Block 3794, lot 014
111 Townsend St
- City’s use
- Industrial
- Built
- 1911
- Stories
- 3
- Rooms
- 3 bathrooms
- Building
- 18,186 sq ft
- Lot
- 199,158 sq ft
- Zoning
- M2
- Construction type
- B
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
38 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 1, 2023 | Completed final sign-off Jan 2025 | 111 Townsend St | Novo Construction Inc | revision to ti pa# 202103096205 & 202202258753, phone booths & location & size confirmation on 2nd & 3rd floor. no exterior work.Details
revision to ti pa# 202103096205 & 202202258753, phone booths & location & size confirmation on 2nd & 3rd floor. no exterior work. | |
| Jun 22, 2022 | Never finaled issued Jun 2022, no final | 111 Townsend St | San Francisco Fire Protection | as builts to pa 202108126325. show existing relay module for roll up door on 3rd floor plan and matrix for reference per inspector per inspector request.Details
as builts to pa 202108126325. show existing relay module for roll up door on 3rd floor plan and matrix for reference per inspector per inspector request. | |
| May 16, 2022 | Completed final sign-off Jul 2022 | 111 Townsend St | R L H Fire Protection Inc | fire sprinker permit. relocate 7 delete 8 and add 15 sprinklers on the 3rd floor. t.i. 202202258753Details
fire sprinker permit. relocate 7 delete 8 and add 15 sprinklers on the 3rd floor. t.i. 202202258753 | $7,000 |
| May 11, 2022 | Completed final sign-off Jan 2025 | 111 Townsend St | Novo Construction Inc | 2nd fl: mechanical and electrical for tenant improvement. ref pa# 202202258753.Details
2nd fl: mechanical and electrical for tenant improvement. ref pa# 202202258753. | $30,000 |
| Apr 12, 2022 | Completed final sign-off Jul 2022 | 111 Townsend St | San Francisco Fire Protection | due to interior remodeling on 2nd floor, four new notification devices will be installed and tie-in to existing circuit and (e) power supply panel on 3rd floor 202202258753Details
due to interior remodeling on 2nd floor, four new notification devices will be installed and tie-in to existing circuit and (e) power supply panel on 3rd floor 202202258753 | $1,800 |
| Feb 25, 2022 | Completed final sign-off Oct 2022 | 111 Townsend St | Novo Construction Inc | 2nd fl - demo of select partitions, ceilings, lighting & finishes. new non-bearing wlls, ceilings, finishes, millwork & lighting. no change of use. no exterior workDetails
2nd fl - demo of select partitions, ceilings, lighting & finishes. new non-bearing wlls, ceilings, finishes, millwork & lighting. no change of use. no exterior work | $100,000 |
| Feb 7, 2022 | Completed final sign-off Oct 2022 | 111 Townsend St | Novo Construction Inc | mep for ti nes fsd's for b32 passage way; furnish and install new low side dict and registers; provide new lighting ref pa 2021-0921-8853 and 2021-0921-8855Details
mep for ti nes fsd's for b32 passage way; furnish and install new low side dict and registers; provide new lighting ref pa 2021-0921-8853 and 2021-0921-8855 | $25,000 |
| Dec 13, 2021 | Completed final sign-off Feb 2022 | 111 Townsend St | San Francisco Fire Protection | fire alarm ti install 2 new ceiling mount strobes in phone rooms. ref pa 2021-0309-6205. 1st flDetails
fire alarm ti install 2 new ceiling mount strobes in phone rooms. ref pa 2021-0309-6205. 1st fl | $3,000 |
| Nov 30, 2021 | Completed final sign-off Jul 2022 | 111 Townsend St | San Francisco Fire Protection | due to office interior remodeling in the basement,four new notification devices will be install 7 tie in to(e) circuit. install new relay module & smoke detectors for new roll-up door tie in to (e) control panel. ref pa 202109218853, 201305287970.Details
due to office interior remodeling in the basement,four new notification devices will be install 7 tie in to(e) circuit. install new relay module & smoke detectors for new roll-up door tie in to (e) control panel. ref pa 202109218853, 201305287970. | $3,500 |
| Nov 2, 2021 | Completed final sign-off Feb 2022 | 111 Townsend St | R L H Fire Protection Inc | 1st floor: fire sprinkler permit. relocate 2 & add 8 sprinklers.Details
1st floor: fire sprinkler permit. relocate 2 & add 8 sprinklers. | $1,000 |
