From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
50 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Jun 30, 2022 | Completed final sign-off Feb 2023 | 920 Leavenworth St | B-Side Inc. | #301: convert existing kitchen to bedroom. relocate kitchen. rehabilitate existing bathroom. install washer & dryer.Details
#301: convert existing kitchen to bedroom. relocate kitchen. rehabilitate existing bathroom. install washer & dryer. | $28,000 |
| May 27, 2022 | Completed final sign-off Dec 2022 | 920 Leavenworth St | B-Side Inc. | unit # 204: rehab (e) kitchen, rehab (e) bathroom, inst washer/dryer, no removal of structural wallsDetails
unit # 204: rehab (e) kitchen, rehab (e) bathroom, inst washer/dryer, no removal of structural walls | $28,000 |
| Jul 15, 2021 | Completed final sign-off Aug 2021 | 920 Leavenworth St | Axa Construction | apt 206: install one (n) clothes washer & dryer. no wall demo.Details
apt 206: install one (n) clothes washer & dryer. no wall demo. | $5,000 |
| Jun 16, 2021 | Completed final sign-off Aug 2021 | 920 Leavenworth St | Axa Construction | apt 206 - bathroom rehabDetails
apt 206 - bathroom rehab | $15,000 |
| Mar 1, 2021 | Completed final sign-off Jun 2021 | 920 Leavenworth St | B-Side Inc. | apt 205: rehab (e) kitchen, no moving of walls. no structural work.Details
apt 205: rehab (e) kitchen, no moving of walls. no structural work. | $15,000 |
| Sep 21, 2020 | Completed final sign-off Feb 2021 | 920 Leavenworth St | Axa Construction | kithcen and bathroom remodel.Details
kithcen and bathroom remodel. | $28,000 |
| Sep 10, 2020 | Completed final sign-off Mar 2021 | 920 Leavenworth St | Au Electric Corporation/Aec Alarms | upgrade the extg fire alarm system to comply with sffc 1103.7.6.1 and nfpa72.Details
upgrade the extg fire alarm system to comply with sffc 1103.7.6.1 and nfpa72. | $65,000 |
| Jan 31, 2020 | Never finaled issued Jan 2020, no final | 920 Leavenworth St | B-Side Inc. | unit #305: upgrade washer/dryer in closetDetails
unit #305: upgrade washer/dryer in closet | $5,000 |
| Nov 20, 2019 | Completed final sign-off Feb 2020 | 920 Leavenworth St | Aguilera Construction Company | rebuild/repair less 50% of deck 60sf of side deck (repair in kind).Details
rebuild/repair less 50% of deck 60sf of side deck (repair in kind). | $15,000 |
| May 21, 2019 | Completed final sign-off Jul 2019 | 920 Leavenworth St | Doherty Restoration, Inc. | unit # 407: remodel existing kitchen and bathroom. no structural change. install new cabinets, counters and appliances.Details
unit # 407: remodel existing kitchen and bathroom. no structural change. install new cabinets, counters and appliances. | $32,000 |
| May 14, 2019 | Expired or cancelled cancelled Sep 2022 | 920 Leavenworth St | Metropolitan Electrical Construction | att modification: install 2 new rrus and new cabinet with batteries, remove all unusual equipment, modify platfor, no change to extg antennas.Details
att modification: install 2 new rrus and new cabinet with batteries, remove all unusual equipment, modify platfor, no change to extg antennas. | $14,000 |
| Jan 3, 2019 | Never finaled issued Jan 2019, no final | 920 Leavenworth St | Holland Brooks Builders Inc | street spaceDetails
street space | |
| Dec 7, 2018 | Completed final sign-off Mar 2019 | 920 Leavenworth St | Holland Brooks Builders Inc | #303: rehabilitate (e) kitchen & bathroom. install washer/dryer.Details
#303: rehabilitate (e) kitchen & bathroom. install washer/dryer. | $28,000 |
| Jul 30, 2018 | Completed final sign-off Dec 2019 | 920 Leavenworth St | J C Tan Builders | #306: revision to pa# 201805169305. additional work in living room & bedroom. new dry wall on walls & ceiling.Details
#306: revision to pa# 201805169305. additional work in living room & bedroom. new dry wall on walls & ceiling. | $15,000 |
