Permit 202509266186
121 Spear St
floors 2, 5, 6 offices: install new bevi water dispensing unit at existing breakroom, including minor plumbing and case work modification.
- Outcome
- Completed (city status: complete, Dec 16, 2025)
- Filed
- Sep 26, 2025
- Permit issued
- Oct 1, 2025
- Final sign-off
- Dec 16, 2025
- Declared cost
- $28,526
- Building use
- office
- Neighborhood
- Financial District/South Beach
- Contractor
- Cobe Construction Inc (license 835122)
- Property
- All permits at this address (block 3716, lot 021)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Cobe Construction Inc (license 835122)
- Architect
- Julia Seen, Studio G Architects (license C29927)
- Authorized agent-others
- Garrett Miller, Cobe Construction (no license listed), applicant