Edgar Lindsley Mceachron
- Listed as
- architect, authorized agent-others
- Firm
- Mceachron Architects, Inc.
- Based in
- San Francisco
- On San Francisco permits
- Feb 2005 to Mar 2021
23 permits since 2000 (architect on 21 permits, authorized agent-others on 2 permits): 20 completed, 3 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Mar 5, 2021 | Completed final sign-off Apr 2022 | 2550 Vallejo St | Stroub Construction | revision to pa# 201912098981. remove post in garage. addition of beams + 3 posts. reduce size of existing mechanical room.Details
revision to pa# 201912098981. remove post in garage. addition of beams + 3 posts. reduce size of existing mechanical room. | $25,000 |
| Nov 2, 2017 | Completed final sign-off Oct 2019 | 2864 Broadway | Moroso Construction Inc | new wood convenience stairs from basement to grade, fenestration changes @ rear, not visable from public ways, repair dry rot as required, replace interior non-compliant stairs with new compliant stair. basement-relocate kitchen from 1/f,Details
new wood convenience stairs from basement to grade, fenestration changes @ rear, not visable from public ways, repair dry rot as required, replace interior non-compliant stairs with new compliant stair. basement-relocate kitchen from 1/f, | $750,000 |
| Jan 8, 2016 | Completed final sign-off May 2017 | 2636 Vallejo St | Stroub Construction | this is a revision to pa#201508285529, remove existing wood balustrade at lower landing of front entry steps and replace with brick veneer wall to match surrounding wall. n/a ordinance #155-13Details
this is a revision to pa#201508285529, remove existing wood balustrade at lower landing of front entry steps and replace with brick veneer wall to match surrounding wall. n/a ordinance #155-13 | $6,000 |
| Aug 28, 2015 | Completed final sign-off May 2017 | 2636 Vallejo St | Stroub Construction | this is a revision to permit 201504032809; new painted metal gate at front porch, re-frame existing front entry steps to relocate landing.Details
this is a revision to permit 201504032809; new painted metal gate at front porch, re-frame existing front entry steps to relocate landing. | $20,000 |
| Apr 3, 2015 | Completed final sign-off May 2017 | 2636 Vallejo St | Stroub Construction | revision to pa# 2013/11/25/2758. revised skylight location. new metal guardrail in (e) location @ rear deck. new garage door in (e) location. additional locations to receive brick veneer @ front facade. 2 new windows (on side & rear facades) as shown on previously approved plans & title 24.Details
revision to pa# 2013/11/25/2758. revised skylight location. new metal guardrail in (e) location @ rear deck. new garage door in (e) location. additional locations to receive brick veneer @ front facade. 2 new windows (on side & rear facades) as shown on previously approved plans & title 24. | $15,000 |
| Jan 29, 2015 | Completed final sign-off May 2017 | 2636 Vallejo St | Stroub Construction | revision to appl #2014.1125.2504: minor revision to wall layout, interior only. framing adjustments due to framing varations uncovered during construction. n/a maher ordinanceDetails
revision to appl #2014.1125.2504: minor revision to wall layout, interior only. framing adjustments due to framing varations uncovered during construction. n/a maher ordinance | $1,000 |
| Nov 25, 2014 | Completed final sign-off May 2017 | 2636 Vallejo St | Stroub Construction | revision to 201407111078 due to existing framing being different from assumed in structural drawings. minor interior play layout changesDetails
revision to 201407111078 due to existing framing being different from assumed in structural drawings. minor interior play layout changes | $10,000 |
| Sep 30, 2014 | Completed final sign-off May 2022 | 3701 Washington St | revision to 201109124425 to include expanding the existing garage deptth by 16'0 (300 sf)Details
revision to 201109124425 to include expanding the existing garage deptth by 16'0 (300 sf) | $60,000 | |
| Jul 11, 2014 | Completed final sign-off May 2017 | 2636 Vallejo St | Stroub Construction | interior work only - no change to height or bulk or to exterior bldg. facade. full seismic upgrade, new foundation, excavation to lower garage level. demo of winder stair and extend primary stair to all levels . install elevator from garage to 3rd floor, mech under app #201311252758s,Details
interior work only - no change to height or bulk or to exterior bldg. facade. full seismic upgrade, new foundation, excavation to lower garage level. demo of winder stair and extend primary stair to all levels . install elevator from garage to 3rd floor, mech under app #201311252758s, | $600,000 |
| Nov 25, 2013 | Completed final sign-off May 2017 | 2636 Vallejo St | Stroub Construction | build out area under(e) 2nd floor deck. cut back roof at rear to enlarge (e) roof deck. ** maher: compliance with ordinance no# 155-13 not required **Details
