Block 0194, lot 005
825 Kearny St
- City’s use
- Commercial Misc
- Built
- 1911
- Stories
- 2
- Rooms
- 9 bathrooms
- Building
- 8,428 sq ft
- Lot
- 3,776 sq ft
- Zoning
- CCB
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
13 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Feb 1, 2022 | Completed final sign-off Aug 2022 | 825 Kearny St | David Jone | remove (e) walls, doors and plumbing fixtures. construct new walls and door. relocate plumbing fixtures. install power door operator on entry doors.Details
remove (e) walls, doors and plumbing fixtures. construct new walls and door. relocate plumbing fixtures. install power door operator on entry doors. | $35,000 |
| Nov 9, 2020 | Completed final sign-off Sep 2021 | 825 Kearny St | Rcm Fire Protection Inc. | modify existing sprinkler system per nfpa 13-2013 for new ceiling feature and layout. 17 total heads added. ref: 2019-1205-8781.Details
modify existing sprinkler system per nfpa 13-2013 for new ceiling feature and layout. 17 total heads added. ref: 2019-1205-8781. | $1,500 |
| Dec 5, 2019 | Completed final sign-off Sep 2021 | 825 Kearny St | Cahill Contractors Llc. | provide a new communicating opening at the 2nd floor from 825 kearny to 827 kearny. replace extg restrooms with new accessible restroom.Details
provide a new communicating opening at the 2nd floor from 825 kearny to 827 kearny. replace extg restrooms with new accessible restroom. | $50,000 |
| Nov 15, 2019 | Completed final sign-off Feb 2022 | 825 Kearny St | Cahill Contractors Llc. | repair of existing deteriorated steel beam in basement of existing buildingDetails
repair of existing deteriorated steel beam in basement of existing building | $3,000 |
| Nov 15, 2019 | Completed final sign-off Jul 2021 | 825 Kearny St | Cahill Contractors Llc. | deferred micro piles for stair support. reference pa# 2019-0916-1756Details
deferred micro piles for stair support. reference pa# 2019-0916-1756 | |
| Sep 16, 2019 | Completed final sign-off Jul 2021 | 825 Kearny St | Cahill Contractors Llc. | replacement of 4 structural columns and the related foundations, supporting an existing exterior metal stair on 825 kearny st property.Details
replacement of 4 structural columns and the related foundations, supporting an existing exterior metal stair on 825 kearny st property. | $10,000 |
| May 15, 2019 | Completed final sign-off May 2021 | 825 Kearny St | Granite Excavation & Demolition Inc | portions of should piles between 827 kearney and 825 kearney hand dug concrete underpinning piers & temp. concrete foundation & pipe shores for (e) super structure & exterior stair.Details
portions of should piles between 827 kearney and 825 kearney hand dug concrete underpinning piers & temp. concrete foundation & pipe shores for (e) super structure & exterior stair. | $70,000 |
| Mar 30, 2009 | Never finaled issued Mar 2009, no final | 825 Kearny St | sidewalk only.Details
sidewalk only. | ||
| Nov 14, 2008 | Never finaled issued Nov 2008, no final | 825 Kearny St | T M C Construction | alteration entrance door single to a pair door at store frontDetails
alteration entrance door single to a pair door at store front | $2,200 |
| Apr 8, 2008 | Never finaled issued Apr 2008, no final | 825 Kearny St | street space permit only.Details
street space permit only. | ||
| Feb 6, 2008 | Never finaled issued Feb 2008, no final | 825 Kearny St | street spaceDetails
street space | ||
| Dec 6, 2007 | Never finaled issued Dec 2007, no final | 825 Kearny St | street space permit only.Details
street space permit only. | ||
| Aug 13, 2007 | Completed final sign-off Oct 2008 | 825 Kearny St | Gm Plumbing Inc. | apply waterproof membrane to interior face of existing brick wall from base to above ground floor level of adjacent building. 728 wash. st. install drainiage piping to existing sump pump. erect new concrete wall from basement to first floor. remove and reinstall interior surfaces and facilitiesDetails
apply waterproof membrane to interior face of existing brick wall from base to above ground floor level of adjacent building. 728 wash. st. install drainiage piping to existing sump pump. erect new concrete wall from basement to first floor. remove and reinstall interior surfaces and facilities | $95,000 |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Cahill Contractors Llc. (4), David Jone, Gm Plumbing Inc., Granite Excavation & Demolition Inc, Rcm Fire Protection Inc., T M C Construction
- Architects
- Stanley Teng (2), Robert Roth
- Engineers
- Farshad Khodayari (2), Erwin O'toole
Find contractors for work like this