Oscar I. Amador-Cabello
- Listed as
- authorized agent-others, contractor
- Firm
- Amador General Construction Inc
- Based in
- South San Francisco
- On San Francisco permits
- Sep 2017 to Aug 2026
32 permits since 2000 (contractor on 32 permits, authorized agent-others on 3 permits): 19 completed, 11 in progress, 2 never finaled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. Their ranked record as a contractor is on their contractor page. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Aug 3, 2026 | In progress issued Sep 2026 | 261 Waller St | Amador General Construction Inc | revision to 202509125177. new deck rails, add concrete to the left side of the property.Details
revision to 202509125177. new deck rails, add concrete to the left side of the property. | $10,000 |
| Apr 21, 2026 | In progress issued Apr 2026 | 300 Beale St | Amador General Construction Inc | unit 202: replace kitchen cabinets, countertops, sink & fixture.Details
unit 202: replace kitchen cabinets, countertops, sink & fixture. | $5,000 |
| Apr 17, 2026 | In progress issued May 2026 | 515 29th St | Amador General Construction Inc | at 2nd floor, remodel (e) kitchenDetails
at 2nd floor, remodel (e) kitchen | $25,000 |
| Apr 16, 2026 | In progress issued Apr 2026 | 4150 17th St | Amador General Construction Inc | interior remodel of kitchen and two bathrooms; no changes to the interior walls. all windows being replaced. electrical & plumbing modifications. no mechanical changes proposed.Details
interior remodel of kitchen and two bathrooms; no changes to the interior walls. all windows being replaced. electrical & plumbing modifications. no mechanical changes proposed. | $20,000 |
| Nov 18, 2025 | In progress issued Jan 2026 | 116 Delmar St | Amador General Construction Inc | revision to pa # 2025-0825-3833. reconfiguration of approved 3rd fl bathroom. addition of an indoor sauna space and a storage/equipment room. no plumbing fixture increase.Details
revision to pa # 2025-0825-3833. reconfiguration of approved 3rd fl bathroom. addition of an indoor sauna space and a storage/equipment room. no plumbing fixture increase. | $15,000 |
| Sep 12, 2025 | In progress issued Oct 2025 | 261 Waller St | Amador General Construction Inc | install interior staircase. lower level buildout bathroom, bedroom, laundry room and flex space. add exterior deck upstairs. add new skylights.Details
install interior staircase. lower level buildout bathroom, bedroom, laundry room and flex space. add exterior deck upstairs. add new skylights. | $100,000 |
| Aug 25, 2025 | In progress issued Aug 2025 | 116 Delmar St | Amador General Construction Inc | interior remodel of e 2 story over basement, partial attic conversion including 1 library space, 1 finished attic space and 1 bath. all e windows to remain. 1 new window at 1st fl back kitchen, 1 new slider in at attic conversion to roof deck, 2 new skylights. e ext finishes remain. roof sep permit.Details
interior remodel of e 2 story over basement, partial attic conversion including 1 library space, 1 finished attic space and 1 bath. all e windows to remain. 1 new window at 1st fl back kitchen, 1 new slider in at attic conversion to roof deck, 2 new skylights. e ext finishes remain. roof sep permit. | $600,000 |
| Aug 4, 2025 | In progress issued Aug 2025 | 847 Haight St | Amador General Construction Inc | revision to pa# 202504043766, foundation from (e) brick to new concrete.Details
revision to pa# 202504043766, foundation from (e) brick to new concrete. | $30,000 |
| May 16, 2025 | In progress issued Feb 2026 | 2839 24th St | Amador General Construction Inc | commencement of work not started pa# 202002285777.Details
commencement of work not started pa# 202002285777. | |
| Oct 21, 2024 | Completed final sign-off Apr 2025 | 160 Pierce St | Amador General Construction Inc | replace under 50% dry rot repair's in front staircase/landing.Details
replace under 50% dry rot repair's in front staircase/landing. | $5,000 |
| Jun 20, 2024 | In progress issued Apr 2025 | 2101 Turk Bl | Amador General Construction Inc | remodel (e) home owner office to (n) adu, per ca state law, government code section 65852.2. (n) unit(2101a) included bedroom. bathroom and kitchen. (n) adu is built within (e) building footprint; increase dwelling unit count from 3 to 4, dmj 05/31/2024;Details
