Block 3514, lot 030
1663 Mission St
- City’s use
- Commercial Retail
- Built
- 1925
- Stories
- 7
- Rooms
- 16 bathrooms
- Building
- 91,995 sq ft
- Lot
- 12,401 sq ft
- Zoning
- NCT3
- Construction type
- B
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
78 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| May 28, 2024 | In progress issued May 2024 | 1663 Mission St | Battalion One Fire Protection | fire only: work to include removing existing sidewall sprinkler that is above the elevator and add new pendant sprinkler on one newly constructed ceiling.Details
fire only: work to include removing existing sidewall sprinkler that is above the elevator and add new pendant sprinkler on one newly constructed ceiling. | $6,800 |
| Jan 22, 2024 | In progress filed Jan 2024, not yet issued | 1663 Mission St | Martin Sign Co Inc. | 1- painted wall sign " san francisco casa help foster children.com"Details
1- painted wall sign " san francisco casa help foster children.com" | $18,000 |
| Dec 29, 2023 | Completed final sign-off Apr 2024 | 1663 Mission St | Modern Construction Inc | 7th fl, ste 700 - add mechanical & electrical title 24 to pa 202311140802Details
7th fl, ste 700 - add mechanical & electrical title 24 to pa 202311140802 | |
| Nov 14, 2023 | Completed final sign-off Apr 2024 | 1663 Mission St | Modern Construction Inc | 7th flr. remove existing walls. install new walls, doors and glazing. minor mechanical and electrical work under separate permit.Details
7th flr. remove existing walls. install new walls, doors and glazing. minor mechanical and electrical work under separate permit. | $55,000 |
| Oct 17, 2023 | In progress issued Jan 2024 | 1663 Mission St | Modern Construction Inc | new ceiling, lighting, and millwork at building lobby.Details
new ceiling, lighting, and millwork at building lobby. | $115,000 |
| May 8, 2023 | Completed final sign-off Oct 2023 | 1663 Mission St | Battalion One Fire Protection | to replace an existing failed fire pump with a new fire pump due to the age of the equipment. a new jockey pump is being provided as well along with new controllers for both pumps.Details
to replace an existing failed fire pump with a new fire pump due to the age of the equipment. a new jockey pump is being provided as well along with new controllers for both pumps. | $34,938 |
| Dec 9, 2021 | Never finaled issued Dec 2021, no final | 1663 Mission St | Innovative Technologies | suite 305: relocate of one strobe in renovated office space.Details
suite 305: relocate of one strobe in renovated office space. | $500 |
| Mar 12, 2021 | Never finaled issued May 2021, no final | 1663 Mission St | Modern Construction Inc | ste 305/320. add mechanical engineering to pa# 202010206985.Details
ste 305/320. add mechanical engineering to pa# 202010206985. | $2,500 |
| Feb 18, 2021 | Completed final sign-off Apr 2021 | 1663 Mission St | Project Contractor Inc | modify of sprinklers system to accomodate app# 2020-1020-6985 per nfpa 13 total = relocate (3), add (1) & remove (1) sprinkler headsDetails
modify of sprinklers system to accomodate app# 2020-1020-6985 per nfpa 13 total = relocate (3), add (1) & remove (1) sprinkler heads | $2,500 |
| Oct 20, 2020 | Never finaled issued Feb 2021, no final | 1663 Mission St | Modern Construction Inc | 3rd floor - suite 305/320: construct new wall, door & sidelight. install new light for the new office rooms. no exterior work, no change of use as defined by planning code.Details
3rd floor - suite 305/320: construct new wall, door & sidelight. install new light for the new office rooms. no exterior work, no change of use as defined by planning code. | $42,000 |
| Jan 14, 2020 | Expired or cancelled cancelled Jan 2026 | 1663 Mission St | install security gate at transformer accessDetails
install security gate at transformer access | $15,000 | |
| Aug 21, 2019 | Never finaled issued Aug 2019, no final | 1663 Mission St | street spaceDetails
street space | ||
