Peter Petruzzi
- Listed as
- architect, authorized agent-others, designer, engineer
- Firm
- Peter Petruzzi Architect
- Based in
- San Francisco
- On San Francisco permits
- Jul 2000 to Aug 2026
215 permits since 2000 (architect on 205 permits, authorized agent-others on 5 permits, engineer on 4 permits, designer on 1 permit): 126 completed, 13 in progress, 32 never finaled, 44 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
Showing the 100 most recent of 215.
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 14, 2026 | In progress filed Aug 2026, not yet issued | 5241 Geary Bl | barrier removal, remove column, alter entry alcove slope, install batter power activator. install steel channel.Details
barrier removal, remove column, alter entry alcove slope, install batter power activator. install steel channel. | $18,000 | |
| Aug 14, 2026 | In progress issued Sep 2026 | 617 Irving St | Qse Construction | install ada restroom and remove abandoned gas/ water/ elect.Details
install ada restroom and remove abandoned gas/ water/ elect. | $10,000 |
| Aug 5, 2026 | In progress issued Aug 2026 | 197 Anzavista Av | to comply with nov #202655939. permit retaining wall and permit landing.Details
to comply with nov #202655939. permit retaining wall and permit landing. | $15,000 | |
| Jul 24, 2026 | In progress filed Jul 2026, not yet issued | 2306 Broadway | Arisalva Construction | create new pilaster & metal sercurity gate @ front yardDetails
create new pilaster & metal sercurity gate @ front yard | $5,250 |
| Jun 26, 2026 | In progress issued Jul 2026 | 701 Minna St | Arisalva Construction | remodel (2) bathrooms - fixture replacement in kind.Details
remodel (2) bathrooms - fixture replacement in kind. | $70,000 |
| May 4, 2026 | In progress filed May 2026, not yet issued | 164 14th St | to comply with nov 202046581 - fire damage replacement in-kind replace 2 teel beams; replace exterior metal siding of north wallDetails
to comply with nov 202046581 - fire damage replacement in-kind replace 2 teel beams; replace exterior metal siding of north wall | $24,000 | |
| Apr 23, 2026 | Completed final sign-off Oct 2026 | 201 Capistrano Av | Tom Mccaffrey | construct (n) deck and stairs at rear of dwelling. top of deck apprx. 7'-10" above grade. area of deck apprx. 112sf. install (n) waterproofing outlet at deckDetails
construct (n) deck and stairs at rear of dwelling. top of deck apprx. 7'-10" above grade. area of deck apprx. 112sf. install (n) waterproofing outlet at deck | $4,500 |
| Jan 27, 2026 | In progress filed Jan 2026, not yet issued | 4220 California St | remodel existing office spaces into 1 single family dwelling at first and 2nd floor remodel space to kitchen, living, bedrooms and bathroomsDetails
remodel existing office spaces into 1 single family dwelling at first and 2nd floor remodel space to kitchen, living, bedrooms and bathrooms | $157,000 | |
| Oct 21, 2025 | Completed final sign-off Jul 2026 | 41 Mallorca Wy | Pacific Gateway Builders Inc | convert existing ground floor storage to master suite. add warm board radiant heat, bathroom, new pell. all wood lifestyle windows in like kind of existing; remove any residual knob/tub replace with romex move electrical meters from rear to front near gas/ water. new sewer lateral & slab on gradeDetails
convert existing ground floor storage to master suite. add warm board radiant heat, bathroom, new pell. all wood lifestyle windows in like kind of existing; remove any residual knob/tub replace with romex move electrical meters from rear to front near gas/ water. new sewer lateral & slab on grade | $75,000 |
| Sep 10, 2025 | In progress filed Sep 2025, not yet issued | 895 Ofarrell St | partial demolition of (e) partitions, restrooms etc. reconstruct interior partitions, entertainment area. install elevator, new code compliant exit stairs, new restrooms.Details
partial demolition of (e) partitions, restrooms etc. reconstruct interior partitions, entertainment area. install elevator, new code compliant exit stairs, new restrooms. | $2,500,000 | |
| Feb 10, 2025 | Completed final sign-off Dec 2025 | 1040 Bryant St | Inishowen Construction | change of use from b/u to b/f-1 continuation of existing industrial (cultivational) ag. for cannabis and new distribution (wholesale sales)Details
change of use from b/u to b/f-1 continuation of existing industrial (cultivational) ag. for cannabis and new distribution (wholesale sales) | |
| Oct 18, 2024 | Completed final sign-off May 2025 | 617 Irving St | Qse Construction | perform accessibility upgrades per abe report 202307247966 including. relocate hardware on door and install battery operator power actuator.Details
