Block 3768, lot 015

444 Spear St

City’s use
Commercial Office
Built
1939
Stories
2
Building
51,460 sq ft
Lot
35,248 sq ft
Zoning
M1
Construction type
C

From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map

Permits filed here

26 permits filed for this property since 2000.

CompletedIn progressNever finaledExpired or cancelled
FiledOutcomeAddressContractorWork described on the permitDeclared cost
Oct 22, 2025Completed
final sign-off Nov 2025
444 Spear StDiablo Electric Inc.deferred electrical for existing permit # 202504295442.
Details
Permit
202510227859
Status
complete
Filed
Oct 22, 2025
Permit issued
Oct 22, 2025
Final sign-off
Nov 19, 2025
Declared cost
$10,000
Address
444 Spear St

deferred electrical for existing permit # 202504295442.

Open the permit page

$10,000
Jun 6, 2025In progress
issued Jun 2025
444 Spear StFreedom Fire Protection Inc.fire sprinkler system t.i. relocating 2 heads and installing 14 new heads total 16 at 2nd floor only. bldg pa #202504295442 suite 215 & 220
Details
Permit
202506068135
Status
issued
Filed
Jun 6, 2025
Permit issued
Jun 6, 2025
Declared cost
$5,000
Address
444 Spear St

fire sprinkler system t.i. relocating 2 heads and installing 14 new heads total 16 at 2nd floor only. bldg pa #202504295442 suite 215 & 220

Open the permit page

$5,000
Apr 29, 2025Completed
final sign-off Nov 2025
444 Spear StWci-Gc Incste# 215 & 220: interior tenant improvement, new non-structural partitions, lights, flooring & finshes.
Details
Permit
202504295442
Status
complete
Filed
Apr 29, 2025
Permit issued
May 12, 2025
Final sign-off
Nov 19, 2025
Declared cost
$210,000
Address
444 Spear St

ste# 215 & 220: interior tenant improvement, new non-structural partitions, lights, flooring & finshes.

Open the permit page

$210,000
Dec 2, 2016Never finaled
issued Dec 2016, no final
444 Spear StTuck Aire Htg &Air Cond. Corpdba Atlas Hunit #205: modify existing ductwork to match new office layout ; ref. permit 201610119905; maher n/a
Details
Permit
201612024006
Status
issued
Filed
Dec 2, 2016
Permit issued
Dec 7, 2016
Declared cost
$5,000
Address
444 Spear St

unit #205: modify existing ductwork to match new office layout ; ref. permit 201610119905; maher n/a

Open the permit page

$5,000
Nov 3, 2016Completed
final sign-off May 2025
444 Spear StAyoob & Peery Plumbing Co Inc2nd flr: relocate 6 and plug 2 sprinklers to conform with the new wall/ceiling of the ti 201610119905 maher na
Details
Permit
201611031809
Status
complete
Filed
Nov 3, 2016
Permit issued
Nov 3, 2016
Final sign-off
May 15, 2025
Declared cost
$1,219
Address
444 Spear St

2nd flr: relocate 6 and plug 2 sprinklers to conform with the new wall/ceiling of the ti 201610119905 maher na

Open the permit page

$1,219
Oct 11, 2016Completed
final sign-off Aug 2018
444 Spear StSaarman Construction,Ltd.suite 205 - adding four private offices to an (e) commercial office space. improvements include new non-bearing, non-rated partitions, interior doors & sidelites, minor hvac modifications, new or relocated electrical & data receptacles and minor lighting adjustments. n/a maher ordinance
Details
Permit
201610119905
Status
complete
Filed
Oct 11, 2016
Permit issued
Nov 2, 2016
Final sign-off
Aug 1, 2018
Declared cost
$144,647
Address
444 Spear St

suite 205 - adding four private offices to an (e) commercial office space. improvements include new non-bearing, non-rated partitions, interior doors & sidelites, minor hvac modifications, new or relocated electrical & data receptacles and minor lighting adjustments. n/a maher ordinance

Open the permit page

$144,647
Sep 20, 2013Completed
final sign-off Oct 2013
444 Spear StIncom Mechanical Incsuite #213-addition of 7 fire sprinkler heads; ti pa 201308265170
Details
Permit
201309207373
Status
complete
Filed
Sep 20, 2013
Permit issued
Sep 23, 2013
Final sign-off
Oct 8, 2013
Declared cost
$4,450
Address
444 Spear St

suite #213-addition of 7 fire sprinkler heads; ti pa 201308265170

Open the permit page

$4,450
Aug 26, 2013Completed
final sign-off Oct 2013
444 Spear StCci Com'l Constr & Improv**See 985808***reno suite 213. demo non structrual partitions, millwork and carpet. construct partiton millwork. mep under separate permit
Details
Permit
201308265170
Status
complete
Filed
Aug 26, 2013
Permit issued
Aug 26, 2013
Final sign-off
Oct 2, 2013
Declared cost
$100,000
Address
444 Spear St

reno suite 213. demo non structrual partitions, millwork and carpet. construct partiton millwork. mep under separate permit