| May 9, 2019 | Never finaled issued May 2019, no final | 1663 Mission St | Battalion One Fire Protection | fire sprinkler modifications for installation of new electrical vault. 30 new sprinklers maher naDetails
fire sprinkler modifications for installation of new electrical vault. 30 new sprinklers maher na | $30,000 |
| Mar 1, 2019 | Never finaled issued Mar 2019, no final | 1663 Mission St | street spaceDetails
street space | ||
| Feb 15, 2019 | Completed final sign-off Apr 2019 | 1663 Mission St | Modern Construction Inc | suite #602 on 6th fl: removing existing partition wall, door, casework & furniture. construction new partition wall, door & casework. maher n/a.Details
suite #602 on 6th fl: removing existing partition wall, door, casework & furniture. construction new partition wall, door & casework. maher n/a. | $20,000 |
| Dec 14, 2018 | Completed final sign-off Feb 2019 | 1663 Mission St | Modern Construction Inc | unit 720. construct new wall, glass wall and door in open officeDetails
unit 720. construct new wall, glass wall and door in open office | $35,000 |
| Aug 30, 2018 | Completed final sign-off Nov 2018 | 1663 Mission St | Modern Construction Inc | demo interior wall to construct new walls, doors, sidelight and install cabinet with sink, new lighting and power outlet. approx 2600 sq ft, arch and elec set. fire under separate permitsDetails
demo interior wall to construct new walls, doors, sidelight and install cabinet with sink, new lighting and power outlet. approx 2600 sq ft, arch and elec set. fire under separate permits | $120,000 |
| Aug 7, 2018 | Completed final sign-off Aug 2018 | 1663 Mission St | Modern Construction Inc | replace (e) air duct with same size, extend partial air duct to new air registers. rev. to appt #201706300852. existing unit to remain.Details
replace (e) air duct with same size, extend partial air duct to new air registers. rev. to appt #201706300852. existing unit to remain. | $2,500 |
| Aug 8, 2017 | Never finaled issued Sep 2018, no final | 1663 Mission St | this project is to upgrade electrical service to the building. remove interior & exterior walls & doors. construct new vault & associated electrical roomsDetails
this project is to upgrade electrical service to the building. remove interior & exterior walls & doors. construct new vault & associated electrical rooms | $1,000,000 | |
| Jul 13, 2017 | Completed final sign-off Sep 2017 | 1663 Mission St | Golden State Plumbing | remove 9 sprinklers & add 12 sprinklers per nfpa 13. ref pa 2017-0630-0852Details
remove 9 sprinklers & add 12 sprinklers per nfpa 13. ref pa 2017-0630-0852 | $5,000 |
| Jun 30, 2017 | Completed final sign-off Aug 2018 | 1663 Mission St | Modern Construction Inc | 4/f: remove part of (e) interior partition wall and construction of new partition per layout plan. install new lighting and outlets, minor a/c duct work modification.Details
4/f: remove part of (e) interior partition wall and construction of new partition per layout plan. install new lighting and outlets, minor a/c duct work modification. | $180,000 |
| Nov 7, 2016 | Completed final sign-off Mar 2017 | 1663 Mission St | Modern Construction Inc | #400: remove existing walls, door, and finishes, construct new walls, doors, sidelights and install new finishes; no mechanical. maher n/aDetails
#400: remove existing walls, door, and finishes, construct new walls, doors, sidelights and install new finishes; no mechanical. maher n/a | $85,000 |
| Nov 13, 2015 | Completed final sign-off Jan 2016 | 1663 Mission St | Precision Design & Drafting Inc | remove all towerstream wifi antennas and associated equipment on rooftop. patch in-kind surfaces after removal.Details
remove all towerstream wifi antennas and associated equipment on rooftop. patch in-kind surfaces after removal. | $500 |
| Sep 3, 2015 | Never finaled issued Sep 2015, no final | 1663 Mission St | Modern Construction Inc | 2nd flr: remove extg partition walls, door and finishes. construct new partition walls, doors, sidelight and install new finish and outlets. revision to app#201502249187. n/a maher.Details