| Sep 21, 2021 | Completed final sign-off Oct 2022 | 111 Townsend St | Novo Construction Inc | basement: demo select light fixtures, finish upgrades, new partitions, minor lighting rework, saw cut new opening for bldg pass through & 1-hour passagewayDetails
basement: demo select light fixtures, finish upgrades, new partitions, minor lighting rework, saw cut new opening for bldg pass through & 1-hour passageway | $189,000 |
| Aug 20, 2021 | Completed final sign-off Oct 2022 | 111 Townsend St | Novo Construction Inc | ground floor: mechanical and electrical work for t.i. ref arch #202103297470Details
ground floor: mechanical and electrical work for t.i. ref arch #202103297470 | $20,000 |
| Aug 12, 2021 | Never finaled issued Aug 2021, no final | 111 Townsend St | San Francisco Fire Protection | ~kf21&due to office interior remodeling on 3rd floor, 3 new notification devices will be install and tie-in to exg power supply.ref#202103096205 and 201501266667Details
~kf21&due to office interior remodeling on 3rd floor, 3 new notification devices will be install and tie-in to exg power supply.ref#202103096205 and 201501266667 | $2,500 |
| Jul 22, 2021 | Completed final sign-off Jan 2025 | 111 Townsend St | Novo Construction Inc | mech and elect work for t.i. on 3rd flr. ref# 2021-0309-6205Details
mech and elect work for t.i. on 3rd flr. ref# 2021-0309-6205 | $20,000 |
| Jul 19, 2021 | Completed final sign-off Aug 2021 | 111 Townsend St | R L H Fire Protection Inc | relocate 2 and add 2 sprinklers on the 3rd fl. ti# 2021-0309-6205Details
relocate 2 and add 2 sprinklers on the 3rd fl. ti# 2021-0309-6205 | $1,500 |
| Mar 29, 2021 | Completed final sign-off May 2025 | 111 Townsend St | Novo Construction Inc | flip (e) steel picket gate and man door. add new metal mesh panel screens to (e) gate. remove partial (e) deck boards, deck supports and guardrails at 101 townsend. provide new wood slat fence and new security fence door at (e) deck. add guardrail at 2 (e) garage door openings.Details
flip (e) steel picket gate and man door. add new metal mesh panel screens to (e) gate. remove partial (e) deck boards, deck supports and guardrails at 101 townsend. provide new wood slat fence and new security fence door at (e) deck. add guardrail at 2 (e) garage door openings. | $70,000 |
| Mar 29, 2021 | Completed final sign-off Oct 2022 | 111 Townsend St | Novo Construction Inc | demo (e) glass wall and door and recessed fire roll down door & soffit at board room. add (n) 2 hr rated wall to backfill demo'd wall. demo (e) glass all at huddle room. add new wall & door to reconfigure huddle room into two sep rooms.Details
demo (e) glass wall and door and recessed fire roll down door & soffit at board room. add (n) 2 hr rated wall to backfill demo'd wall. demo (e) glass all at huddle room. add new wall & door to reconfigure huddle room into two sep rooms. | $200,000 |
| Mar 9, 2021 | Completed final sign-off Jan 2025 | 111 Townsend St | Novo Construction Inc | demolish a few fixed offices/phones/conferences including interior partitions,storefronts,doors/frames,ceiling tiles & power/data. a addition wire mesh partition & casework @ coffe area is being removed. new scope includes a few offices/phones/conferences w/(n)ceiling tiles,lighting,power/dataDetails
demolish a few fixed offices/phones/conferences including interior partitions,storefronts,doors/frames,ceiling tiles & power/data. a addition wire mesh partition & casework @ coffe area is being removed. new scope includes a few offices/phones/conferences w/(n)ceiling tiles,lighting,power/data | $200,000 |
| Sep 19, 2018 | Completed final sign-off Oct 2018 | 111 Townsend St | O'connor Plumbing & Fire Protection | add 6 f/s heads at pass through on each floor (2/floor). ref t.i. pa201802090890.0 maher n/a.Details
add 6 f/s heads at pass through on each floor (2/floor). ref t.i. pa201802090890.0 maher n/a. | $8,000 |
| Sep 14, 2018 | Completed final sign-off Oct 2018 | 111 Townsend St | Martin Sign Co Inc. | installation of evacuation maps for 4 floors maher n/aDetails
installation of evacuation maps for 4 floors maher n/a | $1,000 |
