Block 0090, lot 028
750 Columbus Ave
- City’s use
- Multi-Family Residential
- Built
- 1909
- Stories
- 3
- Units
- 8
- Rooms
- 8 bathrooms
- Building
- 4,392 sq ft
- Lot
- 1,481 sq ft
- Zoning
- NBEACH
- Construction type
- D
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
26 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Nov 13, 2020 | Completed final sign-off Aug 2021 | 750 Columbus Av | Mastec Network Solutions Inc | remove & replace frp faux chimney with new frp faux chimney. install (n) antenna mount, 3 (n) antennas, 2 (n) racks. concrete slab as needed. install bb unit inside racks. install hybrid cables & 6 (n) rru's, 6 diplexers. remove all coax cables & twin diplexers.Details
remove & replace frp faux chimney with new frp faux chimney. install (n) antenna mount, 3 (n) antennas, 2 (n) racks. concrete slab as needed. install bb unit inside racks. install hybrid cables & 6 (n) rru's, 6 diplexers. remove all coax cables & twin diplexers. | $25,000 |
| May 30, 2019 | Completed final sign-off Nov 2020 | 750 Columbus Av | Video Voice Data Communications | t mobile modification to replace 3 antennas with new and 3 rrusDetails
t mobile modification to replace 3 antennas with new and 3 rrus | $25,000 |
| May 22, 2019 | Completed final sign-off Jul 2019 | 750 Columbus Av | Sft Construction Corp | rev to pa# 201810011828 & 20508315673; memorialize strucural changes based on discoverred (e) structural conditions: reconifgure shear wall layout, modification to moment frame connection to structural diaphragmDetails
rev to pa# 201810011828 & 20508315673; memorialize strucural changes based on discoverred (e) structural conditions: reconifgure shear wall layout, modification to moment frame connection to structural diaphragm | |
| Mar 18, 2019 | Never finaled issued Mar 2019, no final | 750 Columbus Av | street spaceDetails
street space | ||
| Oct 1, 2018 | Completed final sign-off Jul 2019 | 750 Columbus Av | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. (commercial) residential pa #201508315673.Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. (commercial) residential pa #201508315673. | $27,000 | |
| May 27, 2016 | Completed final sign-off Dec 2016 | 758 Columbus Av | Francisco Zarceno | 2nd floor: renovate kitchen and bathroomDetails
2nd floor: renovate kitchen and bathroom | $15,000 |
| Jan 19, 2016 | Completed final sign-off May 2016 | 750 Columbus Av | modification to an extg t-mobile microcell facility incuding 1 new antenna within a new faux vent pipe. also intalling 6 new tma's and 1 new diplexer.Details
modification to an extg t-mobile microcell facility incuding 1 new antenna within a new faux vent pipe. also intalling 6 new tma's and 1 new diplexer. | $16,000 | |
| Aug 31, 2015 | Completed final sign-off Jul 2019 | 750 Columbus Av | Sft Construction Corp | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. (residential) commercial pa #201810011828.Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4. (residential) commercial pa #201810011828. | $15,000 |
| Dec 5, 2014 | Never finaled issued Apr 2015, no final | 750 Columbus Av | Westower Communications | metro pcs- remove cabinet. antennas, coax, mounts and radio equipment ownership to be transferred to t-mobile.Details
metro pcs- remove cabinet. antennas, coax, mounts and radio equipment ownership to be transferred to t-mobile. | $10,000 |
| Jun 26, 2013 | Never finaled issued Jul 2013, no final | 750 Columbus Av | Walker Cellular Inc | remove 2 extg t-mobile equipment cabinets and replace with 2 new t-mobile equipment cabinets in basement.Details
remove 2 extg t-mobile equipment cabinets and replace with 2 new t-mobile equipment cabinets in basement. | $20,000 |
| Jan 21, 2011 | Never finaled issued Jan 2011, no final | 760 Columbus Av | street spaceDetails
street space | ||
| May 11, 2010 | Never finaled filed May 2010, never issued | 750 Columbus Av | a modification to an (e) unmanned telecommunications facility consisting of adding a (n) 3518 rbs cabinet, (2) (n) rru's (remote radio units) & pbc-02 cabinet inside an (e) equipment room. also adding (4) (n) runs o9f 7/8" coax cable to (2) (n) antennae inside an (n) extended frp box.Details
