Block 0446, lot 002
15 Marina Blvd
- City’s use
- Commercial Retail
- Built
- 1959
- Stories
- 1
- Units
- 1
- Rooms
- 2 bathrooms
- Building
- 40,212 sq ft
- Lot
- 78,373 sq ft
- Zoning
- NCS
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
33 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Feb 8, 2023 | Completed final sign-off Sep 2024 | 15 Marina Bl | High Band Construction Inc | at&t mobility unmanned telecom facility modification consisting remove & replace (3) (e) omi antennas, install new rf safety signs & stripping install (2) new rrus at equipment area install back-to-back rru mount on (e) unistruct at equipment area and (6) new 1/2" coax cablesDetails
at&t mobility unmanned telecom facility modification consisting remove & replace (3) (e) omi antennas, install new rf safety signs & stripping install (2) new rrus at equipment area install back-to-back rru mount on (e) unistruct at equipment area and (6) new 1/2" coax cables | $25,000 |
| Jan 27, 2022 | Completed final sign-off Oct 2022 | 15 Marina Bl | Eric F Anderson Incorporated | complete remodel of (e) grocery store. fire alarm/life safety/sprinkler under separate permits.Details
complete remodel of (e) grocery store. fire alarm/life safety/sprinkler under separate permits. | $2,100,000 |
| Dec 23, 2021 | Expired or cancelled withdrawn Jan 2022 | 15 Marina Bl | Eric F Anderson Incorporated | full store remodel of existing space.Details
full store remodel of existing space. | $1,000,000 |
| Mar 24, 2021 | Never finaled issued Apr 2021, no final | 15 Marina Bl | Golden Gate Sign Company Inc. | install 6 signs. non-electric. ground. single faced. 6 sqft. (drive up & go pickup)Details
install 6 signs. non-electric. ground. single faced. 6 sqft. (drive up & go pickup) | $2,200 |
| Mar 24, 2021 | Never finaled issued Apr 2021, no final | 15 Marina Bl | Golden Gate Sign Company Inc. | install 1 sign. non-electric. ground. single faced. 3 sqft. (drive up & go pickup)Details
install 1 sign. non-electric. ground. single faced. 3 sqft. (drive up & go pickup) | $2,200 |
| Mar 24, 2021 | Never finaled issued Apr 2021, no final | 15 Marina Bl | Golden Gate Sign Company Inc. | install/paint 6 signs. non-electric. ground. painted on ground. 38 sqft. (online orders)Details
install/paint 6 signs. non-electric. ground. painted on ground. 38 sqft. (online orders) | $2,200 |
| Nov 12, 2020 | Never finaled issued Jan 2021, no final | 15 Marina Bl | T P C Construction Services Inc | interior renovations to provide a warming unit & a temperature controlled grocery lockers unitDetails
interior renovations to provide a warming unit & a temperature controlled grocery lockers unit | $30,000 |
| Aug 27, 2020 | Completed final sign-off Apr 2021 | 15 Marina Bl | Ericsson Inc Dba E U S Inc | at&t modification: remove (2) (e) omni antennas; install (2) (n) omni antennas; remove (4)(n) rrus; install (2)(n) rrus; no proposed chagne to (e) batteries.Details
at&t modification: remove (2) (e) omni antennas; install (2) (n) omni antennas; remove (4)(n) rrus; install (2)(n) rrus; no proposed chagne to (e) batteries. | $13,000 |
| May 7, 2019 | Completed final sign-off Jul 2019 | 15 Marina Bl | La Roza Construction Inc | install new 4 block refrigerator case in reatail area.Details
install new 4 block refrigerator case in reatail area. | $12,000 |
| Sep 13, 2018 | Expired or cancelled cancelled Jan 2026 | 15 Marina Bl | installtion of new refrigerated case, freezer case, hot holding cabinet and shelving unit in retail areaDetails
installtion of new refrigerated case, freezer case, hot holding cabinet and shelving unit in retail area | $10,000 | |
| Mar 30, 2018 | Completed final sign-off Sep 2019 | 15 Marina Bl | Electric Tech Construction Inc | at&t wireless install 1 new bmni antenna. r&r equipment as necessary, remove 1 rrus & replace with (1) rru-32 b66, install (2) 1/2" coax for antenna, swap (e) tdma cabinets for purcell, install 5216 unit in purcell, install (2) triplexers, remove cabinets & replace co/power plant, install (1) dc6.Details