| Jun 6, 2018 | Never finaled issued Jun 2018, no final | 920 Leavenworth St | street spaceDetails
street space | ||
| May 16, 2018 | Completed final sign-off Aug 2018 | 920 Leavenworth St | J C Tan Builders | unit 306 -replace kitchen cabinets, plumbing fixtures in bathroom, flooring & paint. unit 301 -to comply w/ nov 201862011 item 4.Details
unit 306 -replace kitchen cabinets, plumbing fixtures in bathroom, flooring & paint. unit 301 -to comply w/ nov 201862011 item 4. | $18,000 |
| Jan 12, 2018 | Completed final sign-off Jul 2018 | 920 Leavenworth St | Casman Construction Inc | unit #406: 1) rehabilitate extg kitchen. 2)rehabilitate extg bathroom. 3)install washer and dryer. infill (e) window (2) with cmu. n/a for maherDetails
unit #406: 1) rehabilitate extg kitchen. 2)rehabilitate extg bathroom. 3)install washer and dryer. infill (e) window (2) with cmu. n/a for maher | $33,000 |
| Jan 5, 2018 | Completed final sign-off Apr 2018 | 920 Leavenworth St | Casman Construction Inc | (e) kitchen rehabilitation in kind; (e) bathroom rehabilitation in kind. n/a maherDetails
(e) kitchen rehabilitation in kind; (e) bathroom rehabilitation in kind. n/a maher | $24,000 |
| Sep 29, 2017 | Never finaled issued Sep 2017, no final | 920 Leavenworth St | street spaceDetails
street space | ||
| Sep 12, 2017 | Completed final sign-off Jan 2018 | 920 Leavenworth St | Triton Tower Inc | to pay for fire inspection only. ref app#200503228131,200904146225, & 201704275069Details
to pay for fire inspection only. ref app#200503228131,200904146225, & 201704275069 | |
| Jul 28, 2017 | Never finaled issued Jul 2017, no final | 920 Leavenworth St | street spaceDetails
street space | ||
| Jul 7, 2017 | Completed final sign-off Oct 2017 | 920 Leavenworth St | Brighter Bay Builders Inc | unit 401 - rehabilitate existing kitchen and bathroom; install washer & dryer. n/a maher ordinanceDetails
unit 401 - rehabilitate existing kitchen and bathroom; install washer & dryer. n/a maher ordinance | $31,000 |
| Apr 27, 2017 | Completed final sign-off Jul 2018 | 920 Leavenworth St | Triton Tower Inc | to obtain final inspection for work approved under pa#2005-03-22-8131 & 2009-04-14-6225. all work is complete.Details
to obtain final inspection for work approved under pa#2005-03-22-8131 & 2009-04-14-6225. all work is complete. | |
| Oct 3, 2016 | Completed final sign-off Apr 2017 | 920 Leavenworth St | Electric Tech Construction Inc | at&t - modify (e) att cell site. replace 2 antenna. install 2 rrus-11 units, 2 rrus-12 unitsm 1 dcg surge suppressor, 1 gps antenna, relocate (e) 3578 rds cabinet to maher naDetails
at&t - modify (e) att cell site. replace 2 antenna. install 2 rrus-11 units, 2 rrus-12 unitsm 1 dcg surge suppressor, 1 gps antenna, relocate (e) 3578 rds cabinet to maher na | $25,000 |
| Nov 18, 2015 | Completed final sign-off Apr 2016 | 920 Leavenworth St | Hon's Construction Inc. | unit 305 kitchen remodel: remove/install new cabinets & countertops; paint & tile kitchen. compliance with maher ordinance 155-13 not required.Details
unit 305 kitchen remodel: remove/install new cabinets & countertops; paint & tile kitchen. compliance with maher ordinance 155-13 not required. | $8,500 |
| Oct 15, 2015 | Never finaled issued Dec 2015, no final | 920 Leavenworth St | Cal Inc. | unit #402: remodel unit @ the 5th flr, remodel existing bathroom, remodel existing kitchen and add washer and dryer; maher n/aDetails
unit #402: remodel unit @ the 5th flr, remodel existing bathroom, remodel existing kitchen and add washer and dryer; maher n/a | $25,000 |
| Aug 25, 2015 | Never finaled issued Aug 2015, no final | 920 Leavenworth St | street spaceDetails
street space | ||
| Aug 11, 2015 | Never finaled issued Aug 2015, no final | 920 Leavenworth St | street spaceDetails
