Permit 202509175461

375 Laguna Honda Bl

at&t modificiation of an (e) wireless facility consisting of: lower 3 & add 3 antennas; r/r 3 rrus; remove 1 power plant; 13 rectifiers; install (1) netsure power plant; (9) 58v converters, (12) 48v rectifiers; (1)g4 bbu, (a) 15a, (3) 30a dc breakers; rf safety signage stripping & barricades

Outcome
Completed (city status: complete, Jul 2, 2026)
Filed
Sep 17, 2025
Permit issued
Mar 4, 2026
Final sign-off
Jul 2, 2026
Declared cost
$83,700
Building use
office
Neighborhood
Twin Peaks
Contractor
Metropolitan Electrical Construction (license 401047)
Property
All permits at this address (block 2842, lot 007)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Metropolitan Electrical Construction (license 401047)
Engineer
Adam Amortnont (license 81495)
Authorized agent-others