at&t wireless install 1 new bmni antenna. r&r equipment as necessary, remove 1 rrus & replace with (1) rru-32 b66, install (2) 1/2" coax for antenna, swap (e) tdma cabinets for purcell, install 5216 unit in purcell, install (2) triplexers, remove cabinets & replace co/power plant, install (1) dc6. | $15,000 |
| Mar 2, 2018 | Never finaled issued Mar 2018, no final | 15 Marina Bl | Eric F Anderson Incorporated | tenant improvement to consist of replacing (2) refrigerated cases in the meat/seafood department. removing an ice machine. n/a maherDetails
tenant improvement to consist of replacing (2) refrigerated cases in the meat/seafood department. removing an ice machine. n/a maher | $40,000 |
| Mar 31, 2017 | Never finaled issued Mar 2017, no final | 15 Marina Bl | California Fire Systems Inc | relocate 3, and plug 1 fir sprinkler in new produce work area. ref 201605258236 maher naDetails
relocate 3, and plug 1 fir sprinkler in new produce work area. ref 201605258236 maher na | $4,000 |
| May 25, 2016 | Completed final sign-off May 2017 | 15 Marina Bl | Tilton Pacific Const Inc. | interior remodel of produce prep area with the installation of 3 pieces of equipment on the retail floor.Details
interior remodel of produce prep area with the installation of 3 pieces of equipment on the retail floor. | $40,000 |
| Dec 18, 2013 | Completed final sign-off Jan 2014 | 15 Marina Bl | Eric F Anderson Incorporated | revision to appl #2013.09.17.7037 - revise accessible hi-low drinking fountain location from previously permitted drawings.Details
revision to appl #2013.09.17.7037 - revise accessible hi-low drinking fountain location from previously permitted drawings. | |
| Sep 17, 2013 | Completed final sign-off Jan 2014 | 15 Marina Bl | Eric F Anderson Incorporated | replace, relocate, remove display fixtures in sales area, del, meat, bakery, floral depts. non load bearing new interior walls. restripe parking over existing locations. upgrade accessible parking to full compliance. upgrade single occupancy restrooms to full compliance. new interior trench drain.Details
replace, relocate, remove display fixtures in sales area, del, meat, bakery, floral depts. non load bearing new interior walls. restripe parking over existing locations. upgrade accessible parking to full compliance. upgrade single occupancy restrooms to full compliance. new interior trench drain. | $477,450 |
| Dec 27, 2012 | Completed final sign-off Jan 2013 | 15 Marina Bl | Aquamatic Fire Protection | relocate 1 sprinkler in the new 2nd consult room in pharmacy. ti pa# 2012-0706-4006Details
relocate 1 sprinkler in the new 2nd consult room in pharmacy. ti pa# 2012-0706-4006 | $600 |
| Nov 27, 2012 | Completed final sign-off Feb 2013 | 15 Marina Bl | Midstate Construction Corporation | revision to pa#2012-07-03-4006. relocate janitor's closet.Details
revision to pa#2012-07-03-4006. relocate janitor's closet. | |
| Jul 3, 2012 | Completed final sign-off Feb 2013 | 15 Marina Bl | Midstate Construction Corporation | install 2nd consultation room & relocate janitors closet.Details
install 2nd consultation room & relocate janitors closet. | $45,000 |
| Feb 7, 2012 | Completed final sign-off Apr 2012 | 15 Marina Bl | Aquamatic Fire Protection | relocate 5 sprinkler, replace 8 (e) fire sprinklers due to interior remodelDetails
relocate 5 sprinkler, replace 8 (e) fire sprinklers due to interior remodel | $1,700 |
| Jan 9, 2012 | Completed final sign-off Apr 2012 | 15 Marina Bl | Midstate Construction Corporation | revision to app#201106208501. these plans are for structural changes/cut hole. in concrete wall to add door way.Details
revision to app#201106208501. these plans are for structural changes/cut hole. in concrete wall to add door way. | $500 |
| Oct 13, 2011 | Completed final sign-off Apr 2012 | 15 Marina Bl | Delcon Heating & Ac Inc | add 2 ton hvac unit including duct distribution & trim. t-stat controls, add 2 inline exhaust fans with vent through roof. t.i. pa #201106208501.Details
add 2 ton hvac unit including duct distribution & trim. t-stat controls, add 2 inline exhaust fans with vent through roof. t.i. pa #201106208501. | $21,500 |
