Block 0111, lot 001
1 Union St
- City’s use
- Commercial Office
- Built
- 1906
- Stories
- 2
- Units
- 4
- Rooms
- 2 bathrooms
- Building
- 30,000 sq ft
- Lot
- 15,000 sq ft
- Zoning
- C2
- Construction type
- B
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
29 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 21, 2024 | Expired or cancelled cancelled Mar 2025 | 1 Union St | Msr Mechanical Llc | two like for like chillers replacment.Details
two like for like chillers replacment. | $450,000 |
| Dec 15, 2022 | Completed final sign-off Jan 2024 | 1 Union St | Acco Engineered Systems Inc. Dba Acco En | #3 - 3rd flr - replace (2) condensing units located on roof; replace (2) air handling units located above server room.Details
#3 - 3rd flr - replace (2) condensing units located on roof; replace (2) air handling units located above server room. | $52,000 |
| Jun 20, 2018 | Expired or cancelled cancelled Jan 2026 | 1 Union St | barrier removal to upgrade existing level 2 restroom to be ada compliantDetails
barrier removal to upgrade existing level 2 restroom to be ada compliant | $18,000 | |
| Feb 23, 2018 | Completed final sign-off May 2018 | 1075 Front St | O'connor Plumbing & Fire Protection | refurnish existing fire sprinkler system due to fire reconstruction to suite 730. ti #201710262303. maher naDetails
refurnish existing fire sprinkler system due to fire reconstruction to suite 730. ti #201710262303. maher na | $5,000 |
| Dec 14, 2017 | Completed final sign-off Aug 2018 | 1075 Front St | Schmitt Heating Co Inc | replace 5 (e) water service heat pumps connected to (e) building chill water due to fire smoke damage. repalce (e) ductwork due to fire, smoke & water damage in connection w/pa# 201710262303 maher naDetails
replace 5 (e) water service heat pumps connected to (e) building chill water due to fire smoke damage. repalce (e) ductwork due to fire, smoke & water damage in connection w/pa# 201710262303 maher na | $42,000 |
| Dec 4, 2017 | Completed final sign-off Aug 2018 | 1075 Front St | Thompson Electric | eletrical title 24 plans for pa 201710262303Details
eletrical title 24 plans for pa 201710262303 | $45,000 |
| Oct 26, 2017 | Completed final sign-off Aug 2018 | 1075 Front St | D.P. Stearns | 2nd floor - replace 2 recording studios & support space destroyed by fire, interior tenant improvement only. n/a maher ordinanceDetails
2nd floor - replace 2 recording studios & support space destroyed by fire, interior tenant improvement only. n/a maher ordinance | $276,000 |
| Oct 11, 2017 | Never finaled issued Jun 2018, no final | 1 Union St | D Squared Construction | modifications to existing non historic "barn door" window alcoves which were added in 1992.Details
modifications to existing non historic "barn door" window alcoves which were added in 1992. | $97,000 |
| Jul 28, 2017 | Completed final sign-off Dec 2017 | 1 Union St | D.P. Stearns | ab-017 fire damage remove walls not carpet. exploratory demoDetails
ab-017 fire damage remove walls not carpet. exploratory demo | $17,500 |
| Mar 8, 2017 | Never finaled issued Mar 2017, no final | 1 Union St | street spaceDetails
street space | ||
| Feb 1, 2017 | Never finaled issued Feb 2017, no final | 1 Union St | street space permitDetails
street space permit | ||
| Mar 30, 2009 | Expired or cancelled cancelled Jan 2026 | 1 Union St | Rinaldi Construction | at 2nd fl: open partition wall 3'-0" between existing spaces.Details
at 2nd fl: open partition wall 3'-0" between existing spaces. | $1,000 |
| Aug 13, 2008 | Completed final sign-off Nov 2008 | 1 Union St | subdivide large office with glass partitions. reconfigure closet with sliding door. mechanical & sprinkler under separate permit as required.Details