Open the permit page

$100,000
Mar 18, 2013Completed
final sign-off May 2025
444 Spear StAyoob & Peery Plumbing Co Incsuite #210-relocate 2 and add 2 fire sprinkler heads per t.i 2nd fl.
Details
Permit
201303182438
Status
complete
Filed
Mar 18, 2013
Permit issued
Mar 18, 2013
Final sign-off
May 21, 2025
Declared cost
$2,056
Address
444 Spear St

suite #210-relocate 2 and add 2 fire sprinkler heads per t.i 2nd fl.

Open the permit page

$2,056
Jul 10, 2012Expired or cancelled
expired Nov 2014
444 Spear StCisco Fire Sprinklers, Inc.2nd floor - plug exist drops and add 2=ssp in ceiling of tenant improvement
Details
Permit
201207104495
Status
expired
Filed
Jul 10, 2012
Permit issued
Jul 10, 2012
Declared cost
$4,000
Address
444 Spear St

2nd floor - plug exist drops and add 2=ssp in ceiling of tenant improvement

Open the permit page

$4,000
Jun 11, 2012Completed
final sign-off Jul 2012
444 Spear StCci Com'l Constr & Improv**See 985808***ti for suite 210 on 2nd floor including non structural partitions, doors, sidelites, finishes, light fixtures. no change in area, occpancy or use. mep drawings, fire alarms, sprinklers will be submitted under separate permit
Details
Permit
201206112335
Status
complete
Filed
Jun 11, 2012
Permit issued
Jun 12, 2012
Final sign-off
Jul 26, 2012
Declared cost
$65,000
Address
444 Spear St

ti for suite 210 on 2nd floor including non structural partitions, doors, sidelites, finishes, light fixtures. no change in area, occpancy or use. mep drawings, fire alarms, sprinklers will be submitted under separate permit

Open the permit page

$65,000
Jan 19, 2012Completed
final sign-off Feb 2012
444 Spear StAnderson, Rowe & Buckley, Inc.2nd floor tenant improvements existing fire sprinkler system - relocate 6 sprinklers. remove 1.
Details
Permit
201201192560
Status
complete
Filed
Jan 19, 2012
Permit issued
Jan 19, 2012
Final sign-off
Feb 21, 2012
Declared cost
$3,000
Address
444 Spear St

2nd floor tenant improvements existing fire sprinkler system - relocate 6 sprinklers. remove 1.

Open the permit page

$3,000
Jan 17, 2012Completed
final sign-off Mar 2012
444 Spear StR.M.R. Construction Companyminor remodel of existing suite on 2nd fl. new partitions at private offices and new lighting
Details
Permit
201201172346
Status
complete
Filed
Jan 17, 2012
Permit issued
Jan 18, 2012
Final sign-off
Mar 7, 2012
Declared cost
$50,000
Address
444 Spear St

minor remodel of existing suite on 2nd fl. new partitions at private offices and new lighting

Open the permit page

$50,000
Jul 12, 2010Never finaled
issued Jul 2010, no final
444 Spear Ststreet space & sidewalk
Details
Permit
M210646
Status
issued
Filed
Jul 12, 2010
Permit issued
Jul 12, 2010
Address
444 Spear St

street space & sidewalk

Open the permit page

Jan 25, 2007Completed
final sign-off Jun 2008
444 Spear StAnderson, Rowe & Buckley, Inc.2nd floor-7 relocate sprinklers, 2 new sprinklers. t.i. (e) fire sprinkler system.
Details
Permit
200701252537
Status
complete
Filed
Jan 25, 2007
Permit issued
Jan 25, 2007
Final sign-off
Jun 5, 2008
Declared cost
$1,500
Address
444 Spear St

2nd floor-7 relocate sprinklers, 2 new sprinklers. t.i. (e) fire sprinkler system.