perform accessibility upgrades per abe report 202307247966 including. relocate hardware on door and install battery operator power actuator. | $7,500 |
| Oct 18, 2024 | In progress issued Oct 2024 | 993 Filbert St | Douglas Cleaveland | revision to 202308033633. revised 1st flr bedroom and bathroom layout. revise 2nd flr bedroom and bathroom layout.Details
revision to 202308033633. revised 1st flr bedroom and bathroom layout. revise 2nd flr bedroom and bathroom layout. | |
| Oct 18, 2024 | Completed final sign-off Nov 2024 | 701 Chenery St | Bayside Remodeling & Construction | revisions to permit 202406144495. for abe: 202208303524. relocate access entry to side of building.Details
revisions to permit 202406144495. for abe: 202208303524. relocate access entry to side of building. | |
| Sep 6, 2024 | Completed final sign-off May 2025 | 619 Irving St | Qse Construction | install battery operated power assist and actuator for each address. abe #202308168272.Details
install battery operated power assist and actuator for each address. abe #202308168272. | $4,000 |
| Sep 6, 2024 | Completed final sign-off May 2025 | 621 Irving St | Qse Construction | install battery operated power assist and actuator for abe #202308168273.Details
install battery operated power assist and actuator for abe #202308168273. | $4,000 |
| Jul 22, 2024 | Completed final sign-off Aug 2024 | 37 Niagara Av | Baires Construction Inc | to respond to nov# 202419221: replace (4) railing posts, railing and guardrail at rear of property.Details
to respond to nov# 202419221: replace (4) railing posts, railing and guardrail at rear of property. | $1,500 |
| Jun 14, 2024 | Completed final sign-off Nov 2024 | 701 Chenery St | Bayside Remodeling & Construction | reconfigure restroom for accessible complian construct access to rear entry for abe compliance abe #202208303524Details
reconfigure restroom for accessible complian construct access to rear entry for abe compliance abe #202208303524 | $12,000 |
| May 31, 2024 | Completed final sign-off Aug 2024 | 916 Clement St | O'reilly Construction | comply with abe #202405170105. install powered actuator at entry. replace door. renovate restroom for accessible compliance. extend hardrails at stairs.Details
comply with abe #202405170105. install powered actuator at entry. replace door. renovate restroom for accessible compliance. extend hardrails at stairs. | $18,000 |
| May 31, 2024 | In progress issued Jun 2024 | 690 Sacramento St | Kwong Associates | remove partition wall to enlarge bathroom door opening. replace (e) bathroom door.Details
remove partition wall to enlarge bathroom door opening. replace (e) bathroom door. | $480 |
| May 22, 2024 | Completed final sign-off Sep 2024 | 56 Santa Paula Av | Ademo Construction | bathroom remodel. replace fixtures, 1 new toilet. remove tub and replace with (n) shower. construct new non bearing wallDetails
bathroom remodel. replace fixtures, 1 new toilet. remove tub and replace with (n) shower. construct new non bearing wall | $45,000 |
| Mar 27, 2024 | In progress issued Jul 2026 | 779 Bush St | change of use b to a2( laundromat to bar) ti improvement to 1st fl and basement. install bar, consruct 2 ada restrooms, construct protected 2nd exit. construct 2 hr ceiling between a2 and r3.Details
change of use b to a2( laundromat to bar) ti improvement to 1st fl and basement. install bar, consruct 2 ada restrooms, construct protected 2nd exit. construct 2 hr ceiling between a2 and r3. | $180,000 | |
| Feb 26, 2024 | In progress filed Feb 2024, not yet issued | 619 Irving St | abe 202308168272- demolish entry and construct new to fit 36' door with new glass pane. install power battery operated agitnatorDetails
abe 202308168272- demolish entry and construct new to fit 36' door with new glass pane. install power battery operated agitnator | $8,950 | |
| Feb 26, 2024 | In progress filed Feb 2024, not yet issued | 621 Irving St | to comply with accessible business entrance program ord. 51-16. ref abe 202308168273. demolish entry. construct new entry to fit 36" door. install power actuator, battery operated.Details
to comply with accessible business entrance program ord. 51-16. ref abe 202308168273. demolish entry. construct new entry to fit 36" door. install power actuator, battery operated. | $8,950 | |
| Dec 1, 2023 | Completed final sign-off Jan 2024 | 1031 York St | A G D Construction | revision to pa # 202111011538: rear deck reduced in size. deck raised from 2'-3" to 3'-5" off grade.Details
revision to pa # 202111011538: rear deck reduced in size. deck raised from 2'-3" to 3'-5" off grade. | |
| Oct 10, 2023 | Completed final sign-off Mar 2024 | 818 Leavenworth St | Qse Construction | voluntary lateral force-resisiting system alterations also revovating existing restroom to full accessible restroomDetails