remodel (e) home owner office to (n) adu, per ca state law, government code section 65852.2. (n) unit(2101a) included bedroom. bathroom and kitchen. (n) adu is built within (e) building footprint; increase dwelling unit count from 3 to 4, dmj 05/31/2024; | $65,000 |
| Jan 31, 2024 | In progress issued Jan 2024 | 2101 Turk Bl | Amador General Construction Inc | reference to permit 202305188054. less than 50% of dry rot repair. new additional work remove 25x12 torch roof patio. remove sub-floor plywood = repair less than 50% primary dry rot. replace 25'x13' of stucco. all work same side of wall. all work at the back of building.Details
reference to permit 202305188054. less than 50% of dry rot repair. new additional work remove 25x12 torch roof patio. remove sub-floor plywood = repair less than 50% primary dry rot. replace 25'x13' of stucco. all work same side of wall. all work at the back of building. | $20,000 |
| Dec 19, 2023 | Completed final sign-off May 2024 | 2826 Gough St | Amador General Construction Inc | remove entire ceiling from unit-repair in kind. install new insulattion, install new sheetrock, paint entire unit, kitchen remodel, same layout of cabinets will be installedDetails
remove entire ceiling from unit-repair in kind. install new insulattion, install new sheetrock, paint entire unit, kitchen remodel, same layout of cabinets will be installed | $5,000 |
| Nov 15, 2023 | Completed final sign-off Dec 2024 | 67 Saturn St | Amador General Construction Inc | install (6) new construction windows backside of house. install new 2x trim around new windows.Details
install (6) new construction windows backside of house. install new 2x trim around new windows. | $5,000 |
| Nov 15, 2023 | Completed final sign-off Dec 2024 | 65 Saturn St | Amador General Construction Inc | install (5) new construction windows - backside of house. install new 2x trim around windows.Details
install (5) new construction windows - backside of house. install new 2x trim around windows. | $5,000 |
| Jun 28, 2023 | Completed final sign-off Dec 2025 | 2765 Filbert St | Amador General Construction Inc | remodel kitchen, 2 bathrooms & interior space.Details
remodel kitchen, 2 bathrooms & interior space. | $250,000 |
| May 18, 2023 | Never finaled issued May 2023, no final | 2101 Turk Bl | Amador General Construction Inc | remove existing siding 30w x 40h, western side of building, paint all new siding & trim. not visible from the street. all work is non structural only.Details
remove existing siding 30w x 40h, western side of building, paint all new siding & trim. not visible from the street. all work is non structural only. | $20,000 |
| Feb 16, 2023 | Completed final sign-off May 2024 | 2826 Gough St | Amador General Construction Inc | exploritory work to determine the following: orientation size and spacing of ceiling framing at garage level. exisint foundation size and embedded depth at existing grade level. thickness of slab on grade at garage level. front bldg.Details
exploritory work to determine the following: orientation size and spacing of ceiling framing at garage level. exisint foundation size and embedded depth at existing grade level. thickness of slab on grade at garage level. front bldg. | $3,000 |
| Sep 30, 2022 | Completed final sign-off May 2023 | 1301 Clay St | Amador General Construction Inc | demo kitchen sheetrock needed to move same utlities. install new kitchen cabinets. add few more dedicated circuits and move gas line about 3' in same wall. casework replacement in kind.Details
demo kitchen sheetrock needed to move same utlities. install new kitchen cabinets. add few more dedicated circuits and move gas line about 3' in same wall. casework replacement in kind. | $20,000 |
| Aug 9, 2022 | Completed final sign-off Aug 2023 | 85 San Jacinto Wy | Amador General Construction Inc | kitchen and 3 bath remodel. remodel washer dryer room. new sub panelDetails
kitchen and 3 bath remodel. remodel washer dryer room. new sub panel | $68,000 |
| Aug 9, 2022 | Completed final sign-off May 2023 | 663 Shotwell St | Amador General Construction Inc | kitchen remodel: new subpanel, move gas/water lines, install cabinetsDetails
