16 permits since 2000 (engineer on 14 permits, architect on 2 permits): 10 completed, 1 in progress, 3 never finaled, 2 expired or cancelled.
This is the city’s permit record, not a license check: the role and the number come from what was written on each permit (the number spelled one way). It does not show whether the license is current. How to read these records
Most recent permits
| Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
|---|---|---|---|---|---|
| Dec 28, 2022 | In progress issued Aug 2025 | 384 Holladay Av | Concannon Construction Inc | erect a new 3-story over 1-basement, type vb, single family dwelling on vacant lot. includes 4 bedrooms, 3.5 baths, 2 car garage, home office, laundry rm, and occupied roof terraces at levels 2 and 3.Details
erect a new 3-story over 1-basement, type vb, single family dwelling on vacant lot. includes 4 bedrooms, 3.5 baths, 2 car garage, home office, laundry rm, and occupied roof terraces at levels 2 and 3. | $594,000 |
| Aug 3, 2021 | Completed final sign-off Aug 2021 | 312 West Portal Av | Ewsf Inc. | revision 202101263275 move bathroom, add sheetock to scope, add kitchen cabinet, add plywood, add roomsDetails
revision 202101263275 move bathroom, add sheetock to scope, add kitchen cabinet, add plywood, add rooms | $10,000 |
| Jan 26, 2021 | Completed final sign-off Aug 2021 | 312 West Portal Av | Ewsf Inc. | lighting upgrade. bathroom relocation & upgrade to meet disabled access 20% rule.Details
lighting upgrade. bathroom relocation & upgrade to meet disabled access 20% rule. | $30,000 |
| Oct 7, 2019 | Completed final sign-off Dec 2019 | 1163 South Van Ness Av | Adept Construction Solution Inc | revision for pa# 2019-0711-5670. hold downs and shear walls embedments for future seismic retrofit. embedments are installed for future possible hold downs and hss posts. no additional work. no review for structural value.Details
revision for pa# 2019-0711-5670. hold downs and shear walls embedments for future seismic retrofit. embedments are installed for future possible hold downs and hss posts. no additional work. no review for structural value. | |
| Jul 11, 2019 | Completed final sign-off Apr 2022 | 1163 South Van Ness Av | Adept Construction Solution Inc | sectional removal and replace (e) brick foundation w/mat slab & retaining walls. replace (e) wood posts & install new anchor bolts & holddowns for future seismic retrofit of wood framed structure. replace sewer/ water lines as needed. upgrade gas,ele panels now work above basement-under sep permitDetails
sectional removal and replace (e) brick foundation w/mat slab & retaining walls. replace (e) wood posts & install new anchor bolts & holddowns for future seismic retrofit of wood framed structure. replace sewer/ water lines as needed. upgrade gas,ele panels now work above basement-under sep permit | $110,500 |
| Feb 1, 2019 | Never finaled issued Sep 2023, no final | 129 Edgehill Wy | A B J Construction | to erect 4 stories, 1 basement, type v-a, single family building.Details
to erect 4 stories, 1 basement, type v-a, single family building. | $875,000 |
| Jan 5, 2018 | Completed final sign-off Feb 2022 | 4 Aquavista Wy | J Reilly Construction | horizontal and vertical addition. no excavation or foundation added. add (n) garage @ 1st flr. total 2.5 baths & 2 beds will be added. add wood roof deck. ref pa# 201704123783Details
horizontal and vertical addition. no excavation or foundation added. add (n) garage @ 1st flr. total 2.5 baths & 2 beds will be added. add wood roof deck. ref pa# 201704123783 | $475,000 |
| Aug 1, 2017 | Expired or cancelled expired Oct 2021 | 2018 Webster St | Evra Construction, Abbeyside Construction Inc | temporary shoring for approved remodel and addition per app#201409156303Details
temporary shoring for approved remodel and addition per app#201409156303 | $75,000 |
| May 10, 2017 | Completed final sign-off Oct 2017 | 3900 24th St | Arcon Construction Corp | repair of the dryrot & foundation brick replacement with concrete on the west side along property line @ crawl space.Details
repair of the dryrot & foundation brick replacement with concrete on the west side along property line @ crawl space. | $8,000 |
| May 2, 2017 | Never finaled issued May 2017, no final | 2201 Chestnut St | Adept Construction Solution Inc | repairs to (e) water discharge system below grade in basement. replace 3 sump pump. install apprx 70 linear ft of drain pipes under (e) slab patch slab concrete. hook-up sump pump to (e) plumbing.Details
repairs to (e) water discharge system below grade in basement. replace 3 sump pump. install apprx 70 linear ft of drain pipes under (e) slab patch slab concrete. hook-up sump pump to (e) plumbing. | $18,500 |
| Oct 25, 2016 | Never finaled issued Nov 2016, no final | 353 10th St | Ewsf Inc. | accessibility/exit upgrade for existing cafe, office, & manufacturing space. n/a maher ordinanceDetails
accessibility/exit upgrade for existing cafe, office, & manufacturing space. n/a maher ordinance | $120,000 |
| Aug 24, 2016 | Completed final sign-off May 2017 | 5637 Geary Bl | Adept Construction Solution Inc | t.i. at (e) 2 spaces, combine into single space/usage, remodel (2) existing toilets, add ada restroom, remove middle partition wall & add (2) drop beams, upgrade electrical and plumbing, (n) drywall, repair storefront, replace (e) ada entry.Details
t.i. at (e) 2 spaces, combine into single space/usage, remodel (2) existing toilets, add ada restroom, remove middle partition wall & add (2) drop beams, upgrade electrical and plumbing, (n) drywall, repair storefront, replace (e) ada entry. | $35,000 |
| Feb 4, 2016 | Expired or cancelled cancelled Jan 2026 | 3301 Lyon St | Clay Hill Construction | add ada compliant counter to cafe within the larger property (palace o f fine arts). add security shutter replace 3 comp sink and water heater. maner naDetails
add ada compliant counter to cafe within the larger property (palace o f fine arts). add security shutter replace 3 comp sink and water heater. maner na | $11,000 |
| Nov 5, 2015 | Completed final sign-off Mar 2016 | 430 Shotwell St | Ewsf Inc. | revision to pa #201509015839 - reconfigure & relocate the accessible restroom & lunch room & stairs, upgrade mezzanine floor. n/a maher ordinance.Details
revision to pa #201509015839 - reconfigure & relocate the accessible restroom & lunch room & stairs, upgrade mezzanine floor. n/a maher ordinance. | $50,000 |
| Apr 25, 2008 | Completed final sign-off May 2008 | 2076 16th Av | repair garage framing, less than 15% sill plates, splite lumber.Details
repair garage framing, less than 15% sill plates, splite lumber. | $3,500 | |
| Aug 23, 2005 | Completed final sign-off Nov 2005 | 2076 16th Av | new 56"x54" glass block window (1 hr rated window assembly).Details