voluntary lateral force-resisiting system alterations also revovating existing restroom to full accessible restroom | $25,000 |
| Aug 25, 2023 | Completed final sign-off Sep 2024 | 3378 24th St | to comply w/accessible business entry progr/ordinance 51-16, abe 202002262300. install baterry operated power actuator per da-04/da-05, relocate hardware fore operating height compliance. replace door handle with lever.Details
to comply w/accessible business entry progr/ordinance 51-16, abe 202002262300. install baterry operated power actuator per da-04/da-05, relocate hardware fore operating height compliance. replace door handle with lever. | $4,500 | |
| Aug 25, 2023 | Expired or cancelled withdrawn Dec 2023 | 3376 24th St | install baterry operated power actuator per da .04/da-05 relocate hardware fore operating height compliance. replace door handle with level abe 20200226229Details
install baterry operated power actuator per da .04/da-05 relocate hardware fore operating height compliance. replace door handle with level abe 20200226229 | $4,500 | |
| Aug 3, 2023 | Never finaled issued Aug 2023, no final | 993 Filbert St | Douglas Cleaveland | remodel, relocate (e) kitchen, bathroom, install closets, insulate exterior walls, ceiling & 5/8" typ x gypbd, install hydronic heating, capture portion of (e) garage level for new bedroom, new electrical/lighting. adding bedroom on 1st fl w/in (e) evelope @ garageDetails
remodel, relocate (e) kitchen, bathroom, install closets, insulate exterior walls, ceiling & 5/8" typ x gypbd, install hydronic heating, capture portion of (e) garage level for new bedroom, new electrical/lighting. adding bedroom on 1st fl w/in (e) evelope @ garage | $210,000 |
| Jul 19, 2023 | Completed final sign-off Nov 2023 | 2055 Sacramento St | Architectural Fenestration & Restoration | units 206, 306, 406, 506, 606, 706, 806, 906: replace south facing windows at 8 units (not facing street), glazing approx. 123.37 sq.ft each unit.Details
units 206, 306, 406, 506, 606, 706, 806, 906: replace south facing windows at 8 units (not facing street), glazing approx. 123.37 sq.ft each unit. | $30,000 |
| Jul 13, 2023 | Completed final sign-off Oct 2023 | 107 Leland Av | E.A.Davidovits &Co.,Inc. | to comply w/accessible building entry program per ord. 51-16. ref abe 201911047758. infill gap in entry gate greater than 0.5" elevation change. adjust door pressure to 5lbs.Details
to comply w/accessible building entry program per ord. 51-16. ref abe 201911047758. infill gap in entry gate greater than 0.5" elevation change. adjust door pressure to 5lbs. | $3,500 |
| Jun 21, 2023 | Completed final sign-off Sep 2023 | 1029 York St | Cross-Cut Const/Mat Dudek | remove existing windows at rear of house and replace in-kind, remove window between enclosed porch & kitchen, install 2-light fixtures, two outlets.Details
remove existing windows at rear of house and replace in-kind, remove window between enclosed porch & kitchen, install 2-light fixtures, two outlets. | $20,000 |
| Jun 2, 2023 | Completed final sign-off Jun 2023 | 877 Bryant St | no work- abe 201812102847- technical infeasibility, structural impedimentDetails
no work- abe 201812102847- technical infeasibility, structural impediment | ||
| May 10, 2023 | Completed final sign-off Aug 2024 | 4264 Mission St | Inishowen Construction | replace in kind exterior convenience staircase at rear of commercial unit 4264 mission st.not part of egress access nor required to beDetails
replace in kind exterior convenience staircase at rear of commercial unit 4264 mission st.not part of egress access nor required to be | $4,000 |
| Mar 20, 2023 | Completed final sign-off Nov 2023 | 2055 Sacramento St | Architectural Fenestration & Restoration | apts 1006: replace south facing windows for 3 apts in-kind. glazing approx 123.37sf in each apt. to comply with nov202296291Details
apts 1006: replace south facing windows for 3 apts in-kind. glazing approx 123.37sf in each apt. to comply with nov202296291 | $25,000 |
| Feb 21, 2023 | Expired or cancelled cancelled Jan 2026 | 1844 Divisadero St | abe # 202206210746, install power actuator on both inside and outside as alternate means per da 04&05 side clearance & level landingDetails
abe # 202206210746, install power actuator on both inside and outside as alternate means per da 04&05 side clearance & level landing | $4,500 | |
| Feb 21, 2023 | Completed final sign-off May 2023 | 1660 Haight St | Nelson Jameson Construction Inc | rev to bpa# 202209212879, accessible modifications for compliance w/seismic retrofit, replace knob handles lever hardware @ (3) doors, replace toilet cistern w/new cistern having flush handle os rightDetails
