Block 0081, lot 002
150 Greenwich St
- City’s use
- Commercial Misc
- Built
- 1952
- Stories
- 2
- Units
- 1
- Rooms
- 5 bathrooms
- Building
- 48,029 sq ft
- Lot
- 37,840 sq ft
- Zoning
- C2
- Construction type
- C
From the assessor's latest secured roll, which can lag recent work. Lot plans, zoning and planning history on the city’s Property Information Map
Permits filed here
27 permits filed for this property since 2000.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 16, 2025 | In progress filed Dec 2025, not yet issued | 150 Greenwich St | project seeks to gain approval for existing vending machines. improvements to 2nd fl commissary areaDetails
project seeks to gain approval for existing vending machines. improvements to 2nd fl commissary area | $1,000 | |
| Sep 29, 2020 | Never finaled issued Oct 2020, no final | 150 Greenwich St | Firemaster | installatoin of 1 ansul r-102 fire suppression system.Details
installatoin of 1 ansul r-102 fire suppression system. | $5,000 |
| May 4, 2018 | Completed final sign-off Jun 2018 | 150 Greenwich St | Ducheney Construction Inc | revision to app#201707313382 to relocate lula elevator machine room. n/a for maherDetails
revision to app#201707313382 to relocate lula elevator machine room. n/a for maher | |
| Apr 23, 2018 | Completed final sign-off Jun 2018 | 150 Greenwich St | Peters Hvac | install ductless mini split for elevator equip rm ref 201707313382 maher naDetails
install ductless mini split for elevator equip rm ref 201707313382 maher na | $25,000 |
| Apr 23, 2018 | Completed final sign-off Jun 2018 | 150 Greenwich St | Peters Hvac | install new exhaust fan, relocate (e) ducting, install new ducting for dry vents and combustion air for laundry room ref 201707192404. n/a for maher.Details
install new exhaust fan, relocate (e) ducting, install new ducting for dry vents and combustion air for laundry room ref 201707192404. n/a for maher. | $25,000 |
| Oct 2, 2017 | Expired or cancelled cancelled Jan 2026 | 150 Greenwich St | interior t.i. at g/f with new commercial kitchen into (e) gym & servery (cafe). mep shall be design-build under sep permit.Details
interior t.i. at g/f with new commercial kitchen into (e) gym & servery (cafe). mep shall be design-build under sep permit. | $50,000 | |
| Jul 31, 2017 | Completed final sign-off Jun 2018 | 150 Greenwich St | Ducheney Construction Inc | interior t.i. to add a limited use/ limited application elevator & machine room. mep. shall be design build under seperate permit. n/a ordinance #155-13Details
interior t.i. to add a limited use/ limited application elevator & machine room. mep. shall be design build under seperate permit. n/a ordinance #155-13 | $6,250 |
| Jul 19, 2017 | Completed final sign-off Jun 2018 | 150 Greenwich St | Ducheney Construction Inc | interio ti to relocate existing laundry room and convert e laundry room to storage. mep design buildDetails
interio ti to relocate existing laundry room and convert e laundry room to storage. mep design build | $70,000 |
| Jul 12, 2017 | Never finaled issued Jul 2017, no final | 150 Greenwich St | renew expired pa#201412163863 for final inspection only.Details
renew expired pa#201412163863 for final inspection only. | ||
| Feb 19, 2015 | Never finaled issued Mar 2015, no final | 150 Greenwich St | Hillhouse Construction Company Inc | suite 120: revision to app#201310179488 to change toilet 128 to storage 128. ref app#201310179488. n/a for the maher.Details
suite 120: revision to app#201310179488 to change toilet 128 to storage 128. ref app#201310179488. n/a for the maher. | $65,000 |
| Dec 16, 2014 | Never finaled issued Mar 2015, no final | 150 Greenwich St | Hillhouse Construction Company Inc | ti for lobby of e athletic club on gr fl and mezz. includes new partitions staircase, glass guards, flooring. mep & fire sep permit. no exterior work maher not requiredDetails
