details
Permit
M719888
Status
issued
Filed
Sep 7, 2016
Permit issued
Sep 7, 2016
Address
1 Newhall St

streetspace

Open the permit page

Jul 29, 2016Completed
final sign-off Mar 2018
1 Newhall StClark Construction Group Ca Lpdeferred shop drawing submittal to ref pa 201406269545-s2 - fabricate and install stair no.1 and stair no.2 & cross over stair on the roof maher
Details
Permit
201607293773
Status
complete
Filed
Jul 29, 2016
Permit issued
Aug 10, 2016
Final sign-off
Mar 30, 2018
Address
1 Newhall St

deferred shop drawing submittal to ref pa 201406269545-s2 - fabricate and install stair no.1 and stair no.2 & cross over stair on the roof maher

Open the permit page

Mar 17, 2016Never finaled
issued Mar 2016, no final
1 Newhall Ststreet space permit
Details
Permit
M673528
Status
issued
Filed
Mar 17, 2016
Permit issued
Mar 17, 2016
Address
1 Newhall St

street space permit

Open the permit page

Mar 9, 2016Never finaled
filed Mar 2016, never issued
1 Newhall Ststreet space
Details
Permit
M670827
Status
filed
Filed
Mar 9, 2016
Address
1 Newhall St

street space

Open the permit page

Nov 4, 2015Completed
final sign-off Mar 2018
1 Newhall StClark Construction Group Ca Lpshop drawings submittal of 18" pre-cast piles for deep foundation system of proposed new building under permit application #201406269545 s.
Details
Permit
201511041742
Status
complete
Filed
Nov 4, 2015
Permit issued
Dec 8, 2015
Final sign-off
Mar 30, 2018
Address
1 Newhall St

shop drawings submittal of 18" pre-cast piles for deep foundation system of proposed new building under permit application #201406269545 s.

Open the permit page

Jun 26, 2014Completed
final sign-off Mar 2018
1 Newhall StClark Construction Group Ca Lp, Johnson Controls Fireinterior expansion, exterior renovation of (e) 2 story warehouse (circa 1986). new 2nd floor, new roof, renovated & upgraded building & site. change of use from city storage facility to sf office of chief med exam. ** maher: compliance with ordinance no# 155-13 required; route to dph **
Details
Permit
201406269545
Status
complete
Filed
Jun 26, 2014
Permit issued
Aug 6, 2015
Final sign-off
Mar 30, 2018
Declared cost
$28,000,000
Address
1 Newhall St

interior expansion, exterior renovation of (e) 2 story warehouse (circa 1986). new 2nd floor, new roof, renovated & upgraded building & site. change of use from city storage facility to sf office of chief med exam. ** maher: compliance with ordinance no# 155-13 required; route to dph **

Open the permit page

$28,000,000
Nov 10, 2006Expired or cancelled
expired Jul 2016
1 Newhall StWestech Roofing Coreroofing
Details
Permit
200611107392
Status
expired
Filed
Nov 10, 2006
Permit issued
Nov 10, 2006
Declared cost
$73,000
Address
1 Newhall St

reroofing

Open the permit page

$73,000

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
Clark Construction Group Ca Lp (7), Intelligent Technologies & Services Inc, Johnson Controls Fire, Priority Architectural Graphics Dba Prio, Transbay Fire Protection, Westech Roofing Co
Architects
Anastasios Stathopoulos (3)
Engineers
Ramid Arbabaraghi (2), Mennor Chan, Michael Eugene Milani, Neil Joson

Find contractors for work like this