subdivide large office with glass partitions. reconfigure closet with sliding door. mechanical & sprinkler under separate permit as required. | $20,000 | |
| Jun 28, 2005 | Never finaled issued Jun 2005, no final | 1 Union St | Sabah International Incorporated | renew expired pa#200403269762 for final inspectionDetails
renew expired pa#200403269762 for final inspection | |
| Nov 9, 2004 | Never finaled issued Dec 2004, no final | 1 Union St | Marquee Fire Protection Dba Pye Barker F | modify an (e) fire sprinkler system from (e) outlets. total 58 sprinklers.Details
modify an (e) fire sprinkler system from (e) outlets. total 58 sprinklers. | $7,400 |
| Oct 7, 2004 | Completed final sign-off Apr 2005 | 1 Union St | t.i for space #1 on 2nd fl. work includes (n) partitions doors fixtures, finishes & painting. lightiDetails
t.i for space #1 on 2nd fl. work includes (n) partitions doors fixtures, finishes & painting. lighti | $280,000 | |
| Sep 23, 2004 | Expired or cancelled withdrawn Oct 2004 | 1 Union St | Zakskorn Construction Dba Zcon Builders | oti-1 2nd floor me, el, sp, l/sDetails
oti-1 2nd floor me, el, sp, l/s | $280,000 |
| Sep 3, 2004 | Completed final sign-off Nov 2004 | 1 Union St | demolition of (e) sub divided tenant space on 2nd floorDetails
demolition of (e) sub divided tenant space on 2nd floor | $12,000 | |
| Mar 26, 2004 | Never finaled issued Mar 2004, no final | 1 Union St | Sabah International Incorporated | furnish install, test & final fm200 fire suppression systemDetails
furnish install, test & final fm200 fire suppression system | $15,975 |
| Oct 17, 2003 | Completed final sign-off Apr 2005 | 1 Union St | Zakskorn Construction Dba Zcon Builders | oti-4 3rd floor-elDetails
oti-4 3rd floor-el | $100,000 |
| Sep 25, 2003 | Completed final sign-off Jan 2004 | 1 Union St | Marquee Fire Protection Dba Pye Barker F | oti-3 3rd fl. spDetails
oti-3 3rd fl. sp | $9,200 |
| Sep 24, 2003 | Completed final sign-off Jan 2004 | 1 Union St | oti-2 3rd floor meDetails
oti-2 3rd floor me | $44,000 | |
| Sep 10, 2003 | Completed final sign-off Jan 2004 | 1 Union St | Zakskorn Construction Dba Zcon Builders | oti-1 3rd floor, el, me, l/s, spDetails
oti-1 3rd floor, el, me, l/s, sp | $700,000 |
| Aug 20, 2003 | Completed final sign-off Jan 2004 | 1 Union St | Zakskorn Construction Dba Zcon Builders | demo 3rd fl,nonbearing office partitions, mech ductwork &electrical conduits&receptacles,carpet fl.Details
demo 3rd fl,nonbearing office partitions, mech ductwork &electrical conduits&receptacles,carpet fl. | $32,000 |
| Aug 14, 2001 | Completed final sign-off Nov 2001 | 1 Union St | Richlen Construction | oti-2, ground floor-el, me, spDetails
oti-2, ground floor-el, me, sp | $75,000 |
| Mar 1, 2001 | Completed final sign-off Nov 2001 | 1 Union St | oti-1 ground floor, ltg, mech, ls, sprDetails
oti-1 ground floor, ltg, mech, ls, spr | $127,500 | |
| Sep 6, 2000 | Expired or cancelled withdrawn Oct 2000 | 1 Union St | Steve Milovich Gen Contr | reconfig lighting for proposed office alt. remove 6 fix and install floor fix. elec load not affecteDetails
reconfig lighting for proposed office alt. remove 6 fix and install floor fix. elec load not affecte | $2,000 |
| Aug 24, 2000 | Expired or cancelled withdrawn Oct 2000 | 1 Union St | Steve Milovich Gen Contr | oti-1 2nd floor el onlyDetails
oti-1 2nd floor el only | $10,000 |
| Feb 18, 2000 | Expired or cancelled cancelled Feb 2000 | 1075 Front St | replace portions of sidewalk as highlighted on plansDetails
replace portions of sidewalk as highlighted on plans | $3,000 |
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.