| Jul 19, 2018 | Completed final sign-off Aug 2018 | 111 Townsend St | San Francisco Fire Protection | install 3 smoke detectors and three relays to close new fire doors. these doors are installed by others. refer to #2013-0528-7970 and #2018-02-09-0890. maher n/aDetails
install 3 smoke detectors and three relays to close new fire doors. these doors are installed by others. refer to #2013-0528-7970 and #2018-02-09-0890. maher n/a | $7,000 |
| Feb 9, 2018 | Completed final sign-off Nov 2018 | 111 Townsend St | Narrowback Construction Co. | create 3 communicating opening on a shared wall between 101 & 111 at 1st, 2nd and 3rd floors. townsend. add 1 new ramp @ 111 townsendDetails
create 3 communicating opening on a shared wall between 101 & 111 at 1st, 2nd and 3rd floors. townsend. add 1 new ramp @ 111 townsend | $30,000 |
| Mar 13, 2015 | Never finaled issued Mar 2015, no final | 111 Townsend St | Wells Electrical, Inc | title 24 lighting maher - not req'd ref pa# 2014 1205 3198Details
title 24 lighting maher - not req'd ref pa# 2014 1205 3198 | $195,000 |
| Jan 26, 2015 | Completed final sign-off May 2015 | 111 Townsend St | San Francisco Fire Protection | due to office interior remodeling, new power supply panel will be install on 3rd floor and smoke detector above. new notification appliances will be installed through out all floors. new devices will be tie-in to extg control unit on 1st floor. t.i. # 201412053198. n/a maherDetails
due to office interior remodeling, new power supply panel will be install on 3rd floor and smoke detector above. new notification appliances will be installed through out all floors. new devices will be tie-in to extg control unit on 1st floor. t.i. # 201412053198. n/a maher | $7,800 |
| Dec 5, 2014 | Never finaled issued Dec 2014, no final | 111 Townsend St | Narrowback Construction Co. | interior office remodel, new non structural interior partitions, new millwork, new doors, glazing and carpet. rework extg lighting. electrical, mechanical, plmg, and title-24 (energy) are deferred submittal. n/a for the maher.Details
interior office remodel, new non structural interior partitions, new millwork, new doors, glazing and carpet. rework extg lighting. electrical, mechanical, plmg, and title-24 (energy) are deferred submittal. n/a for the maher. | $850,000 |
| Aug 26, 2014 | Completed final sign-off Sep 2014 | 111 Townsend St | San Francisco Fire Protection | as build drawings to reflect the removal of 1 smoke detector in the elevator shaft. maher not req ref 201305287970Details
as build drawings to reflect the removal of 1 smoke detector in the elevator shaft. maher not req ref 201305287970 | |
| Feb 24, 2014 | Completed final sign-off May 2014 | 111 Townsend St | O'connor Plumbing & Fire Protection | install 121 new sprinklers, for coverage, per tenant improvement. nfpa#13.Details
install 121 new sprinklers, for coverage, per tenant improvement. nfpa#13. | $15,000 |
| Jan 15, 2014 | Completed final sign-off Sep 2014 | 111 Townsend St | Narrowback Construction Co. | construction phase change to work presently underway per pa#2012-0227-4914 s1/r1. install (n) concrete walls in rear yard. ** maher: compliance with ordinance no# 155-13 not required **Details
construction phase change to work presently underway per pa#2012-0227-4914 s1/r1. install (n) concrete walls in rear yard. ** maher: compliance with ordinance no# 155-13 not required ** | $15,000 |
| Dec 18, 2013 | Completed final sign-off Dec 2014 | 111 Townsend St | Narrowback Construction Co. | revisions to work presently underway pa#2012-0227-4914. remove (e) cmu infill at flr 1 btwn lines c&d, infill (n) opeining w/ (n) storefront window, 4 remove (e) infill at bsmt repl with (n) storefront windows, 5.change of use under 201202274914,compliance with ord 155-13 not requiredDetails
revisions to work presently underway pa#2012-0227-4914. remove (e) cmu infill at flr 1 btwn lines c&d, infill (n) opeining w/ (n) storefront window, 4 remove (e) infill at bsmt repl with (n) storefront windows, 5.change of use under 201202274914,compliance with ord 155-13 not required | $28,500 |
| Oct 11, 2013 | Completed final sign-off Oct 2014 | 111 Townsend St | Narrowback Construction Co. | revision to 201305136771. relocate toilet room on floor 1Details