2nd flr: remove extg partition walls, door and finishes. construct new partition walls, doors, sidelight and install new finish and outlets. revision to app#201502249187. n/a maher. | $60,000 |
| Apr 27, 2015 | Completed final sign-off Jul 2015 | 1663 Mission St | Modern Construction Inc | 2nd flr - suite 250: remove (e) walls, doors and finishes. construct new walls, doors, sidelights and install new finishes. mep, f/a, sprinklers under separate permit. maher naDetails
2nd flr - suite 250: remove (e) walls, doors and finishes. construct new walls, doors, sidelights and install new finishes. mep, f/a, sprinklers under separate permit. maher na | $42,000 |
| Feb 24, 2015 | Completed final sign-off Mar 2015 | 1663 Mission St | Modern Construction Inc | remove walls, doors and finishes. construct bew walls, doors and sidelights. install new finishes maher - not req'dDetails
remove walls, doors and finishes. construct bew walls, doors and sidelights. install new finishes maher - not req'd | $43,270 |
| Feb 24, 2015 | Never finaled issued Feb 2015, no final | 1663 Mission St | Modern Construction Inc | remove walls, doors and finishes, construct new wall, door and sidelight. nistall new finishes, replace (e) sink and cabinets. maher - not req'dDetails
remove walls, doors and finishes, construct new wall, door and sidelight. nistall new finishes, replace (e) sink and cabinets. maher - not req'd | $64,750 |
| Oct 21, 2014 | Never finaled issued Oct 2014, no final | 1663 Mission St | streetspaceDetails
streetspace | ||
| Aug 12, 2014 | Completed final sign-off Sep 2014 | 1663 Mission St | Modern Construction Inc | #320 - revision to appl #2014.0603.7380: revision to the original plan - build additional office room. n/a maher ordinanceDetails
#320 - revision to appl #2014.0603.7380: revision to the original plan - build additional office room. n/a maher ordinance | $5,000 |
| Jul 15, 2014 | Never finaled issued Jul 2014, no final | 1663 Mission St | street spaceDetails
street space | ||
| Jul 7, 2014 | Completed final sign-off May 2015 | 1665 Mission St | Battalion One Fire Protection | relocate 2 sprinklers and 4 sprinklers for remodel of front retail space showroom. n/a for the maher ordinance #155-13. t.i app#201406027246Details
relocate 2 sprinklers and 4 sprinklers for remodel of front retail space showroom. n/a for the maher ordinance #155-13. t.i app#201406027246 | $12,000 |
| Jul 1, 2014 | Never finaled issued Jul 2014, no final | 1663 Mission St | street spaceDetails
street space | ||
| Jun 3, 2014 | Completed final sign-off Sep 2014 | 1663 Mission St | Modern Construction Inc | #320- remove partition walls and door, construct new walls, doors and side lights, relocate lights. n/a ordinance #155-13Details
#320- remove partition walls and door, construct new walls, doors and side lights, relocate lights. n/a ordinance #155-13 | $42,000 |
| Jun 2, 2014 | Completed final sign-off Dec 2014 | 1665 Mission St | Riggs Construction | ground floor tenant improvement for appliance display. lighting power, floor finish, wall finish. compliance with ordinance no 155-13 not required.Details
ground floor tenant improvement for appliance display. lighting power, floor finish, wall finish. compliance with ordinance no 155-13 not required. | $30,000 |
| May 6, 2014 | Never finaled issued May 2014, no final | 1663 Mission St | street space permit (renewal of permit #m473807)Details
street space permit (renewal of permit #m473807) | ||
| Mar 24, 2014 | Never finaled issued Mar 2014, no final | 1663 Mission St | street space permitDetails
street space permit | ||
| Mar 4, 2014 | Completed final sign-off Apr 2014 | 1663 Mission St | Modern Construction Inc | 6th floor suite 604 - construct new walls, door, sidelight & new finish. install power outlets. compliance with ordinance #155-13 not requiredDetails