| Jun 20, 2011 | Completed final sign-off Apr 2012 | 15 Marina Bl | Midstate Construction Corporation | safeway. relocation of pharmacy toilet room, expansion of pharmacy to contain a consulting room and customer waiting area. relocation of hung soffit wall. mep under separate permit.Details
safeway. relocation of pharmacy toilet room, expansion of pharmacy to contain a consulting room and customer waiting area. relocation of hung soffit wall. mep under separate permit. | $100,000 |
| Jan 29, 2009 | Expired or cancelled cancelled Jul 2012 | 15 Marina Bl | remove all associated tdma radio cabinets leave coax lines, jumpers, antenas, splitter & diplexers, replace extg umts radios & cabinet with one new 3518 radio cabinet & install 2 rru's remote radio units & backup battery pack. no new electrical.Details
remove all associated tdma radio cabinets leave coax lines, jumpers, antenas, splitter & diplexers, replace extg umts radios & cabinet with one new 3518 radio cabinet & install 2 rru's remote radio units & backup battery pack. no new electrical. | $8,000 | |
| Jul 23, 2008 | Completed final sign-off Dec 2008 | 15 Marina Bl | J S J Electrical Display Corp | erect a single faced, electric, wall sign.Details
erect a single faced, electric, wall sign. | $3,000 |
| Jul 23, 2008 | Completed final sign-off Dec 2008 | 15 Marina Bl | J S J Electrical Display Corp | erect a single faced, electric sign.Details
erect a single faced, electric sign. | $3,000 |
| Jul 23, 2008 | Completed final sign-off Dec 2008 | 15 Marina Bl | J S J Electrical Display Corp | erect a single faced electric sign.Details
erect a single faced electric sign. | $2,000 |
| Jul 23, 2008 | Completed final sign-off Dec 2008 | 15 Marina Bl | J S J Electrical Display Corp | erect a single faced, electric sign.Details
erect a single faced, electric sign. | $2,000 |
| Feb 5, 2008 | Completed final sign-off Jun 2008 | 15 Marina Bl | Eric F Anderson Incorporated | non structural expansion of e pharmacy, add front and rear work counters and roll up grills, relocate stockroom doors and add waiting room. reference app 200505112158 for da complianceDetails
non structural expansion of e pharmacy, add front and rear work counters and roll up grills, relocate stockroom doors and add waiting room. reference app 200505112158 for da compliance | $50,000 |
| Jul 26, 2005 | Completed final sign-off Jan 2006 | 15 Marina Bl | Aquamatic Fire Protection | remodel (e) safeway. relocate 8 fire sprinklers.Details
remodel (e) safeway. relocate 8 fire sprinklers. | $2,500 |
| May 11, 2005 | Completed final sign-off Jan 2006 | 15 Marina Bl | remodel (e) grocery store, new accessible bathrooms, phones, signage and drinking fountainsDetails
remodel (e) grocery store, new accessible bathrooms, phones, signage and drinking fountains | $300,000 | |
| Dec 27, 2000 | Completed final sign-off May 2001 | 15 Marina Bl | install one microcell antenna on the roof and equipment cabinet on the side of bldgDetails
install one microcell antenna on the roof and equipment cabinet on the side of bldg | $20,000 | |
| Apr 14, 2000 | Expired or cancelled expired Sep 2000 | 15 Marina Bl | comply w/ n.o.v of 3/13/00, #200002439Details
comply w/ n.o.v of 3/13/00, #200002439 | $900 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Anderson Eric F Inc (6), J S J Electrical Display Corp (4), Midstate Construction Corporation (4), Aquamatic Fire Protection (3), Golden Gate Sign Company Inc. (3), California Fire Systems Inc, Delcon Heating & Ac Inc, Electric Tech Construction Inc, Ericsson Inc Dba E U S Inc, High Band Construction Inc, La Roza Construction Inc, T P C Construction Services Inc, Tilton Pacific Const Inc.
- Architects
- James E Downs (2), Stephen Fortwangler (2), Young Ming Wong (2), Jeffrey Rome, Robert Lyman/Johnson Arc
- Engineers
- Tony Jacob (3), Chris Lee, Gregory Schnackel, Mark Tomita, Robert Arthur, Yunxia Yang
- Authorized agent-otherss
- Matthew Reynolds
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.