rev to bpa# 202209212879, accessible modifications for compliance w/seismic retrofit, replace knob handles lever hardware @ (3) doors, replace toilet cistern w/new cistern having flush handle os right | $1,645 |
| Jan 23, 2023 | Completed final sign-off May 2023 | 735 Columbus Av | abe program: technical infeasibility. doorbell installed as alternate means & product menu in window. abe# 202209214605Details
abe program: technical infeasibility. doorbell installed as alternate means & product menu in window. abe# 202209214605 | ||
| Dec 12, 2022 | Completed final sign-off Jul 2023 | 700 25th Av | Inishowen Construction | modifying top of existing blended transition to be compliant with accessible business entrance ord. 51-16. install. abe 202205311168Details
modifying top of existing blended transition to be compliant with accessible business entrance ord. 51-16. install. abe 202205311168 | $6,000 |
| Dec 5, 2022 | Completed final sign-off Jun 2023 | 2722 Gough St | Seiko Construction Co. | relocate (e) full bath to 3rd floor/demolish (e) bath. demolish-install kitchen. install powder rm 2nd floor. misc lighting/electrical. new closets all bedrooms.Details
relocate (e) full bath to 3rd floor/demolish (e) bath. demolish-install kitchen. install powder rm 2nd floor. misc lighting/electrical. new closets all bedrooms. | $58,000 |
| Dec 5, 2022 | Completed final sign-off Sep 2023 | 991 Filbert St | Douglas Cleaveland | interior remodel - kitchen, bathroom, 2 closets.Details
interior remodel - kitchen, bathroom, 2 closets. | $85,000 |
| Oct 24, 2022 | Expired or cancelled withdrawn Sep 2023 | 1786 Carroll Av | installation of co2 system @ 1st level. anchorage of co2 tank. installation of piping. installation of gas detection system. ref pa#202207289481.Details
installation of co2 system @ 1st level. anchorage of co2 tank. installation of piping. installation of gas detection system. ref pa#202207289481. | $7,500 | |
| Sep 2, 2022 | Completed final sign-off May 2023 | 1660 Haight St | Nelson Jameson Construction Inc | abe program/ alter ramp slope. new handrails. install paver actuator per da-004. install new doors with buttom. remove tiles on ramp. abe # 202002041690.Details
abe program/ alter ramp slope. new handrails. install paver actuator per da-004. install new doors with buttom. remove tiles on ramp. abe # 202002041690. | $9,552 |
| Aug 17, 2022 | Expired or cancelled cancelled Sep 2025 | 3167 21st St | abe# 2022-0405-0206. installing power actuator in lieu of side clearance.Details
abe# 2022-0405-0206. installing power actuator in lieu of side clearance. | $4,200 | |
| Jul 28, 2022 | Completed final sign-off Jul 2024 | 1786 Carroll Av | change of occupancy from s-2 to f-1 & b. ref permit 201808026337Details
change of occupancy from s-2 to f-1 & b. ref permit 201808026337 | ||
| Jul 26, 2022 | Never finaled issued Mar 2023, no final | 201 Turk St | Pacific General Construct | unit a: install self circulating ventless electric cooking appliance. construct approx 27 l.ft of partition.Details
unit a: install self circulating ventless electric cooking appliance. construct approx 27 l.ft of partition. | $10,487 |
| Jun 21, 2022 | Expired or cancelled cancelled Sep 2025 | 3171 21st St | abe# 202204050205. installing power actuator in lieu of side clearance and level landing.Details
abe# 202204050205. installing power actuator in lieu of side clearance and level landing. | $4,000 | |
| Jun 7, 2022 | Completed final sign-off Dec 2022 | 3004 24th St | Cross-Cut Const/Mat Dudek | abe building permit. remove step, slope, install power activators. relocate deadbolt. remove existing pull install new complaint pull. to comple with abe# 202011042990Details
abe building permit. remove step, slope, install power activators. relocate deadbolt. remove existing pull install new complaint pull. to comple with abe# 202011042990 | $5,000 |
| Jun 7, 2022 | Completed final sign-off Feb 2024 | 4733 Geary Bl | Nelson Jameson Construction Inc | to comply w/abe program per ord 51-16 - restripe parking lot for accessible stall. alter entry slope add power actuator primary. comply with abe 201902115049Details
to comply w/abe program per ord 51-16 - restripe parking lot for accessible stall. alter entry slope add power actuator primary. comply with abe 201902115049 | $7,000 |
| Jun 3, 2022 | Completed final sign-off Mar 2023 | 877 Bryant St | deffered mep for replacing (1) 4-ton heat pump, (1) 4-ton condenser and (1) ductless 2-ton samsung - minor distrubtion duct rework. ref pa# 2021-0504-9786-sDetails
deffered mep for replacing (1) 4-ton heat pump, (1) 4-ton condenser and (1) ductless 2-ton samsung - minor distrubtion duct rework. ref pa# 2021-0504-9786-s | $15,500 | |