6th floor suite 604 - construct new walls, door, sidelight & new finish. install power outlets. compliance with ordinance #155-13 not required | $10,000 |
| Dec 17, 2013 | Completed final sign-off Aug 2018 | 1663 Mission St | Modern Construction Inc | #504- install new sidelights, drywall, paint and carpet. comply with pid nov # 200993146. sprinklers under seperate permit.Details
#504- install new sidelights, drywall, paint and carpet. comply with pid nov # 200993146. sprinklers under seperate permit. | $20,000 |
| Dec 17, 2013 | Completed final sign-off Jan 2014 | 1663 Mission St | Modern Construction Inc | #310- build new break area, door, paint and new floor finishes, install new cabinets. comply with pid nov # 200993146Details
#310- build new break area, door, paint and new floor finishes, install new cabinets. comply with pid nov # 200993146 | $33,000 |
| Nov 12, 2013 | Completed final sign-off Dec 2013 | 1663 Mission St | Steven Yeung Inc Dba Chung Wah Plbg&Fire | 7th floor: add 4 sprinkler heads. move one sprinkler head. t i app#201309237516Details
7th floor: add 4 sprinkler heads. move one sprinkler head. t i app#201309237516 | $2,500 |
| Oct 8, 2013 | Never finaled issued Oct 2013, no final | 1663 Mission St | Modern Construction Inc | install furnace and ductwork. ref 201309237516Details
install furnace and ductwork. ref 201309237516 | $7,500 |
| Oct 1, 2013 | Completed final sign-off Dec 2013 | 1663 Mission St | Innovative Technologies | modification of previously approved fire alarm permit, app# 201003118029. addition of 1 strobe in the conference room suite 710. permit issued w/out plansDetails
modification of previously approved fire alarm permit, app# 201003118029. addition of 1 strobe in the conference room suite 710. permit issued w/out plans | $500 |
| Sep 23, 2013 | Completed final sign-off Dec 2013 | 1663 Mission St | Modern Construction Inc | new walls, plumbing, power lights, doors, sidelites, new finishes at 710. mep under separate permit sprinkler and fire alarm under separate permit if neededDetails
new walls, plumbing, power lights, doors, sidelites, new finishes at 710. mep under separate permit sprinkler and fire alarm under separate permit if needed | $132,800 |
| Aug 12, 2013 | Never finaled issued Aug 2013, no final | 1663 Mission St | Modern Construction Inc | #525- remove partition walls, construct new partial height walls, build cabinets & sink for breakroom, replace carpet, new paint.Details
#525- remove partition walls, construct new partial height walls, build cabinets & sink for breakroom, replace carpet, new paint. | $41,000 |
| May 20, 2013 | Completed final sign-off Jun 2013 | 1663 Mission St | Modern Construction Inc | mezzanine - remove wall & doors, construct new wall & doors.Details
mezzanine - remove wall & doors, construct new wall & doors. | $15,000 |
| May 2, 2013 | Completed final sign-off Jun 2013 | 1663 Mission St | Modern Construction Inc | construct new wall, install new carpet and paint and build breakroom with sinkDetails
construct new wall, install new carpet and paint and build breakroom with sink | $5,000 |
| Apr 26, 2013 | Never finaled filed Apr 2013, never issued | 1663 Mission St | to comply w/ nov. installation of 7 towerstream wifi antennas on rooftop & one equipment cabinet (29.2 x 26.4 x 8.5") on interior stairwell wall & associated cables. drawings to follow (approved by ed sweeney)Details
to comply w/ nov. installation of 7 towerstream wifi antennas on rooftop & one equipment cabinet (29.2 x 26.4 x 8.5") on interior stairwell wall & associated cables. drawings to follow (approved by ed sweeney) | $5,000 | |
| Feb 19, 2013 | Completed final sign-off Apr 2013 | 1663 Mission St | Battalion One Fire Protection | suite 602 - addition of 2 strobe appliances for fire alarm.Details
suite 602 - addition of 2 strobe appliances for fire alarm. | $2,800 |
| Dec 20, 2012 | Completed final sign-off Dec 2012 | 1663 Mission St | Modern Construction Inc | 3rd floor #330 - build partition wall, paint interior & replace carpet.Details
