Block 3703, lot 004
34 06th St
- City’s use
- Commercial Hotel
- Built
- 1911
- Stories
- 7
- Units
- 204
- Rooms
- 58 bathrooms
- Building
- 46,320 sq ft
- Lot
- 7,496 sq ft
- Zoning
- RSD
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
49 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 3, 2026 | In progress issued Sep 2026 | 34 06th St | Ambrocio Construction Inc | to comply with nov#202657097. repair damaged boiler-room ceiling & restore requested fire-rated assembly.Details
to comply with nov#202657097. repair damaged boiler-room ceiling & restore requested fire-rated assembly. | $2,000 |
| Jun 9, 2025 | In progress issued Jul 2025 | 34 06th St | 4-Mac Construction | 2/f to 7/f (residential floors): new in kind alteration and remodel to (e) typical stacked bathrooms at 2/f, 3/f, 4/f, 5/f, 6/f and 7/f.Details
2/f to 7/f (residential floors): new in kind alteration and remodel to (e) typical stacked bathrooms at 2/f, 3/f, 4/f, 5/f, 6/f and 7/f. | $100,000 |
| Jun 5, 2025 | In progress issued Jul 2025 | 34 06th St | 4-Mac Construction | exterior - repair in kind the following: patch and remortar cracked brick veneer, cornices, wall on roof & gaps along mortar joints. patch crack on roof parapet and roof cornice. treat w/waterproofing paint. seal or replace in kind roof & parapet coping. clean & recoat dunnage beam. repair waterDetails
exterior - repair in kind the following: patch and remortar cracked brick veneer, cornices, wall on roof & gaps along mortar joints. patch crack on roof parapet and roof cornice. treat w/waterproofing paint. seal or replace in kind roof & parapet coping. clean & recoat dunnage beam. repair water | $10,000 |
| Aug 8, 2024 | Completed final sign-off Jul 2025 | 34 06th St | Fire & Security & Alarm Co/ F.S.A.C. | add on to existing fire system to comply 1103.7.6.1. install new power supply panel & smoke detector on 2nd fl. & nw power supply panel on 5th fl. install low frequency horns in all rooms. new devices will be tie in to existing panel.Details
add on to existing fire system to comply 1103.7.6.1. install new power supply panel & smoke detector on 2nd fl. & nw power supply panel on 5th fl. install low frequency horns in all rooms. new devices will be tie in to existing panel. | $65,000 |
| May 1, 2024 | Completed final sign-off Jun 2024 | 34 06th St | Pineda Construction Inc | comply w/nov #202422027; install new grab bars per cbc 11b-609.9 (force of 250lbs)Details
comply w/nov #202422027; install new grab bars per cbc 11b-609.9 (force of 250lbs) | $700 |
| Mar 25, 2024 | Completed final sign-off May 2024 | 34 06th St | 4-Mac Construction | replace 30 (e) wood doors to metal doors. (bathrooms doors, storage, and offices) maintain rating of doors.Details
replace 30 (e) wood doors to metal doors. (bathrooms doors, storage, and offices) maintain rating of doors. | $28,000 |
| Mar 12, 2024 | Expired or cancelled withdrawn Jul 2025 | 34 06th St | Pineda Construction Inc | demo walls and floor ~ all 2 bathroom in common area in 2nd floor and 4th floor shower install new tile floor and cultured marble in walls.Details
demo walls and floor ~ all 2 bathroom in common area in 2nd floor and 4th floor shower install new tile floor and cultured marble in walls. | $12,000 |
| Jun 21, 2023 | Completed final sign-off Nov 2024 | 34 06th St | S F Garage Company Inc. | replace southwest corner lightwell non structural bricks in kind and remortar/repoint bricks. approx. 100sf ref bpa# 202303234260Details
replace southwest corner lightwell non structural bricks in kind and remortar/repoint bricks. approx. 100sf ref bpa# 202303234260 | $1,000 |
| Mar 23, 2023 | Completed final sign-off Nov 2024 | 34 06th St | S F Garage Company Inc. | perform exterior exploratory demo only on 4/th & 5/th floor; southwest corner of south facing lightwell to remove some bricks to accesss whether to only bricks & mortar in-kind. bricks to be replaced in-kind. separate permit req'd to fix/repair area of work.Details