| May 31, 2022 | Expired or cancelled suspend Sep 2022 | 949 Fell St | Tom Mccaffrey | unit #3 and #5: add washer and dryer in each unit. make soffit and drywall to close in ductwork.Details
unit #3 and #5: add washer and dryer in each unit. make soffit and drywall to close in ductwork. | $5,000 |
| May 13, 2022 | Completed final sign-off Aug 2022 | 4527 Mission St | Nelson Jameson Construction Inc | change of use from an office to a vetenirary clinic. demo approx 20lf of non bearing non reted partition. enlarge (e) restroom to be accessible complaint. revise (e) elevation change on ramps to 1:20 transirion. install misc. elec.Details
change of use from an office to a vetenirary clinic. demo approx 20lf of non bearing non reted partition. enlarge (e) restroom to be accessible complaint. revise (e) elevation change on ramps to 1:20 transirion. install misc. elec. | $110,000 |
| May 13, 2022 | Completed final sign-off Jun 2023 | 587 Lisbon St | Valenciana Concrete Inc, Mill Valley Builders Inc | revision to pa# 202103156563. removal of fire damaged materials. original plans indicated w/ clouding. install guard along front retaining wall. install recessed light fixture throughout. relocate furnace. (n) 90% afue. replace (e) light fixtures with led. (n) recessed lights & closet lighting.Details
revision to pa# 202103156563. removal of fire damaged materials. original plans indicated w/ clouding. install guard along front retaining wall. install recessed light fixture throughout. relocate furnace. (n) 90% afue. replace (e) light fixtures with led. (n) recessed lights & closet lighting. | $4,200 |
| May 9, 2022 | Completed final sign-off Jan 2023 | 989 Filbert St | Douglas Cleaveland | interior residential remodel: renovate kitchen, 2 bathrooms, demolish 2 fireplaces, approx. 39 lf of non bearing non rated construction approx 37 lf of non bearing non rated wall. no increase in plmg fixture count.Details
interior residential remodel: renovate kitchen, 2 bathrooms, demolish 2 fireplaces, approx. 39 lf of non bearing non rated construction approx 37 lf of non bearing non rated wall. no increase in plmg fixture count. | $110,000 |
| May 5, 2022 | Never finaled issued Dec 2022, no final | 1981 Funston Av | Sasso Construction Inc. | apt b. remove angled wall at master bedroom. extend east wall of bedroom approx 8' south and south wall approx 8' east to create squared corner. add (n) door to (e) escape and rescue area deck. (e) bldg is fully sprinkled. 35 sf added to (e) master bedroom.Details
apt b. remove angled wall at master bedroom. extend east wall of bedroom approx 8' south and south wall approx 8' east to create squared corner. add (n) door to (e) escape and rescue area deck. (e) bldg is fully sprinkled. 35 sf added to (e) master bedroom. | $18,000 |
| Mar 25, 2022 | Never finaled issued Jun 2022, no final | 333 Beale St | Daly City Iron Works | install security pickets along exterior planting.Details
install security pickets along exterior planting. | $5,000 |
| Nov 1, 2021 | Completed final sign-off Jan 2024 | 1031 York St | A G D Construction | remove non rated/non bearing partitions, construction 2 bedrooms/ 2 bathrooms. new lighting, insulation fire rated property line walls. replace windows not facing street. new rear deck (15" above grade)Details
remove non rated/non bearing partitions, construction 2 bedrooms/ 2 bathrooms. new lighting, insulation fire rated property line walls. replace windows not facing street. new rear deck (15" above grade) | $122,000 |
| Oct 22, 2021 | Completed final sign-off Jul 2022 | 49 Clayton St | replace in-kind (e) wood stair in light well. replace (e) guard with new compliant guard.Details
replace in-kind (e) wood stair in light well. replace (e) guard with new compliant guard. | $4,500 | |
| Oct 14, 2021 | Completed final sign-off Oct 2022 | 2982 Mission St | Mulderrig Painting | accessible business entrance program. install power actuaor, new door and reslope entry.Details
accessible business entrance program. install power actuaor, new door and reslope entry. | $8,500 |
| Oct 1, 2021 | Expired or cancelled cancelled Jan 2026 | 201 Folsom St | security upgrades for 6 pairs of balanced doors in common area. remove (e) door strike at 6 locations. install maglock on each leaf at 6 locations. install overhead motion sensor for unlocking on inside at 6 locations. install 1 jamb side mounted exit request button at inside of each opening-centerDetails
security upgrades for 6 pairs of balanced doors in common area. remove (e) door strike at 6 locations. install maglock on each leaf at 6 locations. install overhead motion sensor for unlocking on inside at 6 locations. install 1 jamb side mounted exit request button at inside of each opening-center | $23,000 | |