3rd floor #330 - build partition wall, paint interior & replace carpet. | $5,000 |
| Jun 21, 2012 | Completed final sign-off Nov 2018 | 1663 Mission St | Battalion One Fire Protection | install emergency evacuation sign.Details
install emergency evacuation sign. | $3,000 |
| Feb 3, 2012 | Completed final sign-off Feb 2012 | 1663 Mission St | Battalion One Fire Protection | 6th floor:modify extg fire protection sprnklr and piping layout to accmodate the new walls sprinklers will be removed,added and relocated to provide accurate coverage work to be done at 1663 mission only.Details
6th floor:modify extg fire protection sprnklr and piping layout to accmodate the new walls sprinklers will be removed,added and relocated to provide accurate coverage work to be done at 1663 mission only. | $4,500 |
| Jan 5, 2012 | Expired or cancelled cancelled Jul 2023 | 1663 Mission St | Battalion One Fire Protection | revisions to existing sprinkler system to make the building fully sprinklered for high rise sprinkler ordinance compliance requirements. ordinance #377-93. end goal: 2.08 retro sprinkler installation for high-rise umbrella permit under separate application later.Details
revisions to existing sprinkler system to make the building fully sprinklered for high rise sprinkler ordinance compliance requirements. ordinance #377-93. end goal: 2.08 retro sprinkler installation for high-rise umbrella permit under separate application later. | $25,000 |
| Dec 15, 2011 | Never finaled issued Jan 2012, no final | 1663 Mission St | Modern Construction Inc | remove existing walls, doors, and finishes, construct new walls, doors, and new finishes.Details
remove existing walls, doors, and finishes, construct new walls, doors, and new finishes. | $35,000 |
| Aug 23, 2011 | Completed final sign-off Sep 2011 | 1663 Mission St | Innovative Technologies | unit # 400:connect 2 extg duct smoke detectors to extg fire alarm system.Details
unit # 400:connect 2 extg duct smoke detectors to extg fire alarm system. | $1,000 |
| May 31, 2011 | Completed final sign-off Jan 2012 | 1663 Mission St | Modern Construction Inc | #400: construct new walls (partitions), install doors & sidelite. install/replace kitchenette, relocate sinks & toiletsDetails
#400: construct new walls (partitions), install doors & sidelite. install/replace kitchenette, relocate sinks & toilets | $40,000 |
| Apr 5, 2011 | Never finaled issued Apr 2011, no final | 1663 Mission St | Modern Construction Inc | suite 320: construct new walls (partition) new doors, side lite. new kitchenetteDetails
suite 320: construct new walls (partition) new doors, side lite. new kitchenette | $35,000 |
| Aug 23, 2010 | Expired or cancelled cancelled Jan 2026 | 1663 Mission St | demolition of existing walls & doors. construction of new walls & doors. work occurs on the 1st floor & basement. this work is to install a new electrical vault to service this building.Details
demolition of existing walls & doors. construction of new walls & doors. work occurs on the 1st floor & basement. this work is to install a new electrical vault to service this building. | $100,000 | |
| Apr 29, 2010 | Completed final sign-off May 2010 | 1663 Mission St | Steven Yeung Inc Dba Chung Wah Plbg&Fire | move sprinkler heads and add sprinkler heads for new floor plan. 21 headsDetails
move sprinkler heads and add sprinkler heads for new floor plan. 21 heads | $4,000 |
| Mar 11, 2010 | Completed final sign-off May 2010 | 1663 Mission St | Innovative Technologies | install fire alarm system notification devices on the 7th floorDetails
install fire alarm system notification devices on the 7th floor | $700 |
| Feb 24, 2010 | Completed final sign-off May 2010 | 1663 Mission St | Modern Construction Inc | 7th floor work consists of minor demolition & construction as follows: remove exisitng walls, doors & finish, construct new walls, door, sidelights & install new finishes.Details