kitchen remodel: new subpanel, move gas/water lines, install cabinets | $20,000 |
| Mar 29, 2022 | Completed final sign-off Jul 2022 | 2101 Turk Bl | Amador General Construction Inc | replace 25' x 30' of siding, same as (4), @ east side of building visible from street.Details
replace 25' x 30' of siding, same as (4), @ east side of building visible from street. | $15,000 |
| Sep 3, 2021 | Completed final sign-off Nov 2023 | 126 Noe St | Amador General Construction Inc | remodel extg bathroom into 2 new bathrooms. remodel extg family room.Details
remodel extg bathroom into 2 new bathrooms. remodel extg family room. | $30,000 |
| Jun 14, 2021 | Completed final sign-off Apr 2022 | 5 Elsie St | Amador General Construction Inc | kitchen remodel. replace cabinets, floor, move kitchen sink lines. reroute electrical for new design, new subpanel in garageDetails
kitchen remodel. replace cabinets, floor, move kitchen sink lines. reroute electrical for new design, new subpanel in garage | $25,000 |
| Apr 9, 2021 | Completed final sign-off Dec 2023 | 2441 Folsom St | Amador General Construction Inc | addition of dwelling unit - converion of ground floor/basement habitable social space to residential dwelling unit. fire sprinklers(under separate permit), addition of kitchen & kitchen island, addition of bedrooom clocset, addition of ductless mini split heating, removal of structural wall.Details
addition of dwelling unit - converion of ground floor/basement habitable social space to residential dwelling unit. fire sprinklers(under separate permit), addition of kitchen & kitchen island, addition of bedrooom clocset, addition of ductless mini split heating, removal of structural wall. | $55,000 |
| Mar 24, 2021 | Completed final sign-off Dec 2023 | 2441 Folsom St | Amador General Construction Inc | replace 12 front street facing aluminum windows with fiberglass windows. 4 center windows replace sliders with fixed/picture windows. 8 side sliders replaced with casement windows.Details
replace 12 front street facing aluminum windows with fiberglass windows. 4 center windows replace sliders with fixed/picture windows. 8 side sliders replaced with casement windows. | $10,000 |
| Mar 15, 2021 | Completed final sign-off Mar 2022 | 2015 Laguna St | Amador General Construction Inc | revision to pa# 201912311090. revise structural details.Details
revision to pa# 201912311090. revise structural details. | $15,000 |
| Jun 15, 2020 | Completed final sign-off Dec 2023 | 2441 Folsom St | Amador General Construction Inc | remodel kitchens, remove/reconfigure interior walls and add structural support, remodel bathrooms, lightwell infill, remove fireplacesDetails
remodel kitchens, remove/reconfigure interior walls and add structural support, remodel bathrooms, lightwell infill, remove fireplaces | $200,000 |
| Dec 31, 2019 | Completed final sign-off Mar 2022 | 2015 Laguna St | Amador General Construction Inc | mandatory seismic upgradeof soft story per ordinance no66-13. soft story ground floor retrofit per a4(75%)Details
mandatory seismic upgradeof soft story per ordinance no66-13. soft story ground floor retrofit per a4(75%) | $23,000 |
| Dec 31, 2019 | Completed final sign-off Feb 2020 | 51 Mars St | Amador General Construction Inc | replace e dryrot wood decking with new decking and dry rot members. no more than 50% of deck; repair inkind.Details
replace e dryrot wood decking with new decking and dry rot members. no more than 50% of deck; repair inkind. | $5,000 |
| Nov 5, 2019 | Completed final sign-off Dec 2019 | 564 08th Av | Amador General Construction Inc | repair existing exterior egress stairs in kind including replace dry-rot wood members, no more than 50%. replace entire first flight of stair in kind @ first floor due to dry-rot.Details
repair existing exterior egress stairs in kind including replace dry-rot wood members, no more than 50%. replace entire first flight of stair in kind @ first floor due to dry-rot. | $5,000 |
| Sep 18, 2017 | Never finaled issued Mar 2020, no final | 816 Ashbury St | Amador General Construction Inc | soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4Details
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a-4 | $65,000 |