Mark Edward Bartos
- License
- C24138
- Architect
- About the California Architects Board
- Look the license up with the state (Architects Board)
- Listed as
- architect
- Firm
- Bartos Architecture
- Based in
- San Mateo
- On San Francisco permits
- Sep 2016 to Apr 2021
2 permits since 2000 (architect on 2 permits): 1 completed, 1 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. The discipline is read from the letters before the number, as the Board for Professional Engineers, Land Surveyors, and Geologists lists them (its license types, read Oct 16, 2026), and for a C number from whether the permits list the license as an architect or as an engineer. How to read these records
Worked with
Every other licensed party on the same permits, by the role the city lists them under, with how many of those permits each is on.
- Contractors
- Chinchilla Construction Administration, Silver Arrows Paint Restoration
- Engineers
- Stanley Wu
Where they worked
- Single-family 0
- Multi-family (2-family, apartments) 1
- Commercial 0
- Other or unknown 1
One dot per permit, coloured by the building type the city or the assessor gives it. A dark circle is several permits close together: click it to zoom in.
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Apr 23, 2021 | Never finaled filed Apr 2021, never issued | 100 Whitney Young Cr | Chinchilla Construction Administration | remodel(e)classrooms.accessibility upgrades to restroom and walkways and change of occupancy from r3 to e.alteration to restroom for accessibility requirements.including demolition of partitions,adjustment of fixture heights & location.installation of truncated dome ramp to existing parking ramp.Details
remodel(e)classrooms.accessibility upgrades to restroom and walkways and change of occupancy from r3 to e.alteration to restroom for accessibility requirements.including demolition of partitions,adjustment of fixture heights & location.installation of truncated dome ramp to existing parking ramp. | $50,000 |
| Sep 20, 2016 | Completed final sign-off Nov 2016 | 338 Main St | Silver Arrows Paint Restoration | tower d - unit #11c: reconfiguration of master bathroom to add a powder room with one toilet and one sink. will install one exaust fan, 2 light receptacles, 2 outlets, 1 fire sprinkler and reconfigure walls. n/a for maher.Details
tower d - unit #11c: reconfiguration of master bathroom to add a powder room with one toilet and one sink. will install one exaust fan, 2 light receptacles, 2 outlets, 1 fire sprinkler and reconfigure walls. n/a for maher. | $19,000 |