Ophelia Lau
- Listed as
- architect, designer, engineer
- On San Francisco permits
- May 2011 to Sep 2023
8 permits since 2000 (engineer on 5 permits, architect on 2 permits, designer on 1 permit): 4 completed, 3 never finaled, 1 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Sep 5, 2023 | Never finaled issued Sep 2023, no final | 1 Taylor St | Esquivel Grading & Paving, Inc. | demo & replacement of topping sidewalk, partial demo of basement roof slab & reconstruction w/traffic signal foundation concrete belowDetails
demo & replacement of topping sidewalk, partial demo of basement roof slab & reconstruction w/traffic signal foundation concrete below | $20,000 |
| Sep 5, 2023 | Expired or cancelled cancelled Jul 2026 | 1182 Market St | Esquivel Grading & Paving, Inc. | concrete topping sidewalk replacement & removal of (e) traffic signal poleDetails
concrete topping sidewalk replacement & removal of (e) traffic signal pole | $20,000 |
| Mar 9, 2023 | Never finaled issued Jun 2023, no final | 948 Market St | Esquivel Grading & Paving, Inc. | replace sub sidewalk basement roof slab affected by gtraffic signal poles and curb rampsDetails
replace sub sidewalk basement roof slab affected by gtraffic signal poles and curb ramps | $300,000 |
| Dec 15, 2022 | Never finaled issued Jun 2023, no final | 2 Turk St | Esquivel Grading & Paving, Inc. | replace sub-sidewalk basement roof slab affected by traffic signal poles and curb ramps.Details
replace sub-sidewalk basement roof slab affected by traffic signal poles and curb ramps. | $300,000 |
| Aug 24, 2018 | Completed final sign-off Aug 2020 | 625 Polk St | installation of caltrans 1-a pole foundation over existing sub sidewalk basement.Details
installation of caltrans 1-a pole foundation over existing sub sidewalk basement. | $20,000 | |
| Aug 16, 2013 | Completed final sign-off Jan 2014 | 1801 18th Av | revision to 201305237731. add new 1/2 bath in lieu of new full bath to 2nd fl. revise kitchen layout and add 2 windows at 1st flDetails
revision to 201305237731. add new 1/2 bath in lieu of new full bath to 2nd fl. revise kitchen layout and add 2 windows at 1st fl | ||
| Feb 10, 2012 | Completed final sign-off May 2013 | 120 Encline Ct | D M Pauletich & Sons Contruction | addition of 2 new bedrooms, 1.5 bathrooms, new workshop & new storage room on 1st floor (garage)Details
addition of 2 new bedrooms, 1.5 bathrooms, new workshop & new storage room on 1st floor (garage) | $60,000 |
| May 5, 2011 | Completed final sign-off Aug 2011 | 60 Mill St | add new deck at rear of builidngDetails
add new deck at rear of builidng | $3,000 |