revision to 201305136771. relocate toilet room on floor 1 | |
| Jun 17, 2013 | Never finaled issued Jun 2013, no final | 111 Townsend St | street space and mta parkingDetails
street space and mta parking | ||
| May 28, 2013 | Completed final sign-off Sep 2014 | 111 Townsend St | Fire & Security & Alarm Co/ F.S.A.C. | sprinkler waterflow and supervisory system with elevator recall. new fire alarm to accomodate elevator modernization. 7 smoke detectors and 3 relay modules to accommodate elevator recall. tie in waterflow and tamper switch to new control units ti 201202274914Details
sprinkler waterflow and supervisory system with elevator recall. new fire alarm to accomodate elevator modernization. 7 smoke detectors and 3 relay modules to accommodate elevator recall. tie in waterflow and tamper switch to new control units ti 201202274914 | $3,750 |
| May 13, 2013 | Completed final sign-off Oct 2014 | 111 Townsend St | Narrowback Construction Co. | modifications to restroom layouts & locations (additional toilets in each restrm) removal of 1 skylight & relocation of 2 remaining skylights. mechanical, electrical & plumbing work associated with tenant improvement #2012-0227-4914 s1/r1Details
modifications to restroom layouts & locations (additional toilets in each restrm) removal of 1 skylight & relocation of 2 remaining skylights. mechanical, electrical & plumbing work associated with tenant improvement #2012-0227-4914 s1/r1 | $250,000 |
| Sep 7, 2012 | Never finaled issued Sep 2012, no final | 111 Townsend St | street space w/metersDetails
street space w/meters | ||
| Jun 27, 2012 | Completed final sign-off Sep 2014 | 111 Townsend St | Excel Site Services Inc | interior non structural demo only, space to remain vacant, no disable access to be provided for this permit per 2010 sfbc ab 017Details
interior non structural demo only, space to remain vacant, no disable access to be provided for this permit per 2010 sfbc ab 017 | $12,000 |
| Feb 27, 2012 | Completed final sign-off Dec 2014 | 111 Townsend St | change of use from manufacturing (f-1) to office (b). seismic reinforcement per sfbc sec.3403.5. demolish slopped roof & replace w/ flat roof. extend rear facade upward to conform to (n) roofline. (n) elevator, fire exits, electrict & mechanical systems.Details
change of use from manufacturing (f-1) to office (b). seismic reinforcement per sfbc sec.3403.5. demolish slopped roof & replace w/ flat roof. extend rear facade upward to conform to (n) roofline. (n) elevator, fire exits, electrict & mechanical systems. | $400,000 | |
| Sep 20, 2010 | Completed final sign-off Jan 2013 | 111 Townsend St | Oliver & Company Inc. | installation of soldier piles shoring work under this permit. see licensing agreement on sheet 5.0 for temporary construction easement, excavation and shoring agreement.Details
installation of soldier piles shoring work under this permit. see licensing agreement on sheet 5.0 for temporary construction easement, excavation and shoring agreement. | $20,400 |
| Mar 22, 2010 | Never finaled filed Mar 2010, never issued | 111 Townsend St | site permit-change of occupancy from warehouse to office, seismic reinforcement per sfbc sec 3403.5. demolish sloped roof & replace with flat roof, extend rear facade upward to confirm to new roofline, new elevator, fire exits, electrical & mechanical systemsDetails
site permit-change of occupancy from warehouse to office, seismic reinforcement per sfbc sec 3403.5. demolish sloped roof & replace with flat roof, extend rear facade upward to confirm to new roofline, new elevator, fire exits, electrical & mechanical systems | $400,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Novo Construction Inc (10), San Francisco Fire Protection (8), Narrowback Construction Co. (6), R L H Fire Protection Inc (3), O'connor Plumbing & Fire Protection (2), Excel Site Services Inc, Fire & Security & Alarm Co/ F.S.A.C., Martin Sign Co Inc., Oliver & Company Inc., Wells Electrical, Inc
- Architects
- Denis Henmi (6), Harvey Hacker (4), Douglas Dahlin
- Engineers
- Daniel Ahkiam (2), Jesus B Cabellon Jr (2), Donald David
- Designers
- Michael Williams, Ryan Wall
Find contractors for work like this