Open the permit page

$1,500
Dec 28, 2006Completed
final sign-off Jun 2008
444 Spear StDecker Electric Co Inc Electrical Contraoti-3 2nd floor el
Details
Permit
200612280642
Status
complete
Filed
Dec 28, 2006
Permit issued
Dec 28, 2006
Final sign-off
Jun 5, 2008
Declared cost
$10,000
Address
444 Spear St

oti-3 2nd floor el

Open the permit page

$10,000
Dec 21, 2006Expired or cancelled
expired Jun 2008
444 Spear StAnderson, Rowe & Buckley, Inc.ti.i. to exist. fire spkr system 4 new 23 relocate
Details
Permit
200612210321
Status
expired
Filed
Dec 21, 2006
Permit issued
Dec 21, 2006
Final sign-off
May 21, 2007
Declared cost
$6,000
Address
444 Spear St

ti.i. to exist. fire spkr system 4 new 23 relocate

Open the permit page

$6,000
Dec 21, 2006Completed
final sign-off Jun 2008
444 Spear StWestern Allied Mechanical Inc.oti-2 2nd floor me
Details
Permit
200612210318
Status
complete
Filed
Dec 21, 2006
Permit issued
Dec 21, 2006
Final sign-off
Jun 5, 2008
Declared cost
$12,000
Address
444 Spear St

oti-2 2nd floor me

Open the permit page

$12,000
Nov 22, 2006Completed
final sign-off Jun 2008
444 Spear Stoti-1 2nd fl el,me,ls,sp
Details
Permit
200611228338
Status
complete
Filed
Nov 22, 2006
Permit issued
Nov 22, 2006
Final sign-off
Jun 5, 2008
Declared cost
$120,000
Address
444 Spear St

oti-1 2nd fl el,me,ls,sp

Open the permit page

$120,000
Apr 27, 2006Expired or cancelled
expired Aug 2007
444 Spear StGucho Plumbingrelocate 10 heads
Details
Permit
200604270040
Status
expired
Filed
Apr 27, 2006
Permit issued
Apr 27, 2006
Declared cost
$1,500
Address
444 Spear St

relocate 10 heads

Open the permit page

$1,500
Oct 4, 2005Expired or cancelled
expired Aug 2007
444 Spear Stremove (e) store front glass panele in lobby. center of wall & concrete column. exposed slab no furnished ceiling.
Details
Permit
200510044757
Status
expired
Filed
Oct 4, 2005
Permit issued
Oct 4, 2005
Declared cost
$10,000
Address
444 Spear St

remove (e) store front glass panele in lobby. center of wall & concrete column. exposed slab no furnished ceiling.

Open the permit page

$10,000
Jun 15, 2005Expired or cancelled
expired Oct 2007
444 Spear Stlighting & electrical (all new 2nd floor)
Details
Permit
200506155135
Status
expired
Filed
Jun 15, 2005
Permit issued
Jun 15, 2005
Declared cost
$35,000
Address
444 Spear St

lighting & electrical (all new 2nd floor)

Open the permit page

$35,000
Apr 27, 2005Expired or cancelled
expired Oct 2007
444 Spear Stsoft demo/construct new partition in new offices space
Details
Permit
200504271040
Status
expired
Filed
Apr 27, 2005
Permit issued
Apr 27, 2005
Declared cost
$320,000
Address
444 Spear St

soft demo/construct new partition in new offices space

Open the permit page

$320,000
Sep 2, 2004Completed
final sign-off Dec 2004
444 Spear Stoti-1 1st floor sp me
Details
Permit
200409023194
Status
complete
Filed
Sep 2, 2004
Permit issued
Sep 2, 2004
Final sign-off
Dec 29, 2004
Declared cost
$106,100
Address
444 Spear St

oti-1 1st floor sp me

Open the permit page

$106,100
Aug 25, 2004Completed
final sign-off Dec 2004
444 Spear Stelectrical t-24 lighting
Details
Permit
200408252489
Status
complete
Filed
Aug 25, 2004
Permit issued
Aug 25, 2004
Final sign-off
Dec 29, 2004
Declared cost
$4,000
Address
444 Spear St

electrical t-24 lighting

Open the permit page

$4,000
Aug 20, 2004Expired or cancelled
withdrawn Aug 2004
444 Spear Stoti-1, 2nd floor, el, ls, me, sp
Details
Permit
200408202088
Status
withdrawn
Filed
Aug 20, 2004
Declared cost
$106,100
Address
444 Spear St

oti-1, 2nd floor, el, ls, me, sp

Open the permit page

$106,100

Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

Contractors
Anderson, Rowe & Buckley, Inc. (3), Ayoob & Peery Plumbing Co Inc (2), Cci Com'l Constr & Improv**See 985808*** (2), Cisco Fire Sprinklers, Inc., Decker Electric Co Inc Electrical Contra, Diablo Electric Inc., Freedom Fire Protection Inc., Gucho Plumbing, Incom Mechanical Inc, R.M.R. Construction Company, Saarman Construction,Ltd., Tuck Aire Htg &Air Cond. Corpdba Atlas H, Wci-Gc Inc, Western Allied Mechanical Inc.
Architects
Daniel E Huntsman (3), Hook Design, Sandy Blair
Engineers
Donald D Dammen, Stephen Shafter

Find contractors for work like this

Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.