ti for lobby of e athletic club on gr fl and mezz. includes new partitions staircase, glass guards, flooring. mep & fire sep permit. no exterior work maher not required | $325,000 |
| Aug 27, 2010 | Never finaled issued Aug 2010, no final | 150 Greenwich St | street space & sidewalk | ||
| Jul 21, 2010 | Never finaled issued Jul 2010, no final | 150 Greenwich St | street space and mta parking | ||
| Mar 7, 2005 | Completed final sign-off May 2005 | 150 Greenwich St | new signage for accessibility path of travel from 150 greenwich st to 1444 sansome.Details
new signage for accessibility path of travel from 150 greenwich st to 1444 sansome. | $200 | |
| Jun 17, 2004 | Completed final sign-off Jul 2004 | 150 Greenwich St | Rapp Construction Co. | renew permit 200302187692/r1Details
renew permit 200302187692/r1 | |
| Mar 29, 2004 | Never finaled issued Mar 2004, no final | 150 Greenwich St | street space permit | ||
| Feb 18, 2004 | Completed final sign-off Mar 2004 | 150 Greenwich St | Reinhardt Roofing Inc | reroofingDetails
reroofing | $27,000 |
| Jan 14, 2004 | Completed final sign-off Mar 2004 | 150 Greenwich St | Reinhardt Roofing Inc | reroofingDetails
reroofing | $31,000 |
| Dec 12, 2003 | Completed final sign-off May 2004 | 150 Greenwich St | Reinhardt Roofing Inc | reroofingDetails
reroofing | $75,500 |
| Aug 4, 2003 | Completed final sign-off Feb 2005 | 150 Greenwich St | Cannon Constructors North Inc | rev. appl#200208053175 rev. to stairDetails
rev. appl#200208053175 rev. to stair | $100 |
| Feb 18, 2003 | Expired or cancelled expired Jun 2005 | 150 Greenwich St | Rapp Construction Co. | build 2 spas, granite, steel plumbing electric archit. work approved under bldg permitDetails
build 2 spas, granite, steel plumbing electric archit. work approved under bldg permit | $110,000 |
| Aug 5, 2002 | Completed final sign-off Feb 2005 | 150 Greenwich St | Cannon Constructors North Inc | 18,000 s.f t.i & renovation of existing health club including locker rooms, toilets, showers, steamDetails
18,000 s.f t.i & renovation of existing health club including locker rooms, toilets, showers, steam | $2,300,000 |
| Apr 11, 2002 | Completed final sign-off May 2002 | 150 Greenwich St | Cal-Air Inc | replace air chiller at roof topDetails
replace air chiller at roof top | $33,000 |
| Apr 23, 2001 | Completed final sign-off Dec 2001 | 150 Greenwich St | Cannon Constructors North Inc | cafe remodel/added millwork and appliances to cafe areaDetails
cafe remodel/added millwork and appliances to cafe area | $20,000 |
| Feb 8, 2001 | Completed final sign-off May 2001 | 150 Greenwich St | interior non-structural demolition only respon to complaint #200114023 (2-6-01).Details
interior non-structural demolition only respon to complaint #200114023 (2-6-01). | $3,000 | |
| Sep 8, 2000 | Completed final sign-off Dec 2001 | 150 Greenwich St | Cannon Constructors North Inc | squash court remodelDetails
squash court remodel | $83,000 |
| Aug 9, 2000 | Expired or cancelled expired May 2001 | 150 Greenwich St | renew appln #9920428 to final |
Who worked here
Everyone with a license on these permits, by role, with how many permits each is on.
- Contractors
- Cannon Constructors North Inc (4), Ducheney Construction Inc (3), Reinhardt Roofing Inc (3), Hillhouse Construction Company Inc (2), Peters Hvac (2), Rapp Construction Co. (2), Cal-Air Inc, Firemaster
- Architects
- Grant Takahashi Lee (3), James Tefend, Robert Giannini
- Engineers
- Jeff Williams
- Authorized agents
- Southwest Sign Co.
Find contractors for work like this
Starts from the last permit filed here; change it to describe your own project. Results cover every building: the city does not class this parcel as single-family, two-family or apartments.