a modification to an (e) unmanned telecommunications facility consisting of adding a (n) 3518 rbs cabinet, (2) (n) rru's (remote radio units) & pbc-02 cabinet inside an (e) equipment room. also adding (4) (n) runs o9f 7/8" coax cable to (2) (n) antennae inside an (n) extended frp box. | $22,000 | |
| Jul 28, 2009 | Completed final sign-off Oct 2009 | 750 Columbus Av | Cba Site Services Inc. | modification to an (e) telecom facility consisting of adding 2 new rru's (remote radio units).Details
modification to an (e) telecom facility consisting of adding 2 new rru's (remote radio units). | $5,000 |
| May 11, 2009 | Completed final sign-off Sep 2009 | 750 Columbus Av | Francisco Zarceno | revision to pa #200905017542, add 8"x12" stem wall to foundation.Details
revision to pa #200905017542, add 8"x12" stem wall to foundation. | $1,000 |
| May 1, 2009 | Completed final sign-off Sep 2009 | 750 Columbus Av | Francisco Zarceno | level 4: renovate kitchen/bath; remove skylight, infill roof. rebuild 'nook' walls all 4 levels, install (n) fdn along foundation wall and stairwell wall.Details
level 4: renovate kitchen/bath; remove skylight, infill roof. rebuild 'nook' walls all 4 levels, install (n) fdn along foundation wall and stairwell wall. | $20,000 |
| Apr 15, 2009 | Never finaled issued Apr 2009, no final | 750 Columbus Av | street space & sidewalk repair.Details
street space & sidewalk repair. | ||
| May 30, 2006 | Expired or cancelled expired May 2009 | 750 Columbus Av | Momentum Services Corp | installation of (2) micro antennas inside frp concealment facade with the associated equipment cabinet located at the basement level.Details
installation of (2) micro antennas inside frp concealment facade with the associated equipment cabinet located at the basement level. | $55,000 |
| Mar 28, 2006 | Completed final sign-off Oct 2007 | 750 Columbus Av | Ccr Builders Inc.**See Note*** | install new microcell panel antenna enclosed within new pedestal, built to match existing, install of associated equipment, cabling and cable trays. complaint #200557747.Details
install new microcell panel antenna enclosed within new pedestal, built to match existing, install of associated equipment, cabling and cable trays. complaint #200557747. | $25,000 |
| Mar 22, 2005 | Completed final sign-off Apr 2006 | 750 Columbus Av | Metropolitan Electrical Construction | installation & operation of new cingular wireless telecommunications facility, including microcellDetails
installation & operation of new cingular wireless telecommunications facility, including microcell | $40,000 |
| Jan 12, 2005 | Never finaled issued Jan 2005, no final | 750 Columbus Av | street spaceDetails
street space | ||
| Mar 10, 2003 | Completed final sign-off Mar 2003 | 750 Columbus Av | Woodstone Construction | renew pa#2002/09/09/6011 for final insp.Details
renew pa#2002/09/09/6011 for final insp. | |
| Sep 9, 2002 | Expired or cancelled expired May 2009 | 750 Columbus Av | Woodstone Construction | to comply w/ h.i.d. n.o.v. issued on 8/7/02 complaint tracking#200232156 item#2.Details
to comply w/ h.i.d. n.o.v. issued on 8/7/02 complaint tracking#200232156 item#2. | $1,700 |
| Dec 18, 2000 | Expired or cancelled expired Apr 2001 | 750 Columbus Av | sidewalk repairDetails
sidewalk repair | ||
| Dec 11, 2000 | Expired or cancelled expired Nov 2001 | 750 Columbus Av | Bay Area Signs | to erect sign electric, wall,single facedDetails
to erect sign electric, wall,single faced | |
| Dec 1, 2000 | Expired or cancelled cancelled Oct 2024 | 750 Columbus Av | to erect sign electric wall single facedDetails
to erect sign electric wall single faced | ||
| Mar 10, 2000 | Completed final sign-off Mar 2000 | 754 Columbus Av | Amer. Canvas & Awning | provide & install pre-fabricate hand-crank retractable awningDetails
provide & install pre-fabricate hand-crank retractable awning |
Find contractors for work like this