Sep 2009 to May 2018

4 permits since 2000 (engineer on 4 permits): 4 completed.

CompletedIn progressNever finaledExpired or cancelled

This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records

Most recent permits

FiledOutcomeAddressContractorWork described on the permitDeclared cost
May 9, 2018Completed
final sign-off Aug 2018
555 Selby Stadd as built drawings to application #201606281054 s8/r-1. this was requested by sffd inspector. maher na
Details
Permit
201805098699
Status
complete
Filed
May 9, 2018
Permit issued
May 10, 2018
Final sign-off
Aug 17, 2018
Address
555 Selby St

add as built drawings to application #201606281054 s8/r-1. this was requested by sffd inspector. maher na

Open the permit page

Apr 21, 2011Completed
final sign-off May 2013
555 Pine StRoebbelen Contracting Incupgrades (e)standby generator fueling sys:(n)supply&return piping to bush st 555 pine st: replace leaking piping in bsmt,add redundant fuel supply piping,replace(e)pump sys feeding 430 bush st.facility,upsize retrn piping,upgrade monitor sys.install (n) secondary containment.
Details
Permit
201104214546
Status
complete
Filed
Apr 21, 2011
Permit issued
May 11, 2012
Final sign-off
May 10, 2013
Declared cost
$75,000
Address
555 Pine St

upgrades (e)standby generator fueling sys:(n)supply&return piping to bush st 555 pine st: replace leaking piping in bsmt,add redundant fuel supply piping,replace(e)pump sys feeding 430 bush st.facility,upsize retrn piping,upgrade monitor sys.install (n) secondary containment.

Open the permit page

$75,000
Apr 20, 2011Completed
final sign-off May 2013
430 Bush StGettler-Ryan Incupgrades to (e) standby generator fueling system: (n) fuel supply and return lines from/to 555 pine st. basement
Details
Permit
201104204479
Status
complete
Filed
Apr 20, 2011
Permit issued
Mar 7, 2012
Final sign-off
May 10, 2013
Declared cost
$75,000
Address
430 Bush St

upgrades to (e) standby generator fueling system: (n) fuel supply and return lines from/to 555 pine st. basement

Open the permit page

$75,000
Sep 15, 2009Completed
final sign-off Jun 2010
360 Spear StGettler-Ryan Incremove (e)400 gal generator base fuel tank from roof,replace w/ (n) 200 gal.dw steel day tank, dw piping from day tank to (e)generator within (e) 15ft high metal enclosure. (n)veeder root tls-350 tank monitoring panel/sensors for all (e) & (n)at&t owned fuel sys sensors/probes. sffd permit required
Details
Permit
200909156836
Status
complete
Filed
Sep 15, 2009
Permit issued
Nov 10, 2009
Final sign-off
Jun 23, 2010
Declared cost
$100,000
Address
360 Spear St

remove (e)400 gal generator base fuel tank from roof,replace w/ (n) 200 gal.dw steel day tank, dw piping from day tank to (e)generator within (e) 15ft high metal enclosure. (n)veeder root tls-350 tank monitoring panel/sensors for all (e) & (n)at&t owned fuel sys sensors/probes. sffd permit required

Open the permit page