perform exterior exploratory demo only on 4/th & 5/th floor; southwest corner of south facing lightwell to remove some bricks to accesss whether to only bricks & mortar in-kind. bricks to be replaced in-kind. separate permit req'd to fix/repair area of work. | $500 |
| Mar 2, 2023 | Completed final sign-off Mar 2023 | 34 06th St | Pineda Construction Inc | to comply with complaint #202301381: repair room #626. repair ceiling hall damage from fire, paint, and install new floor. repair w/ 5/8" type x sheetrock for fire separation.Details
to comply with complaint #202301381: repair room #626. repair ceiling hall damage from fire, paint, and install new floor. repair w/ 5/8" type x sheetrock for fire separation. | $4,500 |
| Oct 19, 2022 | Never finaled filed Oct 2022, never issued | 34 06th St | San Francisco Fire Protection | phase 1 like for like alarm replacement, install aes radio, monitoring, module, relpace facu, alarm annvnciator, smoke detectors, pu;l stations, heat detectors, mimi moinitoring modules, relay modules, control modulesDetails
phase 1 like for like alarm replacement, install aes radio, monitoring, module, relpace facu, alarm annvnciator, smoke detectors, pu;l stations, heat detectors, mimi moinitoring modules, relay modules, control modules | $15,000 |
| Oct 24, 2020 | Expired or cancelled cancelled Jan 2026 | 32 06th St | Wells Electrical, Inc | installing 4 anchors on the facade of 32-40 6th st. the anchors will hold marketlite professionally rated outdoor string lights with 3 ft in diameter lanterns. power will be sourced from 510 stevenson st.Details
installing 4 anchors on the facade of 32-40 6th st. the anchors will hold marketlite professionally rated outdoor string lights with 3 ft in diameter lanterns. power will be sourced from 510 stevenson st. | $13,000 |
| Mar 20, 2019 | Expired or cancelled cancelled Jan 2026 | 32 06th St | upgrade entrance door to meet ada. accessible business entrance program per ord. 51 16Details
upgrade entrance door to meet ada. accessible business entrance program per ord. 51 16 | $5,000 | |
| Dec 11, 2018 | Never finaled issued Dec 2018, no final | 32 06th St | street spaceDetails
street space | ||
| Nov 30, 2018 | Never finaled issued Nov 2018, no final | 32 06th St | street space & sidewalk repair w/mtaDetails
street space & sidewalk repair w/mta | ||
| Sep 27, 2018 | Never finaled filed Sep 2018, never issued | 40 06th St | exterior t.i.work only. existing ground fl storefront & storefront entry improvements. exterior replacement lighting, minor facade repairs & facade repainting @ new work only. new structural work, new electrical & lighting, t24 work. no mechanical workDetails
exterior t.i.work only. existing ground fl storefront & storefront entry improvements. exterior replacement lighting, minor facade repairs & facade repainting @ new work only. new structural work, new electrical & lighting, t24 work. no mechanical work | $42,000 | |
| Jun 27, 2018 | Expired or cancelled cancelled Jan 2026 | 40 06th St | grnd flr - ti - exterior & int improvvements. retail tenant unit. new storefron & entry door. new ext signage and lighting, new interior partitions and mezz (storage), new int finishes, new structural and ele wk. no mech work. under sep permit: signage, fire lifesafety/sprinkler modificationsDetails
grnd flr - ti - exterior & int improvvements. retail tenant unit. new storefron & entry door. new ext signage and lighting, new interior partitions and mezz (storage), new int finishes, new structural and ele wk. no mech work. under sep permit: signage, fire lifesafety/sprinkler modifications | $110,000 | |
| Feb 21, 2018 | Completed final sign-off Mar 2018 | 34 06th St | G C Builders | install or replace grab bars in shower tub bathroom in units 102, 203.Details
install or replace grab bars in shower tub bathroom in units 102, 203. | $3,000 |
| Jun 23, 2015 | Expired or cancelled cancelled Jan 2026 | 34 06th St | add bed bug treatment room in basement area with electric heating system.Details
add bed bug treatment room in basement area with electric heating system. | $9,000 | |