street space | ||
| Jul 24, 2015 | Completed final sign-off Jan 2016 | 920 Leavenworth St | Cal Inc. | unit #207: remodel bathroom and kitchen, add washer and dryer. remove wall between kitchen and living. maher n/a.Details
unit #207: remodel bathroom and kitchen, add washer and dryer. remove wall between kitchen and living. maher n/a. | $25,000 |
| Jun 25, 2015 | Never finaled issued Jun 2015, no final | 920 Leavenworth St | street spaceDetails
street space | ||
| Mar 4, 2015 | Completed final sign-off Oct 2015 | 920 Leavenworth St | Cal Inc. | remodel #302 - remodel bathroom and kitchen. add new washer & dryer. maher - not req'dDetails
remodel #302 - remodel bathroom and kitchen. add new washer & dryer. maher - not req'd | $10,000 |
| Sep 5, 2014 | Completed final sign-off Feb 2015 | 920 Leavenworth St | D3 Construction | remodel kitchen & bathroom. no change to window, walls & doors. lighting to comply w/cec 150(k). work in unit #405 only. replace exhaust fan in bathroom.Details
remodel kitchen & bathroom. no change to window, walls & doors. lighting to comply w/cec 150(k). work in unit #405 only. replace exhaust fan in bathroom. | $18,000 |
| Jul 2, 2014 | Completed final sign-off Oct 2014 | 920 Leavenworth St | D3 Construction | unit 304: remodel kitchen & bathroom, no change to window walls & doors, lighting to comply w/cec 150(k).Details
unit 304: remodel kitchen & bathroom, no change to window walls & doors, lighting to comply w/cec 150(k). | $18,000 |
| May 15, 2014 | Never finaled issued May 2014, no final | 1094 Bush St | addotional layer of ceiling sheetrock. maher n/a. revision appl. 201301178234. to comply with complaintDetails
addotional layer of ceiling sheetrock. maher n/a. revision appl. 201301178234. to comply with complaint | $12,000 | |
| Jul 2, 2013 | Never finaled issued Jul 2013, no final | 1094 Bush St | revision to pa# 2013-0117-8234-no work at back wall of gym, revise detail 2 on a2 to reflect (e) conditionsDetails
revision to pa# 2013-0117-8234-no work at back wall of gym, revise detail 2 on a2 to reflect (e) conditions | ||
| May 7, 2013 | Never finaled issued May 2013, no final | 1094 Bush St | revision to pa# 2013-0117-8234-reflect ceiling detail from previous permit #2012-1214-6301Details
revision to pa# 2013-0117-8234-reflect ceiling detail from previous permit #2012-1214-6301 | ||
| Jan 30, 2013 | Completed final sign-off Apr 2013 | 1094 Bush St | Zebra Awning Co Inc | erect non-electric projecting single faced sign fitness classes personal training chiropractic massage. graphic signage only.Details
erect non-electric projecting single faced sign fitness classes personal training chiropractic massage. graphic signage only. | $900 |
| Jan 30, 2013 | Completed final sign-off Apr 2013 | 1094 Bush St | Zebra Awning Co Inc | fabricate & install 1 awning, equipped with break away panel below fire escape drop down ladder. signs on separate permits.Details
fabricate & install 1 awning, equipped with break away panel below fire escape drop down ladder. signs on separate permits. | $6,000 |
| Jan 18, 2013 | Completed final sign-off Mar 2013 | 1094 Bush St | J S J Electrical Display Corp | erect electric wall single faced 'livefit gym well ness club' sign.Details
erect electric wall single faced 'livefit gym well ness club' sign. | $2,500 |
| Jan 17, 2013 | Never finaled issued Jan 2013, no final | 1094 Bush St | install gym equipment. install existing sign with strobe lights. change of use from retail to gym. change occupancy from m to b.Details
install gym equipment. install existing sign with strobe lights. change of use from retail to gym. change occupancy from m to b. | $13,000 | |
| Dec 14, 2012 | Completed final sign-off May 2013 | 1094 Bush St | Malagic Construction | comply with complaint 201278121. repair and replace ceiling in retail ground floor with sheetrock.Details