build out area under(e) 2nd floor deck. cut back roof at rear to enlarge (e) roof deck. ** maher: compliance with ordinance no# 155-13 not required ** | $800,000 |
| Aug 14, 2013 | Completed final sign-off Mar 2014 | 205 Hoffman Av | remove existing exterior deck . new exterior deck with new star to grade.Details
remove existing exterior deck . new exterior deck with new star to grade. | $20,000 | |
| Dec 13, 2012 | Completed final sign-off Apr 2013 | 28 Allen St | Stroub Construction | revision to app#201210303171. 2nd level:reconfigure bath #2 lay out including removing extg french doors and replaceing with smaller window.Details
revision to app#201210303171. 2nd level:reconfigure bath #2 lay out including removing extg french doors and replaceing with smaller window. | $6,500 |
| Oct 30, 2012 | Completed final sign-off Apr 2013 | 28 Allen St | Stroub Construction | 1st fl reconfigure bedroom closet, renovate bath #1, new cabinets at kitchen. 2nd fl: reconfigure study, new powder room. reconfigure closets at bedroom 2, renovate bath 2. no new conditioned space. no increase in evelope . no alteration of facade, no structuralDetails
1st fl reconfigure bedroom closet, renovate bath #1, new cabinets at kitchen. 2nd fl: reconfigure study, new powder room. reconfigure closets at bedroom 2, renovate bath 2. no new conditioned space. no increase in evelope . no alteration of facade, no structural | $45,000 |
| Oct 25, 2012 | Completed final sign-off Apr 2013 | 28 Allen St | Stroub Construction | to comply with complaint #201272442. replace extg foundation. add plywood sheathing, bolts, and clips at garage level. replace extg slab.Details
to comply with complaint #201272442. replace extg foundation. add plywood sheathing, bolts, and clips at garage level. replace extg slab. | $180,000 |
| Sep 6, 2012 | Completed final sign-off Oct 2017 | 33 08th St | Swinerton Builders | erect 19 stories, 6 basement with residential & commercial building.Details
erect 19 stories, 6 basement with residential & commercial building. | $133,333,000 |
| Aug 8, 2012 | Completed final sign-off Mar 2014 | 4 25th North Av | revise application 201106027312 s1 to allow shotcrete placement vs cast in place concrete. (revise information as shown in special inspection and structural observation form)Details
revise application 201106027312 s1 to allow shotcrete placement vs cast in place concrete. (revise information as shown in special inspection and structural observation form) | ||
| Jun 9, 2011 | Completed final sign-off Nov 2012 | 2754 Vallejo St | 1 story addition at rear on grade(bsmt level only).fill in recessed exterior stair at rear of bldg from 1/fl to grade.new bay window at 2/fl living room. new windows at side of the bldg.the new side windows are not visible from front.Details
1 story addition at rear on grade(bsmt level only).fill in recessed exterior stair at rear of bldg from 1/fl to grade.new bay window at 2/fl living room. new windows at side of the bldg.the new side windows are not visible from front. | $150,000 | |
| Jun 2, 2011 | Completed final sign-off Mar 2014 | 4 25th North Av | horizontal extension @ basement level only. deck on top of extension. at 1st floor, enclose (e) terrace / patio with glass walls & glass roof.Details
horizontal extension @ basement level only. deck on top of extension. at 1st floor, enclose (e) terrace / patio with glass walls & glass roof. | $150,000 | |
| Mar 25, 2010 | Completed final sign-off May 2010 | 340 Kansas St | Pk International | title-24 documentation to be included in separate permit as described in issued permit #2009/1007/8517.Details
title-24 documentation to be included in separate permit as described in issued permit #2009/1007/8517. | $5,000 |
| Jul 20, 2009 | Completed final sign-off Jun 2014 | 40 Edgehill Wy | Versaggi Construction, Canyon Construction | new construction of a three-story over basemensingle family building.Details
new construction of a three-story over basemensingle family building. | $1,100,000 |
| Dec 8, 2008 | Expired or cancelled cancelled Jan 2026 | 1035 Filbert St | Mayta & Jensen | install one new fixed fire rated single pane window 2'6"x5'8" and match exterior & interior window trims @ east side of building.Details
install one new fixed fire rated single pane window 2'6"x5'8" and match exterior & interior window trims @ east side of building. | $7,500 |
| Feb 9, 2005 | Expired or cancelled expired Dec 2007 | 2160 Green St | J M K Construction Inc | return the (e)bldg as a single family home by eliminating the basement group use (planning code sectDetails
return the (e)bldg as a single family home by eliminating the basement group use (planning code sect | $30,000 |
| Feb 9, 2005 | Expired or cancelled expired Dec 2007 | 2160 Green St | J M K Construction Inc | remove exterior stairs & deck, brick chimney and fluies on roof, and other minor interior & exteriorDetails
remove exterior stairs & deck, brick chimney and fluies on roof, and other minor interior & exterior | $400,000 |