| Aug 27, 2021 | Completed final sign-off Feb 2022 | 1831 Divisadero St | Nelson Jameson Construction Inc | remove existing windows in interior lightwell. replace in-kind with dual glazed ufactor .26 shgc .23 vt.57. @ residential upstairsDetails
remove existing windows in interior lightwell. replace in-kind with dual glazed ufactor .26 shgc .23 vt.57. @ residential upstairs | $3,200 |
| Jul 14, 2021 | Completed final sign-off Dec 2021 | 2513 Mission St | Future General Construction Inc | abe compliance plans/barrier removal. remove extg step, constuct ramp, install poiver actuators da.004. use of poiver doors inlieu of level landing.Details
abe compliance plans/barrier removal. remove extg step, constuct ramp, install poiver actuators da.004. use of poiver doors inlieu of level landing. | $5,000 |
| Jul 14, 2021 | Completed final sign-off Mar 2022 | 2515 Mission St | Future General Construction Inc | abe compliance plans. remove (e) doors, extend jamb, install new doors, power actuators. da-004 use of power doors in lieu of level landing.Details
abe compliance plans. remove (e) doors, extend jamb, install new doors, power actuators. da-004 use of power doors in lieu of level landing. | $10,000 |
| Jun 22, 2021 | Never finaled issued Nov 2021, no final | 1098 Howard St | to comply with nov #202178647, #20068442: install walk-in coolerDetails
to comply with nov #202178647, #20068442: install walk-in cooler | $2,500 | |
| Jun 16, 2021 | Expired or cancelled cancelled Aug 2023 | 1837 Divisadero St | Nelson Jameson Construction Inc | abe per ord 51-16: remove front step/replace w/ ramp & power actuator. install tile to match (e) pattern & color.Details
abe per ord 51-16: remove front step/replace w/ ramp & power actuator. install tile to match (e) pattern & color. | $6,000 |
| Jun 8, 2021 | Completed final sign-off Jan 2023 | 632 45th Av | Construction America | level (e) house. install footing @ crawl space.replace wood foundation w/conc. replace front conc steps remove & replace facade stucco. replace conc. walkway not on row) replace conc. pad @ laudry rm, install insulation @ north wallDetails
level (e) house. install footing @ crawl space.replace wood foundation w/conc. replace front conc steps remove & replace facade stucco. replace conc. walkway not on row) replace conc. pad @ laudry rm, install insulation @ north wall | $65,000 |
| May 4, 2021 | Completed final sign-off Mar 2023 | 877 Bryant St | land use change request for cannabis retail, distribution, non-volatile manufacturing on 1st floor, 2nd floor and basement. change of occupancy 1st floor a2 to m, basement b to f1. upgrade north facing entry to ada compliance. remove previous west facing restaurant entry and windows, interior t.i.Details
land use change request for cannabis retail, distribution, non-volatile manufacturing on 1st floor, 2nd floor and basement. change of occupancy 1st floor a2 to m, basement b to f1. upgrade north facing entry to ada compliance. remove previous west facing restaurant entry and windows, interior t.i. | ||
| Apr 16, 2021 | Completed final sign-off Aug 2024 | 4260 Mission St | Inishowen Construction | mandatory soft story retrofit per sfebc ch 4d & 2019 cebc appendix a-4. 3 accessible bathrooms. 2 door actuators per ab05. (commercial portion)Details
mandatory soft story retrofit per sfebc ch 4d & 2019 cebc appendix a-4. 3 accessible bathrooms. 2 door actuators per ab05. (commercial portion) | $32,000 |
| Apr 16, 2021 | Completed final sign-off Aug 2024 | 4260 Mission St | Inishowen Construction | mandatory soft story retrofit per sfebc ch 4d & 2019 cebc appendix a-4. (residential portion)Details
mandatory soft story retrofit per sfebc ch 4d & 2019 cebc appendix a-4. (residential portion) | $64,000 |
| Mar 15, 2021 | Completed final sign-off Jun 2023 | 587 Lisbon St | Bay Area Construction & Remodeling, Valenciana Concrete Inc, Mill Valley Builders Inc | to comply with nov# 202041531: fire damage repair: street facing siding and entry steps. replace gyp bd removed by fire, smoke, water damage. replace kitchen cabinets, windows at facade, relocated electrical, plmbg. legalize extg non habitable on 1st floor.Details
to comply with nov# 202041531: fire damage repair: street facing siding and entry steps. replace gyp bd removed by fire, smoke, water damage. replace kitchen cabinets, windows at facade, relocated electrical, plmbg. legalize extg non habitable on 1st floor. | $190,000 |
| Feb 9, 2021 | Completed final sign-off May 2021 | 1831 Divisadero St | Nelson Jameson Construction Inc | to comply with nov # 202050813. remove wd framing & corrugated fiberglass roof over existing light well.Details
to comply with nov # 202050813. remove wd framing & corrugated fiberglass roof over existing light well. | $2,000 |