comply with complaint 201278121. repair and replace ceiling in retail ground floor with sheetrock. | $6,000 |
| Dec 5, 2012 | Completed final sign-off Jan 2013 | 1094 Bush St | Malagic Construction | demo interior finishes only per ab-017 at ground floor retail.Details
demo interior finishes only per ab-017 at ground floor retail. | $8,600 |
| May 31, 2012 | Never finaled issued May 2012, no final | 920 Leavenworth St | Westower Communications | to obtain final inspection for work approved under pa#201011054458 all work is completeDetails
to obtain final inspection for work approved under pa#201011054458 all work is complete | |
| Nov 5, 2010 | Never finaled issued Nov 2010, no final | 920 Leavenworth St | Westower Communications | remove and replace (4) flags of concrete, trench from existing sub box to front wall approx 13'; place nw 2" conduit from existing sub box into basement @920 leavenworthDetails
remove and replace (4) flags of concrete, trench from existing sub box to front wall approx 13'; place nw 2" conduit from existing sub box into basement @920 leavenworth | $7,000 |
| Apr 14, 2009 | Expired or cancelled expired Jan 2011 | 920 Leavenworth St | Pinnacle Wireless Usa Inc. | modification of an (e) telecom facility consisting of removing 2 (e) rbs 3303 'radio' cabinets & replacing it with 2 new rbs 3518 'radio' cabinets. adding also 4 rru (remote radio units) & adding 2 new pbc-02 battery backup cabinetsDetails
modification of an (e) telecom facility consisting of removing 2 (e) rbs 3303 'radio' cabinets & replacing it with 2 new rbs 3518 'radio' cabinets. adding also 4 rru (remote radio units) & adding 2 new pbc-02 battery backup cabinets | $5,000 |
| Mar 22, 2005 | Expired or cancelled expired Aug 2009 | 920 Leavenworth St | Metropolitan Electrical Construction | installation & operation of new cingular wireless telecommunications facility, including microcell chicklet antennas to be mounted to (e) bldg. facade & associated equip on (e) bldg rooftop. no batteries in this installation.Details
installation & operation of new cingular wireless telecommunications facility, including microcell chicklet antennas to be mounted to (e) bldg. facade & associated equip on (e) bldg rooftop. no batteries in this installation. | $40,000 |
| Aug 30, 2004 | Expired or cancelled expired Sep 2005 | 920 Leavenworth St | Associated Builders | reroofingDetails
reroofing | $20,000 |
| Jun 3, 2004 | Never finaled issued Jun 2004, no final | 920 Leavenworth St | street spaceDetails
street space | ||
| Mar 15, 2004 | Completed final sign-off Mar 2005 | 920 Leavenworth St | K Lui General Const, | rev. appl#2001091281308-umbDetails
rev. appl#2001091281308-umb | |
| Sep 12, 2001 | Completed final sign-off Feb 2005 | 920 Leavenworth St | seismic upgrade as per bolt w/ irregularities corrected for this umb buildingDetails
seismic upgrade as per bolt w/ irregularities corrected for this umb building | $58,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- B-Side Inc. (4), Axa Construction (3), Cal Inc. (3), Casman Construction Inc (2), D3 Construction (2), Holland Brooks Builders Inc (2), J C Tan Builders (2), Malagic Construction (2), Metropolitan Electrical Construction (2), Triton Tower Inc (2), Westower Communications (2), Zebra Awning Co Inc (2), Aguilera Construction Company, Associated Builders, Au Electric Corporation/Aec Alarms, Brighter Bay Builders Inc, Doherty Restoration, Inc., Electric Tech Construction Inc, Hon's Construction Inc., J S J Electrical Display Corp, K Lui General Const,, Pinnacle Wireless Usa Inc.
- Architects
- Ashton Richards (2), Kevin Skiles
- Engineers
- Joe Win Kon (2), Brett Mccomb, Joe Kwon
- Authorized agent-otherss
- Alina Karelina
- Designers
- James Spore, Joe Kon