Block 1198, lot 022
524 Central Ave
- City’s use
- Multi-Family Residential
- Built
- 1925
- Stories
- 2
- Units
- 4
- Rooms
- 4 bathrooms
- Building
- 3,440 sq ft
- Lot
- 2,500 sq ft
- Zoning
- RH3
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
20 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jan 23, 2026 | In progress issued Feb 2026 | 524 Central Av | revision to pa 202404260881 remove structural work @ 3rd fl front unit; front unit layout to remain unchanged. structural work removed was approved under voluntary seismic strengthening, ref (202404260881 and 202111303291)Details
revision to pa 202404260881 remove structural work @ 3rd fl front unit; front unit layout to remain unchanged. structural work removed was approved under voluntary seismic strengthening, ref (202404260881 and 202111303291) | ||
| Oct 15, 2025 | In progress issued Oct 2025 | 524 Central Av | recommencement and completion of work approved under pa#2018-0417-6634 & pa#2021-1130-3291 & pa#2024-0426-0881.Details
recommencement and completion of work approved under pa#2018-0417-6634 & pa#2021-1130-3291 & pa#2024-0426-0881. | ||
| Oct 15, 2025 | In progress issued Oct 2025 | 524 Central Av | to obtain a final inspection for work approved under pa#2023-0815-4466Details
to obtain a final inspection for work approved under pa#2023-0815-4466 | ||
| Sep 23, 2025 | In progress issued Feb 2026 | 524 Central Av | revision to pa #2018-1221-9017. to change a.o.r and to address discrepancies between approved plans and as built conditions. foundation revision to match field condition.Details
revision to pa #2018-1221-9017. to change a.o.r and to address discrepancies between approved plans and as built conditions. foundation revision to match field condition. | ||
| Jan 7, 2025 | Completed final sign-off Dec 2025 | 524 Central Av | to obtain final inspection for work approved under pa 201907186280. all work is completeDetails
to obtain final inspection for work approved under pa 201907186280. all work is complete | ||
| Dec 10, 2024 | In progress issued Jul 2025 | 524 Central Av | Hue & Cry Security System | installation of new fire alarm system. installing low frequency horns in all sleeping areas to meet code 1103.7.6.1. pull stations at all egress exist doors. smoke and notification within all common areas. cell communicator for monitoring.Details
installation of new fire alarm system. installing low frequency horns in all sleeping areas to meet code 1103.7.6.1. pull stations at all egress exist doors. smoke and notification within all common areas. cell communicator for monitoring. | $22,955 |
| Aug 23, 2024 | In progress issued Dec 2024 | 524 Central Av | restore stucco on front facade. replace dipapicated lap siding on sides and rear.Details
restore stucco on front facade. replace dipapicated lap siding on sides and rear. | $100,000 | |
| Jul 25, 2024 | In progress issued Jul 2024 | 524 Central Av | unit #4: revision to bpa# 202111303291: reduce scope of work in unit #4, no kitchen remodel, no full interior remodel. one bath remodel only. keep structural works for the bldg.Details
unit #4: revision to bpa# 202111303291: reduce scope of work in unit #4, no kitchen remodel, no full interior remodel. one bath remodel only. keep structural works for the bldg. | ||
| Apr 26, 2024 | In progress issued Apr 2024 | 524 Central Av | change of engineer of record & new engineer design ref pa# 202111303291Details
change of engineer of record & new engineer design ref pa# 202111303291 | ||
| Aug 15, 2023 | Never finaled issued Aug 2023, no final | 524 Central Av | Best Way Mechanical Inc | install new fire sprinkler system for entire building.Details
install new fire sprinkler system for entire building. | $35,000 |
| Dec 22, 2021 | Never finaled issued Dec 2021, no final | 524 Central Av | recommencement & completion of work under pa #201804176634 & pa #201907186280.Details
recommencement & completion of work under pa #201804176634 & pa #201907186280. | $25,000 | |
| Nov 30, 2021 | Never finaled issued Dec 2021, no final | 524 Central Av | revision 201804176634: interior remodel of 4 e units 2nd and 3rd fl . remove and replace e windows on upper floor at side and rear, new hydronic base board radiiators and boiler voountary seismic upgradeDetails
revision 201804176634: interior remodel of 4 e units 2nd and 3rd fl . remove and replace e windows on upper floor at side and rear, new hydronic base board radiiators and boiler voountary seismic upgrade | $60,000 | |
| Aug 24, 2020 | Expired or cancelled withdrawn Nov 2021 | 524 Central Av | interior remodel for 4 existing residential units on 2nd & 3rd floors. remove or replace (e) windows on upper floors at side & rear elevations only. no changes to street facing facade. new hydronic baseboard radiators and new boilers.Details
interior remodel for 4 existing residential units on 2nd & 3rd floors. remove or replace (e) windows on upper floors at side & rear elevations only. no changes to street facing facade. new hydronic baseboard radiators and new boilers. | $200,000 | |
| Jul 18, 2019 | Expired or cancelled expired Dec 2025 | 524 Central Av | replacement of (e) windows in-kind (same size as existing windows) to bring up to current compliance requirements.Details
replacement of (e) windows in-kind (same size as existing windows) to bring up to current compliance requirements. | $6,000 | |
| Feb 13, 2019 | Completed final sign-off Oct 2019 | 524 Central Av | to comply w/ complaint 201928381 dated 2/12/2019 repaired exterior wood stairs due to dryrot and severe damage from tenant less than 50 % in kind repair work.Details
to comply w/ complaint 201928381 dated 2/12/2019 repaired exterior wood stairs due to dryrot and severe damage from tenant less than 50 % in kind repair work. | $3,000 | |
| Feb 11, 2019 | Expired or cancelled cancelled Oct 2021 | 524 Central Av | apt #1: remodel 1 bathroom & 1 kitchen unit #1. approx 170 sq ft totalDetails
apt #1: remodel 1 bathroom & 1 kitchen unit #1. approx 170 sq ft total | $25,000 | |
| Dec 21, 2018 | Never finaled issued Jun 2020, no final | 524 Central Av | conversion of (e) garage to single dwelling unit (adu) per ord#162-16. minor structural alteration, (n) non-bearing walls, minor alteration to front & rear facades, (n) mech & elect improvements to accomodate (n) residential unit. maher n/a.Details
conversion of (e) garage to single dwelling unit (adu) per ord#162-16. minor structural alteration, (n) non-bearing walls, minor alteration to front & rear facades, (n) mech & elect improvements to accomodate (n) residential unit. maher n/a. | $85,000 | |
| Apr 17, 2018 | Never finaled issued Apr 2018, no final | 524 Central Av | remodel 2 bathroom & 2 kitchens. total in unit 2 & 3 in kind. no moving of doors or walls. maher naDetails
remodel 2 bathroom & 2 kitchens. total in unit 2 & 3 in kind. no moving of doors or walls. maher na | $31,000 | |
| Mar 6, 2018 | Completed final sign-off Mar 2018 | 524 Central Av | Top2 Builders Corporation | replace 1,800 sq. ft. of roof plywood for reroof, no structural changes, 1/2" plywood. maher n/aDetails
replace 1,800 sq. ft. of roof plywood for reroof, no structural changes, 1/2" plywood. maher n/a | $2,000 |
| Mar 6, 2018 | Completed final sign-off Mar 2018 | 524 Central Av | Top2 Builders Corporation | re-roofingDetails
re-roofing | $9,000 |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover apartment buildings like this one.