| Oct 2, 2020 | Never finaled issued Nov 2020, no final | 1098 Howard St | change from deli to specialty grocery. install shelving/remove tables.Details
change from deli to specialty grocery. install shelving/remove tables. | $500 | |
| Mar 13, 2020 | Completed final sign-off Apr 2023 | 15 Massasoit St | Nelson Jameson Construction Inc | comply with nov 201907211 legalize ground floor rooms: bedroom, living room, full bath, and kitchenette.Details
comply with nov 201907211 legalize ground floor rooms: bedroom, living room, full bath, and kitchenette. | |
| Jan 7, 2020 | Completed final sign-off Feb 2020 | 3171 21st St | remove latex paint from vitrolite tiles on 1st floor exterior facade per 2019001460 enf.Details
remove latex paint from vitrolite tiles on 1st floor exterior facade per 2019001460 enf. | $500 | |
| Oct 1, 2019 | Completed final sign-off May 2022 | 5116 Geary Bl | install power actuator for abe accessible business entrance program per ord 51-16Details
install power actuator for abe accessible business entrance program per ord 51-16 | $4,000 | |
| Sep 12, 2019 | Completed final sign-off Mar 2020 | 2810 Diamond St | Gil Construction & Assoc Inc. | patch concrete at front of business, test activation operation. to comply with abe programDetails
patch concrete at front of business, test activation operation. to comply with abe program | $500 |
| Aug 16, 2019 | Expired or cancelled cancelled Jan 2026 | 1611 Lombard St | accessible business entry program. replace door with 3'-0" door. install power activator. install sign and doorbell per ordinance 51-16Details
accessible business entry program. replace door with 3'-0" door. install power activator. install sign and doorbell per ordinance 51-16 | $10,850 | |
| Jun 21, 2019 | Completed final sign-off Oct 2019 | 1564 Bush St | Nelson Jameson Construction Inc | response to nov 201945881. replace extg restroom with accessible restroom. install breakroom, 3 consulting rooms, new storefront window at right, replace extg lighting, reconfigure hvac ducting. permitted change of use from dry cleaner to services, health.(family counseling)Details
response to nov 201945881. replace extg restroom with accessible restroom. install breakroom, 3 consulting rooms, new storefront window at right, replace extg lighting, reconfigure hvac ducting. permitted change of use from dry cleaner to services, health.(family counseling) | $106,792 |
| Jun 5, 2019 | Completed final sign-off Apr 2023 | 1901 Pacific Av | Nextech Security Solutions | revised 11/12/21: restore legal use & occupancy of this 9 unit apt building. correct all work done w/o permit-separate eid & pid permits to be obtained for final inspec. comply w/planning enf case 2018-012306enf. resolve 201889561;201890541;201809811;201809801. comp. 201989472 to be resolved sep.Details
revised 11/12/21: restore legal use & occupancy of this 9 unit apt building. correct all work done w/o permit-separate eid & pid permits to be obtained for final inspec. comply w/planning enf case 2018-012306enf. resolve 201889561;201890541;201809811;201809801. comp. 201989472 to be resolved sep. | $500 |
| Apr 26, 2019 | Never finaled issued May 2019, no final | 645 Valencia St | Zarc Construction Inc | for dph review only as dph was bypassed under pa# 2018-1228-9325.Details
for dph review only as dph was bypassed under pa# 2018-1228-9325. | |
| Apr 16, 2019 | Completed final sign-off Jul 2019 | 1265 Folsom St | Electric Works | mandatory disability access improvement program. install power actuator. per abe program per ordinance 51-16.Details
mandatory disability access improvement program. install power actuator. per abe program per ordinance 51-16. | $6,500 |
| Apr 16, 2019 | Completed final sign-off Jul 2019 | 271 09th St | Electric Works | mandatory disability access program. install power actuator da004/da005. per abe program per ordinance 51-16.Details
mandatory disability access program. install power actuator da004/da005. per abe program per ordinance 51-16. | $6,200 |
| Apr 12, 2019 | Completed final sign-off May 2019 | 650 Church St | Peter Spediacci Company | to comply with nov 201800321 0new permit to remove chimney for apartment 1 & 2Details
to comply with nov 201800321 0new permit to remove chimney for apartment 1 & 2 | $2,500 |
| Apr 4, 2019 | Expired or cancelled cancelled Jan 2026 | 72 Converse St | install 4 fire separation doors to allow for communicating openings between building aat 1040 bryant st (3575/026).Details
install 4 fire separation doors to allow for communicating openings between building aat 1040 bryant st (3575/026). | $10,000 | |
| Apr 1, 2019 | Never finaled filed Apr 2019, never issued | 1901 Pacific Av | nov #201890542. removal of (2) chimneys & installing of (1) 3x2 window @ rear of building. not visible from street. ** maher: n/a **Details