| Nov 6, 2014 | Completed final sign-off Mar 2015 | 32 06th St | Essa's Remodeling | legalization for perfect fry ki 2006 award.Details
legalization for perfect fry ki 2006 award. | |
| Jan 2, 2014 | Completed final sign-off Jan 2014 | 34 06th St | Occidental Express | replacing water damaged plaster on walls and ceiling in community lounge and kitchen with 5/8" type x drywall, approx 1000 sf.Details
replacing water damaged plaster on walls and ceiling in community lounge and kitchen with 5/8" type x drywall, approx 1000 sf. | $3,580 |
| Aug 1, 2013 | Completed final sign-off Aug 2013 | 34 06th St | Fire & Security & Alarm Co/ F.S.A.C. | emergency replacement of obsolete afp200 notifier panel with newest nfs-320 notifier panel on like for like basis at the same location on the ground floor in fully sprinklered building. all (e) devices remain as is & will be connect to new panel& monitoredDetails
emergency replacement of obsolete afp200 notifier panel with newest nfs-320 notifier panel on like for like basis at the same location on the ground floor in fully sprinklered building. all (e) devices remain as is & will be connect to new panel& monitored | $1,000 |
| Jun 3, 2013 | Completed final sign-off May 2014 | 34 06th St | comply with ordiance 029-13 only. installation of grab bars in sro at following locations. all common area bathrooms & toilet rooms (total of 40).Details
comply with ordiance 029-13 only. installation of grab bars in sro at following locations. all common area bathrooms & toilet rooms (total of 40). | $3,000 | |
| Jan 8, 2013 | Completed final sign-off Mar 2013 | 34 06th St | an extg library room on ground floor, build partial ht. partition with door to divide extg room into 2 offices. install accoustic ceiling tile, addtitional duplex outlets and ceiling fans.Details
an extg library room on ground floor, build partial ht. partition with door to divide extg room into 2 offices. install accoustic ceiling tile, addtitional duplex outlets and ceiling fans. | $4,000 | |
| Sep 12, 2012 | Completed final sign-off Oct 2012 | 34 06th St | comply with complaint #201237082/legalize front door replacement.Details
comply with complaint #201237082/legalize front door replacement. | $1,000 | |
| Jul 19, 2012 | Completed final sign-off Oct 2012 | 34 06th St | S F Garage Company Inc. | remove & replace (e) sub floor & tiles for second floor bathroom only. all work in kind.Details
remove & replace (e) sub floor & tiles for second floor bathroom only. all work in kind. | $1,500 |
| May 16, 2012 | Completed final sign-off Jun 2012 | 34 06th St | comply with nov # 201204741 legaliza interior counter security glazingDetails
comply with nov # 201204741 legaliza interior counter security glazing | $3,000 | |
| May 10, 2012 | Completed final sign-off Oct 2012 | 34 06th St | replace 2 king studs and 2 jack studs at doorway. work to address nov complaint #201213621. no structural work.Details
replace 2 king studs and 2 jack studs at doorway. work to address nov complaint #201213621. no structural work. | $500 | |
| Jan 15, 2010 | Completed final sign-off Feb 2010 | 32 06th St | Wong Ho Yu/Ho's Electric Co | shower stall repair, new tiles for floor & wall. no new lighting & structural workDetails
shower stall repair, new tiles for floor & wall. no new lighting & structural work | $1,500 |
| Jul 15, 2008 | Never finaled issued Jul 2008, no final | 32 06th St | S F Garage Company Inc. | renew pa# 2004/05/11/3567, pa# 2004/03/08/8056, pa# 2006/10/27/6224 & pa# 2006/01/19/2458 for final inspection only.Details
renew pa# 2004/05/11/3567, pa# 2004/03/08/8056, pa# 2006/10/27/6224 & pa# 2006/01/19/2458 for final inspection only. | |
| Jan 8, 2008 | Never finaled issued Jan 2008, no final | 34 06th St | street space permitDetails
street space permit | ||
| Sep 27, 2007 | Never finaled issued Sep 2007, no final | 34 06th St | street spaceDetails
street space | ||
| Aug 23, 2007 | Never finaled issued Aug 2007, no final | 34 06th St | street spaceDetails