7th floor work consists of minor demolition & construction as follows: remove exisitng walls, doors & finish, construct new walls, door, sidelights & install new finishes. | $85,000 |
| Jun 3, 2008 | Completed final sign-off Jul 2008 | 1663 Mission St | Modern Construction Inc | 5th floor #501 - tenant improvement, add 3 walls, new electrical and telephone wiring.Details
5th floor #501 - tenant improvement, add 3 walls, new electrical and telephone wiring. | $6,000 |
| Aug 2, 2007 | Completed final sign-off Nov 2007 | 1663 Mission St | Ben & Ken Construction ***See Note** | upgrade of bathroom improvements and ada compliance on the 4th floor. mep under separate permitDetails
upgrade of bathroom improvements and ada compliance on the 4th floor. mep under separate permit | $30,000 |
| Feb 9, 2007 | Never finaled issued Feb 2007, no final | 1663 Mission St | street space & sidewalkDetails
street space & sidewalk | ||
| Nov 14, 2006 | Completed final sign-off Feb 2007 | 1665 Mission St | Walters Construction | oti-1 3/f el me ls spDetails
oti-1 3/f el me ls sp | $8,500 |
| Nov 4, 2004 | Expired or cancelled expired Jul 2006 | 667 Mission St | Rossi Builders Inc. | change configuration of level 1 lobby, new ceiliing, new wallsDetails
change configuration of level 1 lobby, new ceiliing, new walls | $19,379 |
| Mar 29, 2004 | Completed final sign-off Jul 2004 | 667 Mission St | Zebra Awning Co Inc | non electric projecting single-faced painted wallDetails
non electric projecting single-faced painted wall | |
| Apr 30, 2003 | Completed final sign-off Dec 2003 | 667 Mission St | remove existing windows from west exterior wall and fill in openings with 4 hr rated closureDetails
remove existing windows from west exterior wall and fill in openings with 4 hr rated closure | $38,000 | |
| Sep 5, 2001 | Completed final sign-off Feb 2002 | 667 Mission St | Peacock Construction Inc | oti-1 2nd fl ltg,mech,ls,Details
oti-1 2nd fl ltg,mech,ls, | $200,000 |
| Sep 5, 2001 | Completed final sign-off Feb 2002 | 667 Mission St | Peacock Construction Inc | oti-2 2nd fl el, meDetails
oti-2 2nd fl el, me | $140,000 |
| Jul 26, 2001 | Completed final sign-off Feb 2002 | 667 Mission St | Peacock Construction Inc | demo dry wall & acoustical ceiling at 3rd floorDetails
demo dry wall & acoustical ceiling at 3rd floor | $9,200 |
| Jul 26, 2001 | Completed final sign-off Feb 2002 | 667 Mission St | Peacock Construction Inc | demo dry wall & acoustical ceilings 2nd floorDetails
demo dry wall & acoustical ceilings 2nd floor | $9,200 |
| Apr 3, 2001 | Completed final sign-off Jun 2001 | 667 Mission St | Pacific Auxiliary Fire Alarm | adding to extg fire alarm system fodr new tenant impr. on the 4th floorDetails
adding to extg fire alarm system fodr new tenant impr. on the 4th floor | $13,000 |
| Mar 13, 2001 | Completed final sign-off Jun 2001 | 667 Mission St | Chen's Plumbing Inc | replace & add new sprinkler heads to (e) systemDetails
replace & add new sprinkler heads to (e) system | $4,000 |
| Mar 9, 2001 | Completed final sign-off Jun 2001 | 667 Mission St | Rossi Builders Inc. | revision to 200101039058 & 200101039063: oti-1=el, me, ls & sp (4th fl only)Details
revision to 200101039058 & 200101039063: oti-1=el, me, ls & sp (4th fl only) | $7,000 |
| Mar 9, 2001 | Completed final sign-off Jun 2001 | 667 Mission St | Rossi Builders Inc. | revision to 200101039058 & 200101039063: oti-2= (4th fl) el onlyDetails
revision to 200101039058 & 200101039063: oti-2= (4th fl) el only | $7,000 |
| Jan 3, 2001 | Completed final sign-off Jun 2001 | 667 Mission St | Rossi Builders Inc. | oti-2 4th floor, el, meDetails
oti-2 4th floor, el, me | $150,000 |
| Jan 3, 2001 | Completed final sign-off Jun 2001 | 667 Mission St | Rossi Builders Inc. | interior demo on 4th fl.Details
interior demo on 4th fl. | $11,000 |
| Jan 3, 2001 | Completed final sign-off Jun 2001 | 667 Mission St | Rossi Builders Inc. | oti-1, 4th floor, el, me, ls, sp.Details
oti-1, 4th floor, el, me, ls, sp. | $300,000 |