nov #201890542. removal of (2) chimneys & installing of (1) 3x2 window @ rear of building. not visible from street. ** maher: n/a ** | $15,000 | |
| Feb 5, 2019 | Completed final sign-off Jul 2019 | 516 Green St | Gene Catania Construction | abatement of violation 2015-004865enf cont approx 10'-6" of non bearing/non rated partitionDetails
abatement of violation 2015-004865enf cont approx 10'-6" of non bearing/non rated partition | $1,200 |
| Feb 5, 2019 | Never finaled filed Feb 2019, never issued | 1732 Taraval St | correction of notice of violation 2017-00993enf construct a rated tunnel from the rear dwelling unit to the st exterior. modify the exterior. separate b/r3 occupancies with 2 hr separation (1st fl); 2nd floor install kitchenDetails
correction of notice of violation 2017-00993enf construct a rated tunnel from the rear dwelling unit to the st exterior. modify the exterior. separate b/r3 occupancies with 2 hr separation (1st fl); 2nd floor install kitchen | $9,000 | |
| Jan 10, 2019 | Expired or cancelled expired Jul 2024 | 1786 Carroll Av | Scott Cassell Construction | occupancy change from s-2 to f-1 & b for cannabis. minor tenant improvement: construction of non-load bearing rated walls & restroom all on mezz/2nd floor. b occupancy is only on the 2nd flr.**maher n/a**Details
occupancy change from s-2 to f-1 & b for cannabis. minor tenant improvement: construction of non-load bearing rated walls & restroom all on mezz/2nd floor. b occupancy is only on the 2nd flr.**maher n/a** | |
| Jan 10, 2019 | Expired or cancelled cancelled Aug 2023 | 1351 Polk St | no work occupancy load calculations onlyDetails
no work occupancy load calculations only | ||
| Dec 28, 2018 | Completed final sign-off Apr 2019 | 645 Valencia St | renovate extg restrooms. install accessible complaint restroom.Details
renovate extg restrooms. install accessible complaint restroom. | $50,000 | |
| Dec 28, 2018 | Expired or cancelled withdrawn Apr 2021 | 1950 Cesar Chavez St | brick masonry repair interior pilaster replacement. n/a for maherDetails
brick masonry repair interior pilaster replacement. n/a for maher | $45,000 | |
| Nov 14, 2018 | Never finaled issued May 2019, no final | 539 Octavia St | Tom Mccaffrey | compliance with mandatory seismic retrofit program per fema p-807. (residential)Details
compliance with mandatory seismic retrofit program per fema p-807. (residential) | $18,000 |
| Nov 14, 2018 | Expired or cancelled expired Mar 2024 | 535 Octavia St | Tom Mccaffrey | compliance with mandatory seismic retrofit program per fema p-807. (commercial). includes ada compliance submittal.Details
compliance with mandatory seismic retrofit program per fema p-807. (commercial). includes ada compliance submittal. | $7,000 |
| Aug 7, 2018 | Expired or cancelled cancelled Jan 2026 | 63 Casa Wy | replace extg kitchen cabinets. new appliances relocate extg laundry room, adjacent to kitchen. install new bathroomn in extg bedroom.Details
replace extg kitchen cabinets. new appliances relocate extg laundry room, adjacent to kitchen. install new bathroomn in extg bedroom. | $32,000 | |
| Jun 14, 2018 | Completed final sign-off Jun 2018 | 177 Stillman St | Nelson Jameson Construction Inc | revision to pa 2018-0529-0340 per inspector's request to change disability checklistDetails
revision to pa 2018-0529-0340 per inspector's request to change disability checklist | |
| Jun 6, 2018 | Expired or cancelled withdrawn Jun 2026 | 69 Hill St | create (2) legal units per ordinance 162-16. (seismic separate permit)Details
create (2) legal units per ordinance 162-16. (seismic separate permit) | $75,000 | |
| May 29, 2018 | Completed final sign-off Jun 2018 | 177 Stillman St | Nelson Jameson Construction Inc | barrier removal alter restroom for compliance with clear floor spaceDetails
barrier removal alter restroom for compliance with clear floor space | $8,000 |
| Apr 27, 2018 | Expired or cancelled cancelled Jun 2020 | 1040 Bryant St | Schrobsdorff Construction | fire dept licensure requirement co2 lines. ref pa 2015-0817-4403 and 2015-1223-5857Details
fire dept licensure requirement co2 lines. ref pa 2015-0817-4403 and 2015-1223-5857 | |
| Apr 27, 2018 | Expired or cancelled cancelled Jul 2023 | 150 Potrero Av | Schrobsdorff Construction | fire dept licensure requirement co2 lines. ref pa 2016-0629-1174Details
fire dept licensure requirement co2 lines. ref pa 2016-0629-1174 | |
| Jan 26, 2018 | Completed final sign-off Sep 2019 | 156 Evelyn Wy | install new foundation. add bathroom. reconfigure lower level for legal head room.Details
install new foundation. add bathroom. reconfigure lower level for legal head room. | $82,820 |