street space | ||
| Aug 21, 2007 | Expired or cancelled cancelled Jan 2026 | 32 06th St | new non-illuminated 10'x8' sign on exterior - non-electric single faced wall sign 1" thick.Details
new non-illuminated 10'x8' sign on exterior - non-electric single faced wall sign 1" thick. | $1,700 | |
| May 22, 2007 | Never finaled issued May 2007, no final | 34 06th St | street spaceDetails
street space | ||
| Jan 19, 2007 | Never finaled issued Jan 2007, no final | 34 06th St | street spaceDetails
street space | ||
| Oct 27, 2006 | Expired or cancelled expired Dec 2007 | 32 06th St | renew pa# 2004/03/08/8056.Details
renew pa# 2004/03/08/8056. | $50,000 | |
| Jan 19, 2006 | Expired or cancelled expired Feb 2008 | 32 06th St | Occidental Express | retrofiting of (e) elevator shaft for proposed new repalcement elevator.Details
retrofiting of (e) elevator shaft for proposed new repalcement elevator. | $45,000 |
| Dec 9, 2005 | Never finaled issued Dec 2005, no final | 34 06th St | Fire & Security & Alarm Co/ F.S.A.C. | adding new devices to (e) fire alarm system at lobby and 1st floorDetails
adding new devices to (e) fire alarm system at lobby and 1st floor | $8,000 |
| Sep 1, 2005 | Expired or cancelled expired May 2006 | 34 06th St | K Y J Construction Company | extension of (e0 wet pipe fire spkr system to provide pendent heads at (n) ceilingsDetails
extension of (e0 wet pipe fire spkr system to provide pendent heads at (n) ceilings | $3,000 |
| Aug 1, 2005 | Completed final sign-off Mar 2006 | 34 06th St | eliminate trans window, wliminate the blake sign per pa 200502095136Details
eliminate trans window, wliminate the blake sign per pa 200502095136 | $150,000 | |
| Jun 7, 2005 | Completed final sign-off Jun 2006 | 32 06th St | Occidental Express | renew 200207242210Details
renew 200207242210 | |
| Feb 9, 2005 | Completed final sign-off Mar 2006 | 34 06th St | remodeling store front/convert bar into pizza restaurant. install type 11 hood for pizza oven.Details
remodeling store front/convert bar into pizza restaurant. install type 11 hood for pizza oven. | $56,000 | |
| May 11, 2004 | Expired or cancelled expired Nov 2007 | 34 06th St | provide accessible dwelling units and restrooms, new community kitchen, new tenant laundry,Details
provide accessible dwelling units and restrooms, new community kitchen, new tenant laundry, | $315,000 | |
| Mar 8, 2004 | Expired or cancelled expired Mar 2007 | 32 06th St | structural repair of exterior brick facadeDetails
structural repair of exterior brick facade | $100,000 | |
| Dec 10, 2003 | Completed final sign-off Mar 2005 | 32 06th St | Occidental Express | adding of manager's unit and accessible bathroom at ground flr levelDetails
adding of manager's unit and accessible bathroom at ground flr level | $18,000 |
| Jun 20, 2003 | Never finaled issued Jun 2003, no final | 32 06th St | street spaceDetails
street space | ||
| Dec 5, 2002 | Completed final sign-off Jan 2003 | 34 06th St | Kilcur Construction | sheetrock 5/8" type x trash room complete w/ sheet metal,replacing old lath & plaster.no change in wDetails
sheetrock 5/8" type x trash room complete w/ sheet metal,replacing old lath & plaster.no change in w | $7,000 |
| Jul 24, 2002 | Expired or cancelled expired Mar 2007 | 32 06th St | abandonment of a sub-sidewalk basement construction of a concrete retaining wall in basementDetails
abandonment of a sub-sidewalk basement construction of a concrete retaining wall in basement | $50,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Occidental Express (4), S F Garage Company Inc. (4), 4-Mac Construction (3), Fire & Security & Alarm Co/ F.S.A.C. (3), Pineda Construction Inc (3), Ambrocio Construction Inc, Essa's Remodeling, G C Builders, K Y J Construction Company, Kilcur Construction, San Francisco Fire Protection, Wells Electrical, Inc, Wong Ho Yu/Ho's Electric Co
- Architects
- Michael Steiner (2), Jim Foster
- Engineers
- Abdelkader Khelifa, Charles Ng
- Authorized agent-otherss
- Manuel Ambrocio
Find contractors for work like this